A00002 page 2 VALIANT DS Repairs P4502000.pdf

PDF 175 KB Posted

Attached to
Dock-Side (DS): USCGC VALIANT DOCKSIDE Repairs FY21 Federal contract opportunity
Solicitation number
70Z080-21-Q-P4502000
Issued by
Department of Homeland Security US Coast Guard

About this file

This document includes an amendment to a solicitation for dock-side repairs of the USCGC VALIANT. The amendment provides responses to questions from potential offerors. It clarifies that for work items involving tank cleaning, the cutter will have pumped down tanks as much as possible but may still contain residual liquids up to the amounts specified in each work item. Offerors will be responsible for removing all liquids present in the tanks. The period of performance for the repairs is from November 4, 2020 through December 30, 2020. The solicitation is seeking quotes from contractors to perform various repair and maintenance work aboard the cutter during its dockside maintenance period at an unspecified location.

View the file

Other files for this federal contract opportunity

Other files attached to Dock-Side (DS): USCGC VALIANT DOCKSIDE Repairs FY21, newest first.
File Type Posted
CGC VALIANT Dockside Repairs FY21 Award Notice.pdf PDF
D-123-2046 Fluid Handling Plan.pdf PDF
VALIANT Amendment of Solicitation A0003 P4502000 SIGNED.pdf PDF
VALIANT Amendment of Solicitation A0002 P4502000.pdf PDF
General_Security_Guidance.pdf PDF
A00001 page 2 VALIANT DS Repairs P4502000.pdf PDF
VALIANT Amendment of Solicitation A0001 P4502000.pdf PDF
Alpha Wharf Berth A-1.pdf PDF
Mayport_Naval_Base_ Vendor Access Form.doc DOC document
Valiant DS P450200 SPECS.pdf PDF
SOSS Valiant FY21 DS P450200 .xls XLS spreadsheet
Valiant DS P450200 Solicitation.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

70Z080-21-Q-P4502000

VALIANT DOCKSIDE REPAIRS FY21

AMENDMENT A00002

Response to Questions/Requests for Clarification:

Question #1: In reference to Work Item 1, 3, 4, 5 and 7 will the tanks be turned over to the contractor at the low suction amount advertised in the table?

Answer #1: The cutter normally has the tanks pumped down as much as possible, but it is hurricane season, so cutters have to keep a certain amount of fuel onboard, in each one of those work items, it gives to the amount of liquids that the tanks may have in them and the contractor will have to be responsible to remove that amount.

File details come from the government source that posted it. Updated .