This document provides a fluid handling plan for tank inspections aboard a 210-foot Coast Guard cutter. The plan details stability criteria to be followed during inspections and lists tanks to be inspected over two separate 96-month periods. It describes recommended tank conditions upon vessel arrival and provides fluid handling procedures to maintain stability for each round of inspections. Tanks will be emptied, filled, and inspected according to a set sequence. Diesel oil will be transferred between tanks as necessary. The plan aims to allow all tank inspections while avoiding added costs through judicious fluid management. Operators are advised to adjust loadings as needed to limit list and trim.

View the file

Other files for this federal contract opportunity

Other files attached to Dock-Side (DS): USCGC VALIANT DOCKSIDE Repairs FY21, newest first.
File Type Posted
CGC VALIANT Dockside Repairs FY21 Award Notice.pdf PDF
VALIANT Amendment of Solicitation A0003 P4502000 SIGNED.pdf PDF
A00002 page 2 VALIANT DS Repairs P4502000.pdf PDF
VALIANT Amendment of Solicitation A0002 P4502000.pdf PDF
General_Security_Guidance.pdf PDF
A00001 page 2 VALIANT DS Repairs P4502000.pdf PDF
VALIANT Amendment of Solicitation A0001 P4502000.pdf PDF
Alpha Wharf Berth A-1.pdf PDF
Mayport_Naval_Base_ Vendor Access Form.doc DOC document
Valiant DS P450200 SPECS.pdf PDF
SOSS Valiant FY21 DS P450200 .xls XLS spreadsheet
Valiant DS P450200 Solicitation.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

210B_WMEC_0220

210’ WMEC B CLASS FLUID

HANDLING PLAN FOR TANK

INSPECTIONS

D-123-2046

210’ WMEC B CLASS

FLUID HANDLING PLAN FOR TANK INSPECTIONS

INTRODUCTION

This fluid handling plan facilitates tank inspections of the 210’ WMEC B Class while maintaining acceptable stability. It documents the stability criteria that is used, lists the tanks and periods of inspection, recommends tank conditions upon arrival, and then describes the fluid handling plans for DS2-A and DS2-B availabilities.

The second to last page presents a table depicting the tank conditions at the various steps and the last page can be used to quickly determine which tanks are to be inspected during either of the two availabilities.

TABLE OF CONTENTS

Introduction

Stability Criteria During Tank Inspections

210’ WMEC B Class Tank Inspection Periods

Tank Conditions Upon Arrival

Fluid Handling for DS2-A Availability

Fluid Handling for DS2-B Availability

Final Note

TABLE 1: Depiction of Tank Conditions at Various Steps

TABLE 2: Tanks to be Inspected During DS2-A and DS2-B Availabilities

STABILITY CRITERIA DURING TANK INSPECTIONS

The intact stability criteria are IAW U.S. Navy Design Data Sheet, DDS 079-1 (1975), modified as follows:

Beam winds - 60 knots

Rollback Angle - 20 degrees.

The damage stability criteria are IAW DDS 079-1 (1975), modified as follows:

Maximum Heel - 20 degrees

Margin Line Immersion Allowed.

Cosine reduction to Righting Arms – 0.04Cosine(theta)

Rollback Angle - 80% of the DDS 079-1 value.

Because the above criteria differ from that used by the cutter’s FCCS Database, Operators should not use FCCS to evaluate the stability during the tank inspection period.

210’ WMEC B CLASS TANK INSPECTION PERIODS

There will be two Availabilities over 96 months, DS2-A and DS2-B, that will result in all of the tanks being inspected. Some tanks are inspected each availability; others are inspected only once. The following tank inspection periods apply:

Tanks Having an Inspection Period of 48 Months:

4-143-1-F DIESEL OIL SERVICE

4-143-2-F DIESEL OIL SERVICE

4-96-3-F DIRTY OIL

4-143-0-F OWS DIRTY OIL

4-164-1-J JP-5 SERVICE

4-172-0-W POTABLE WATER

4-174-1-W POTABLE WATER

4-174-2-W POTABLE WATER

4-FP-0-W PEAK TANK

4-62-0-F DIESEL OIL/SALT WATER BALLAST

3-84-0-W SEWAGE

3-84-1-W SEWAGE

Tanks Having an Inspection Period of 96 Months:

4-72-1-F DIESEL OIL/SALT WATER BALLAST

4-72-2-F DIESEL OIL/SALT WATER BALLAST

4-72-3-F DIESEL OIL/SALT WATER BALLAST

4-72-4-F DIESEL OIL/SALT WATER BALLAST

4-84-1-F DIESEL OIL/SALT WATER BALLAST

4-84-2-F DIESEL OIL/SALT WATER BALLAST

4-96-4-F DIESEL OIL/SALT WATER BALLAST

4-96-5-F DIESEL OIL/SALT WATER BALLAST

4-96-1-F DIESEL OIL OVERFLOW

4-96-2-F LUBE OIL

4-191-1-F LUBE OIL

4-191-2-F LUBE OIL

4-164-2-J JP-5 STORAGE

4-164-3-J JP-5 STORAGE

TANK CONDITIONS UPON ARRIVAL

When the cutter arrives in port the tanks should be loaded in a manner that allows tank inspections and avoids added costs.

Diesel Oil Tanks: The cutter should arrive with the total diesel oil aboard at 70% of the full load amount, which corresponds to 105.2 LT. The 70% loading occurs when the cutter is in Step (c) of the liquid loading instructions (described on DCB Page II(a)6) having the Diesel Oil Service Tanks 4-143-1 & 2-F at 75% , the

DO in 4-62-0-F consumed, and with 4-72-3 &4-F at 41% of capacity. [If DO Overflow Tank 4-96-1-F is not empty the DO that is in it should be transferred into 4-72-3 & 4-F prior to arrival.] If the cutter arrives with more than 111 LT of DO for the DS2-A availability or more than 108 LT for the DS2-B availability the amount in excess of 105.2 LT should be offloaded.

Ballast Tanks: Per the Damage Control Book liquid loading instructions, the 210’ WMEC B Class upon arrival with 70% fuel aboard, would have the Peak Tank (4-FP-0-W) loaded to 67% capacity and emptied DO Storage

Tank 4-62-0-F pressed full with Salt Water Ballast. Prior to arrival both of these tanks (4-FP-0-W and 4-62-0-

F) should be emptied.

Fresh Water Tanks: The centerline fresh water tank (4-172-0-W) must be pressed full to prevent a potentially large free surface. The port and starboard fresh water tanks (4-174-1 & 2-W) can be at any loading upon arrival.

JP-5, Lube Oil, Dirty Oil, & Sewage Tanks: These tanks can be at any loading at arrival.

FLUID HANDLING FOR DS2-A AVAILABILITY

The following guidance will maintain acceptable stability, trim, and list during the tank inspection period of the

DS2-A availability. Operators should adjust loadings aboard when necessary to prevent the list from exceeding approximately one degree, and/or to prevent trim from exceeding approximately 1 foot by the bow or 2 feet by the stern.

The following discussion assumes that the ship arrives during Step (c) of the liquid loading instructions with

70% of the full load amount of diesel oil aboard as described previously (TANK CONDITIONS UPON

ARRIVAL). During the DS2-A availability the DO will be transferred between tanks two different times. It will also be necessary to empty all of the non-DO tanks to allow their inspections; plus to fill the JP-5 and Lube

Oil tanks when specified in order to maintain acceptable stability. The tank loadings during each of a total of four rounds of tank inspections during this availability are described below and are depicted in the table on the second to last page.

ROUND 1a (DS2-A)

The following Diesel Oil and Ballast tanks are empty upon arrival and are to be inspected in the first of four rounds of tank inspection during the DS2-A availability. The two tanks that the DCB liquid loading instructions have loaded with ballast water prior to arrival (4-FP-0-W and emptied DO Tank 4-62-0-F) should be emptied prior to arrival.

Round 1a Inspections:

4-62-0-F DO Storage

4-96-1-F DO Overflow

4-FP-0-W Peak Tank

ROUND 2a (DS2-A)

After the Round 1a tank inspections are complete:

JP-5 Tanks - Empty the JP-5 Storage (4-164-2 & 3-J) and Service (4-164-1-J) Tanks

Fresh Water, Lube Oil, Sewage, and Dirty Oil Tanks - Empty the Fresh Water (4-172-0-W and 4-174-1 & 2-

W), Lube Oil (4-96-2-F and 4-191-1 & 2-F), Sewage (3-84-0-W and 3-84-1-W), Dirty Oil (4-96-3-F), and

OWS Dirty Oil (4-143-0-F).

After the Round 2a tank loading adjustments have been completed inspect the following tanks.

Round 2a Inspections:

4-164-2 & 3-J JP-5 Storage 4-

164-1-J JP-5 Service

4-172-0-W Fresh Water

4-174-1 & 2-W Fresh Water

4-96-2-F Lube Oil

4-191-1 & 2-F Lube Oil

3-84-0-W Sewage

3-84-1-W Sewage

4-96-3-F Dirty Oil

4-143-0-F OWS Dirty Oil

ROUND 3a (DS2-A)

After the Round 2a tank inspections are complete:

JP-5 Tanks - Fill the JP-5 Storage (4-164-2 & 3-J) and JP-5 Service (4-164-1-J) tanks to 95% capacity;

EXCEPT, if filling the tanks will result in the list exceeding one degree do not completely fill the JP-5 storage tank on that side. This is necessary in order to maintain acceptable damage stability.

Lube Oil Tanks - Fill the Lube Oil Storage (4-96-2-F, 4-191-1-F , and 4-191-2-F) to 95% capacity. This is necessary in order to maintain acceptable damage stability.

Diesel Oil Tanks - After the JP-5 and Lube Oil tanks are filled, transfer diesel oil from 4-143-1 & 2-F (Service) into 4-72-3 & 4-F until full and then into 4-62-0-F. The Diesel Oil Service Tanks (4-143-1 & 2-F) are now empty.

After the Round 3a tank loading adjustments have been completed inspect the following tanks.

Round 3a Inspections:

4-143-1 & 2-F DO Service

ROUND 4a (DS2-A)

After the Round 3a tank inspections are compete:

Diesel Oil Tanks - Transfer fuel from 4-72-3 & 4-F into 4-143-1 & 2-F (Service). This empties Diesel Oil

Tanks 4-72-3 & 4-F.

After the Round 4a tank loading adjustments have been completed inspect the following tanks.

Round 4a Inspections:

4-72-3 & 4-F Diesel Oil Tanks

Completion of DS2-A Availability

The above completes the tank inspections of the DS2-A availability. The diesel oil tanks should then be loaded to either the Full Load amount or a lesser amount consistent with the fuel consumption sequence of the liquid loading instructions.

FLUID HANDLING FOR DS2-B AVAILABILITY

The following guidance will maintain acceptable stability (except as described in the following discussion), trim and list during the tank inspection period of the DS2-B availability. Operators should adjust loadings aboard when necessary to prevent the list from exceeding approximately one degree, and/or to prevent trim from exceeding approximately 1 foot by the bow or 2 feet by the stern.

The following discussion assumes that the ship arrives during Step (c) of the liquid loading instructions with

70% of the full load amount of fuel aboard as described previously (TANK CONDITIONS UPON ARRIVAL).

See the table provided on the second to last page for a depiction of the tank loadings at various steps of the fluid handling plan.

ROUND 1b (DS2-B)

JP-5 Tanks - To provide needed improvement of the cutter’s stability for the first and subsequent rounds of tank inspections, fill the JP-5 storage tanks (4-164-2 & 3-J) to 95% before beginning the DO transfers for

Round 1b. The JP-5 Storage Tanks will not be inspected during the DS2-B availability.

The JP-5 Service (4-164-1-J) Tank should be pumped empty before beginning the tank inspections of Round

1b; however, it is not inspected until a later round.

Lube Oil Tanks - To provide needed improvement of the cutter’s stability for the first and subsequent rounds of tank inspections, fill the Lube Oil storage tanks (4-96-2-F, 4-191-1 & 2-F) to 95% before beginning the DO transfers for Round 1b. The Lube Oil Storage Tanks will not be inspected during the DS2-B availability.

Diesel Oil Tanks - After the JP-5 and LO storage tanks have been filled, transfer the DO in the Service Tanks

(4-143-1 & 2-F) into 4-72-3 & 4-F until full and then into 4-62-0-F.This empties the DO Service Tanks (4-143-

1 & 2-F).

Fresh Water, and Dirty Oil Tanks - Empty the Fresh Water (4-172-0-W and 4-174-1 & 2-W), Dirty Oil (4-96-

3-F), and OWS Dirty Oil (4-143-0-F) before beginning the tank inspections of Round1b; however, these tanks are not inspected until a later round.

After the Round 1b tank loading adjustments have been completed inspect the following tanks.

Round 1b Inspections:

4-143-1 & 2-F DO Service Tanks

ROUND 2b (DS2-B)

After the Round 1b tank inspections are complete:

Diesel Oil Tanks - Transfer fuel from 4-96-4 & 5-F into 4-143-1 & 2-F (Service) until full, and then into 4-62-

0-F.This empties Diesel Oil Storage tanks 4-96-4 & 5-F. These are the only tanks to be inspected during

Round 2b.

During this round the damage stability criteria for reserve dynamic stability criteria (A1/A2 >1.4) is satisfied but the stability criteria that limits the heel to 20 degrees is exceeded by 1 degree for the worst case of flooding.

It is recommended that the next fuel transfer step be started as soon as practical after 4-96-4 & 5-F are inspected. The damage stability for the Round 3b loading condition is much better.

After the Round 2b tank loading adjustments are completed inspect the following tanks.

Round 2b Inspections:

4-96-4 & 5-F DO Storage tanks

ROUND 3b (DS2-B)

After the Round 2b tank inspections are complete:

Diesel Oil Tanks - Transfer fuel from 4-62-0-F, 4-72-1 & 2-F and 4-84-1 & 2-F into 4-96-4 & 5-F. This empties 4-62-0-F, 4-72-1 & 2-F and 4-84-1 & 2-F.

After the Round 3b tank loading adjustments have been completed inspect the following tanks.

Round 3b Inspections:

4-62-0-F DO Storage

4-72-1 & 2-F DO Storage 4-

84-1 & 2-F DO Storage 4-FP-

0-W Peak Tank

4-164-1-J JP-5 Service

4-172-0-W Fresh Water

4-174-1 & 2-W Fresh Water

4-96-3-F Dirty Oil

4-143-0-F OWS Dirty Oil

Completion of DS2-A Availability

The above completes the tank inspections of the DS2-B availability. When completed the diesel oil tanks should be loaded to either the Full Load amount or a lesser amount consistent with the fuel consumption sequence of the liquid loading instructions.

FINAL NOTE

Operators with questions about stability or this Fluid Handling Plan should contact MECPL Naval

Architect.

210' WMEC B CLASS FLUID HANDLING PLAN FOR TANK INSPECTIONS

1. The cutter arrives for each availability with SW Ballast tanks empty and Fuel Oil loaded in accordance with the DCB Part II(a) liquid loading instructions; with the total Fuel aboard equal to 70% of the full load amount.

2. Diesel Oil is to be transferred between tanks and the Fresh Water, JP-5, JP-5 Service, Lube Oil, Dirty Oil, and Sewage Tanks are to be emptied and/or filled as specified in this Plan and illustrated below.

3. The tanks that are to be inspected during each round of inspections are indicated by a box labeled "EMPTY".

DS2-A

AVAILABILITY

DS2-B

AVAILABILITY

ROUND 1a

ARRIVAL FOR BOTH

AVAILABILITIES

ROUND 2a

ROUND 3a

ROUND 4a

ROUND 1b

ROUND 2b

ROUND 3b

DO STORAGE/SWB :

4-62-0-F EMPTY Empty Slack Slack Slack Slack EMPTY

4-72-1 & 2-F Full Full Full Full Full Full EMPTY

4-72-3 & 4-F At 41% At 41% Full EMPTY Full Full Full

4-84-1 & 2-F Full Full Full Full Full Full EMPTY

4-96-4 & 5-F Full Full Full Full Full EMPTY Slack

DO SERVICE:

4-143-1 & 2-F At 75% At 75% EMPTY Slack EMPTY Full Full

DO OVERFLOW:

4-96-1-F EMPTY Empty Empty Empty Empty Empty Empty

FRESH WATER

4-172-0-W PRESSED EMPTY Empty Empty Empty Empty EMPTY

4-174-1 & 2-W Full or Slack EMPTY Empty Empty Empty Empty EMPTY

JP-5 STORAGE Full or Slack EMPTY Full Full Full Full Full

JP-5 SERVICE Full or Slack EMPTY Full Full Empty Empty EMPTY

LUBE OIL Full or Slack EMPTY Full Full Full Full Full

PEAK TANK EMPTY Empty Empty Empty Empty Empty EMPTY

DIRTY OIL Slack EMPTY Empty Empty Empty Empty EMPTY

SEWAGE Slack EMPTY Empty Empty Empty Empty Empty

210' WMEC B Class

Tanks to be inspected during DS2-A and DS2-B Availabilities

DS2-A Availability DS2-B Availability

4-62-0-F Diesel Oil Storage 4-62-0-F Diesel Oil Storage

4-72-3-F Diesel Oil Storage 4-72-1-F Diesel Oil Storage

4-72-4-F Diesel Oil Storage 4-72-2-F Diesel Oil Storage 4-84-1-F Diesel Oil Storage 4-84-2-F Diesel Oil Storage 4-96-4-F Diesel Oil Storage 4-96-5-F Diesel Oil Storage

4-143-1-F Diesel Oil Service 4-143-1-F Diesel Oil Service

4-143-2-F Diesel Oil Service 4-143-2-F Diesel Oil Service

4-96-1-F Diesel Oil Overflow

4-96-2-F Lube Oil

4-191-1-F Lube Oil

4-191-2-F Lube Oil

4-164-2-J JP-5 Storage

4-164-3-J JP-5 Storage

4-164-1-J JP-5 Service 4-164-1-J JP-5 Service

4-172-0-W Fresh Water 4-172-0-W Fresh Water

4-174-1-W Fresh Water 4-174-1-W Fresh Water

4-174-2-W Fresh Water 4-174-2-W Fresh Water

4-FP-0-W SW Ballast 4-FP-0-W SW Ballast

4-96-3-F Dirty Oil 4-96-3-F Dirty Oil

4-143-0-F OWS Dirty Oil 4-143-0-F OWS Dirty Oil

3-84-0-W Sewage

3-84-1-W Sewage