REC_51200_FLT_«REC»
WORK ITEM 1: Vent Ducts (Engine And Motor Room All), Commercial Cleaning
RFQ NR 70Z080-19-Q-P45C1700
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the designated shipboard ventilation systems.
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings
Coast Guard Drawing 905 WMEC 512-009, Rev C, Vent 01 Level and Above Fr 103-140 A & D
Coast Guard Drawing 905 WMEC 514-001, Rev F, HVAC System Diagram
Coast Guard Drawing 905 WMEC 514-005, Rev C, HVAC Fan Rooms Main Deck A & D Coast Guard Publications
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean Shipboard Ventilation Systems
Other References
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.3.1 Install filter medium at the terminal ends of all supply vent ducting to prevent any residual foreign mater from blowing into the engine room spaces.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
note
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard personnel perform an initial operational test of the ventilation systems included in this work item, to demonstrate existing operational condition. Submit a CFR.
3.3 Cleaning requirements. The Contractor shall clean and inspect the following ventilation systems, shown on «DWG1», in accordance with SFLC Std Spec 5100. Submit a CFR.
Table 1 – engine room
| ventilation sytem |
| type |
| location |
| 01-104-2 |
| Supply |
| Engneer’s workshop |
| 01-106-1 |
| Supply |
| Engine room 3-103-0-e |
| 01-106-2 |
| supply |
| Engine room 3-103-0-e |
3.3.1 The Contractor shall clean the exhaust ventilation ducting up to and including the discharge of the engine room exhaust fans. The Contractor is not expected to clean the exhaust stack plenum area.
Past experience has shown that the engine room exhaust ventilation systems have accumulated oils and greases and systems are coated with a very sticky and very thick sludge. Take this into consideration in the bid.
3.3.2 Disassemble the exhaust system as required to clean all sections of the exhaust system.
3.3.2.1 After cleaning, reassemble vent ducting using new gaskets and fasteners.
3.3.3 Prior to reassembling the vent systems, visually inspect the systems in the presence of the Coast Guard Inspector. Verify that the vent systems are clean and oil and build up free. The Contractor shall use video probe equipment to allow viewing the internal surfaces of all vent ducting.
3.4 Notification. The Contractor shall give written notification to the COR 48 hours before starting ventilation cleaning work.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.5 Operational test, post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the ventilation systems disturbed to be in satisfactory operating condition. Submit a CFR.
4. NOTES
This section is not applicable to this work item.