USCGC RICHARD T. SNYDER (WPC 1127)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2019

Developed By: Ryan S Hopkins

(Rev-0, 20 December 2018)

RFQ 70Z08019QP4557800

USCGC RICHARD T. SNYDER (WPC-154) DOCKSIDE AVAILABILITY FY2019

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: Sewage and Grey Water System, Clean and Inspect WORK ITEM 2: Machinery Ventilation System, Clean WORK ITEM 3: HVAC Duct System, Clean WORK ITEM 4: Electrical Power Distribution System, Thermographic Inspection (450 VAC And

Below) iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 127-302, Rev B, Potable Water & Sewage Tank Fabrication Details

Coast Guard Drawing 154 WPC 320-301, Rev C, 450V System Deck Plan

Coast Guard Drawing 154 WPC 330-301, Rev E, 120V System Deck Plan

Coast Guard Drawing 154 WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows Arrangement

Coast Guard Drawing 154 WPC 506-301, Rev -, Fills, Vents, Sounds, Overflows Diagram

Coast Guard Drawing 154 WPC 512-201, Rev -, HVAC Arrangement

Coast Guard Drawing 154 WPC 512-301, Rev A, HVAC System Diagram

Coast Guard Drawing 154 WPC 512-305, Rev 8, HVAC Equipment List

Coast Guard Drawing 154 WPC 513-201, Rev 1, Machinery Ventilation Arrangement

Coast Guard Drawing 154 WPC 513-301, Rev C, Machinery Ventilation Diagram

Coast Guard Drawing 154 WPC 528-301, Rev -, Grey Water System Diagram

Coast Guard Drawing 154 WPC 593-201, Rev D, Sewage System Arrangement

Coast Guard Drawing 154 WPC 593-301, Rev C, Sewage System Diagram

Coast Guard Drawing 154 WPC 593-303, Rev -, Sewage Control System

Coast Guard Drawing 154 WPC 601-302, Rev C, General Arrangement

Coast Guard Drawing 154 WPC 633-301, Rev B, Cathodic Protection System

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Coast Guard Technical Publication (TP) 8123, 15 SEP 2015, Preliminary - Heating, Ventilation, and Air

Conditioning System - Frc-514-P1

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean

Shipboard Ventilation Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures v (Rev-0)

OTHER REFERENCES

American Society for Nondestructive Testing, SNT-TC-1A: Personnel Qualification and Certification in

Nondestructive Testing, 2016

ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets vi (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM

DESCRIPTION

NSN/PN QTY ESTIMATED

COST

($/UNIT)

1 N Sewage Tank Zinc

Anode

NIIN: 014474686 2 142.19

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter vii (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

1 Sewage and Grey Water System, Clean and Inspect viii (Rev-0)

PRINCIPAL CHARACTERISTICS

154' WPC (SENTINEL CLASS)

PHYSICAL

Anchor ROCNA, anchor, 150 KG/ 331 LB, Stainless Steel

Bulkheads (7), Watertight Bulkheads located below the Main Deck

Displacement, delivery, light ship 302 Metric Tons

Draft, full load 2.58 Meters (8.46 Feet)

End of service life displacement 353 Metric Tons

Framing Longitudinal

Full load displacement 353 Metric Tons

Height of highest projection 17.22 Meters (56.5 Feet)

Length overall (loa) 46.80 Meters (153.5 Feet)

Maximum beam 7.75 Meters (25.43 Feet)

Minimum operating displacement 314 Metric Tons

Waterline length (lwl) 44.35 Meters (145.5 Feet)

HULL

Hull/main weatherdeck material AH-36 Steel

Superstructure 5456-H1111 Aluminum

MACHINERY

Bow thruster Schottel STT 60 LK

Diameter of propeller 1900 mm

Emergency service generator (edg) Cummins 6BTA5.9-DM Diesel with Stanford 93KW Generator

Fin stabilizer (2), Quantum QC1500

Main propulsion (2), MTU 20V4000 M93L, Sequential Turbo-Charged Diesels

Number of blades 6

Number of propellers (2) Michigan Wheel Marine

Propeller pitch capability Fixed

Propulsion shafts (2), Electralloy Nitronic 50HS (9430mm) Shafts

Reduction gears (2), ZF 23560C/D Series

Rudders (2), 316L Stainless Steel

Shaft rotations per minute 478

Shaft(s) bearing, aft (2), Duramax Bearings

Shaft(s) bearing, intermediate (2), Duramax Bearings

Shaft(s) diameter 8 Inches

Shaft(s) Seal (2), Wartsila Mechanical Seals

Ship service generators (2), Cummins QSM11-DM Diesels with Stanford 317KW Generator

TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)

Fresh water tank, port (3-38-2-w) 708 gal

Fresh water tank, stbd (3-38-1-w) 756 gal

Fuel oil edg day tank (1-10-1-f) 134 gal

Fuel oil gen. ovrflw tnk, ctr. (3-40-0-f) 1,159 gal

Fuel oil overflow tank, center (3-10-0-f)

616 gal

Fuel oil service tank, #1 port (3-17-2-f) 1,750 gal

Fuel oil service tank, #1 stbd (3-17-1-f) 1,750 gal

Fuel oil service tank, #2 port (3-40-2-f) 890 gal

Fuel oil service tank, #2 stbd (3-40-1-f) 890 gal

Fuel oil storage tank, #1 center (3-11-0- 5,040 gal ix (Rev-0) f)

Fuel oil storage tank, #2 center (3-23-0-f)

5,350 gal

TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)

Grey water tank, (3-17-0-w) 2,668 gal.

Lube oil storage tank, (2-35-2-f) 146 gal.

Oily water tank, (3-34-1-w) 336 gal.

Sewage collection tank, (3-6-0-w) 429 gal.

Waste oil tank, (3-34-2-f) 336 gal.

1 (Rev-0)

00000_0618_FLT

REC_00000_FLT_Commercial Project @ CG Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec

0000, in accomplishing the following task:

Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes

(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC

Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable

Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is small quantity.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an

NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3 (Rev-0)

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste

Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the

Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the

Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For

Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the

Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast

Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

4 (Rev-0)

3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint

Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of

SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay

(RRL) wire rope or Dyform-18, rotation resistant wire rope."

3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

7 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

8 (Rev-0)

TIME

9 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading

(mils)

Mean Reading (mils) IAW ASTM DD4417).

10 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

11 (Rev-0)

12 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic

Pull-Off (Type I/Banana) Gauge Is

Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

13 (Rev-0)

59301_JLW_0818_154WPC

WORK ITEM 1: Sewage and Grey Water System, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the sewage and grey water system (e.g. tanks, piping, etc.).

TABLE 1

USE OF COAST GUARD SEWAGE AND GREY WATER DISPOSAL FACILITIES

(PARA 3.3.4.2)

NO

1.1.1 Repairs. The scope of know repair work, in addition to cleaning and inspection requirements, are described below.

TABLE 2

KNOWN REQUIRED REPAIR WORK

(PARA 3.4.1)

REPAIR

ITEM

DESCRIPTION

1 NONE.

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

N Sewage Tank Zinc Anode NIIN: 014474686 2 142.19

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 127-302, Rev B, Potable Water & Sewage Tank Fabrication

Details

Coast Guard Drawing 154 WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows

Coast Guard Drawing 154 WPC 506-301, Rev -, Fills, Vents, Sounds, Overflows Diagram

Coast Guard Drawing 154 WPC 528-301, Rev -, Grey Water System Diagram

Coast Guard Drawing 154 WPC 593-201, Rev D, Sewage System Arrangement

Coast Guard Drawing 154 WPC 593-301, Rev C, Sewage System Diagram

Coast Guard Drawing 154 WPC 593-303, Rev -, Sewage Control System file://///d05ms-mwebapps1/../sflc/ProductLineSpecs/SWBS%20ETC.pdf

14 (Rev-0)

Coast Guard Drawing 154 WPC 601-302, Rev C, General Arrangement

Coast Guard Drawing 154 WPC 633-301, Rev B, Cathodic Protection System

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for paragraph 3.2.1 Inspection of Grey Water Tank.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec

0000, paragraph 3.3.5 (Interferences).

3.1.5 Temporary Sanitary and Sewage Facilities. Whenever sewage or grey water collection service is disrupted due to contractor repairs, the Contractor shall provide temporary facilities in accordance with

SFLC Standard Spec 0000 par 3.2.11.

3.1.6 Temporary HVAC. If the contractor’s proposed cleaning plan (para 3.2.1 below) will degrade continuous operation of the ship’s HVAC system then the Contractor shall provide temporary ventilation to all impacted areas equivalent to the normal zonal ventilation rating for those spaces (i.e. maintain existing climate control) for the duration of work as described in SFLC Std Spec 0000.

3.1.7 Refer to Coast Guard Drawings 154 WPC 506-201, 154 WPC 506-301, 154 WPC 528-301, 154

WPC 593-301, 154 WPC 593-303, 154 WPC 601-302, and 154 WPC 633-301.

NOTE

Be aware that the grey water system has few isolation valves and many openings that must be plugged or blanked to contain cleaning media.

15 (Rev-0)

Be aware that AC condensate drains into the Grey Water Tank at 8 separate locations. Any temporary disruption or degradation of climate control must be fully addressed by the cleaning plan.

For these reasons, based on lessons learned, it is suggested that chemical cleaning be used on sewage piping and grey water system piping be cleaned mechanically (e.g. waterjetting, etc.)

3.1.8 Cleaning Plan. No later than 7 days after the arrival conference, and prior to the start of cleaning work, the Contractor shall submit a cleaning plan CFR that contains the following:

A list of qualified personnel who will disassemble machinery or handle chemicals.

An SDS for every chemical proposed for use.

A step by step description of the procedures and methods that will be used to clean the systems

A list of locations in the sewage and grey water piping system where piping lines will be opened and components will be removed. At a minimum the piping shall be opened at 3 separate sewage system clean-out locations and 3 separate grey water system clean-out locations for “before and after” inspections to determine the extent of cleaning required and to verify cleaning was adequately performed. These locations shall be pre-approve by the

COR and included in the cleaning plan CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test and inspection - initial. Prior to commencement of cleaning work, the Contractor shall witness Coast Guard personnel perform an operational pre-test of all items and shipboard devices to be disturbed, used, repaired, or altered, (e.g. TLIs, pumps, etc.) to demonstrate existing operational condition and to determine a more precise scope of cleaning required. Submit a CFR detailing any required growth work or repairs identified during the operational test based on the observed condition of the systems. Use the most economical methods for accomplishing the work.

3.2.1 Inspection of Grey Water Tank. The Contractor shall open and inspect the grey water tank to determine the condition of the grey water tank coating system to the greatest extent practicable, pre-cleaning. Submit CIR detailing the condition of the grey water tank coating system and any noted discrepancies, include an estimated square footage of failed coating in the CIR.

3.3 Cleaning and Inspection Requirements. After the COR approves the “Cleaning Plan” the Contractor shall clean the piping and tanks and in accordance with the approved “Cleaning Plan”, and as described below. Clean, in their entirety, all sewage and grey water system interior surfaces (e.g. sewage and grey water ppg interiors, pump interiors, valve interiors, all sewage and grey water tank vent lines interiors, sewage vacuum switch manifold interiors, fire main sprinkler pipe interiors and spray hole interiors in main sewage tank used to flush sewage tank, overboard/to shore connection discharge pump and all related valve and pipe interiors, etc.) that may come in contact with sewage or grey-water, by removing all obstructions, clogs, uric scale, and waste build-up on piping and component interiors, ensuring subsequent free unobstructed flow of waste solids and fluids.

16 (Rev-0)

NOTE

Depending on the condition of the system at the contract start date, chemical cleaning may not adequately remove all obstructions, scale, and build-up present. More intrusive cleaning methods, such as pressure washing, flexible auger cleaning, or other mechanical means of cleaning, may be required to remove all obstructions, scale, etc. These more intrusive methods are in scope of this work item and the contractor may be required to use one or more them, in the appropriate quantities, to achieve minimum cleaning requirements.

3.3.1 Repairs. In addition to the cleaning and inspection requirement specified herein, the Contractor shall perform the repairs described in Table 2 beneath paragraph 1.1.1. If “NONE” appears in Table 2 then there are no known repairs required to the systems.

Before filling a system with descaler ensure all openings below the fill point are blanked off or plugged.

3.3.2 Chemical Cleaning of Piping. When chemically cleaning piping and component interiors use a commercially available biodegradable sewage/grey-water system descaler (e.g. SEW CLEAN, etc.) safe for use on stainless steel. Fill the systems with descaler and hold for a long enough period to clean the systems as described above. After cleaning is complete drain and dispose of all sewage and grey water system contents.

3.3.3 Tank Cleaning. Interior surfaces of the Grey Water Tank 3-17-0-W, Sewage Holding Tank 2-4-0-

W, and sewage vacuum accumulation tank shall be cleaned until free of all foreign materials, sediment, and sludge. Remove all persistent residues, residual wash media, and moisture with clean lint-free cloths.

Remove, clean, and re-install all tank interior components (e.g. TLIs, limit switches, eductors, etc.).

Renew all zinc anodes installed in the sewage tank and grey water tanks using Government-furnished property. Remove and dispose of all sewage system contents and collect, contain, and dispose of all wash media and cleaning materials in accordance with all applicable Federal, state, and local regulations.

Remove all unused chemicals from USCG property immediately upon completion of work item.

3.3.4 Inspections. After cleaning, inspect the piping interior at the locations specified in the “Cleaning

Plan” using a borescope in the presence of the COR, verify that all solid deposits, visible to the unmagnified eye, have been removed. Visually inspect all system components (e.g. TLIs, limit switches, pressure switches, tank interior surfaces, fasteners, gasket seating surfaces, manhole cover surfaces, etc.)

for excessive wear, damage, and all other notable discrepancies. Open and vacuum-clean the control panel assembly and inspect for any indications of overheating or loose wiring or connections. Submit a

CFR.

3.3.5 Miscellaneous. Do not drain any fluids (e.g. sewage, grey water, fresh water, etc.) into any space, bilge, or exterior location. Take all precautions required to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations. Renew all disturbed soft components (e.g. seals, gaskets, o-rings, etc.). Do not use the sewage pump installed in the system to offload sewage system contents.

17 (Rev-0)

3.3.5.1 Plug log. Plug all unattended openings in the system. Plugs shall be fitted with a lanyard, ring or other device to prevent loss of the plug inside the system. Create and maintain a written log of each plug that specifies the location of each. Remove and dispose of all plugs upon completion of work. Furnish the plug log to the Coast Guard Inspector during the performance of close-out inspections.

3.3.5.2 Use of Coast Guard Sewage and Grey Water Disposal Facilities. If “YES” is denoted in table beneath paragraph 1.1 (Intent), the Contractor may offload and dispose sewage and grey water system contents into the Coast Guard pier facility tanks in lieu of a contractor furnished tank truck, otherwise the contractor shall dispose of all waste using the contractor’s disposal facilities.

3.6 Closing tanks. The Contractor shall notify the COR at least 24 hours prior to closing the tank. After completion of all authorized repairs and after the COR inspects all work performed, close the tanks.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.7 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test all disturbed components and systems and accomplish the following tasks in conjunction with each other as appropriate, in the presence of the Coast Guard Inspector, and submit a CFR:

3.7.1 Adjust the set point on each of the vacuum pressure switches (as applicable) to the set points noted previously.

3.7.2 Verify operation of the low and high level switches/alarms and that the pumps cycle from lead to lag status during operation. Demonstrate proper operation of tank TLIs to prove satisfactory operating condition.

3.7.3 Leak test. After all system components are reinstalled, the Contractor shall test all disturbed piping for leaks, as follows:

Run water down all disturbed grey water system piping runs for 5 minutes.

Ensure the system holds vacuum without cycling for at least 20 mins.

Place both vacuumarator selection switches in the "RUN" position. Allow vacuumarator pump to run until system operating pressure of -0.40 to -0.55 bar is reached. Observe vacuum tank pressure gauge. Place both vacuumarator selection switches in the "OFF" position. (NOTE: A vacuum loss of more than 0.14 bar indicates an air leak exists in the system.) Verify vacuum system pressure remains between -0.40 to -0.55 bar for 20 minutes.

Record pressure value and include in the CFR.

Perform smoke leak test on vacuum portions of the sewage system where the contractor has disturbed a mechanical joint.

Closely monitor the systems for leaks. Repair all leaks detected. Repeat test and inspection tasks until no leaks are detected.

3.7.4 Upon completion of testing and, in the presence of the Coast Guard Inspector, pump tanks to the limit of the ship’s installed pumps.

18 (Rev-0)

4. NOTES

This section is not applicable to this work item.

19 (Rev-0)

WORK ITEM 2: Machinery Ventilation System, Clean

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the interior of the following ventilation system components and ducts.

TABLE 1 –MACHINERY VENTILATION DUCTS TO BE CLEANED

Duct Main Engine Room Supply

Main Engine Room Exhaust

Generator Room Supply

Generator Room Exhaust

PORT Steering Gear Room Supply

PORT Steering Gear Room Exhaust

STBD Steering Gear Room Supply

STBD Steering Gear Room Exhaust

FWD Auxiliary Machinery Room Supply

FWD Auxiliary Machinery Room Exhaust

Galley Hood Supply

Galley Hood Exhaust

EDG Room Supply

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 513-201, Rev 1, Machinery Ventilation Arrangement

Coast Guard Drawing 154 WPC 513-301, Rev C, Machinery Ventilation Diagram

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean

Shipboard Ventilation Systems

Coast Guard Technical Publication (TP) 8123, 15 SEP 2015, Preliminary - Heating, Ventilation, and Air Conditioning System - Frc-514-P1

OTHER REFERENCES

None

20 (Rev-0)

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

Coast Guard personnel will operate all shipboard machinery and equipment.

The Contractor is reminded to comply with ALL requirements invoked by this work item, such as SFLC Std Spec 0000 and SFLC Std Spec 5100 (e.g.

mark and restore damper positions; remove all intake and exhaust screens, clean vent systems in their entirety from the point where the air enters the system to the point where the air is discharged from the system; restore, renew, or repair all articles or component removed or disturbed to their original condition if damaged or modified during contract work, etc).

3.2 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard

Personnel perform an initial operational test of the ventilation systems included in this work item, to demonstrate the existing operational condition. Document all modifications to the system (e.g. new holes in existing duct, etc.) that will be required to perform the cleaning work, do not perform modifications without Coast Guard authorization. Submit a CFR.

NOTE

Please be aware that this work item does not describe cleaning work for MDE and SSDG combustion air intake ducting (the large vertical trunks on main deck and the 01 deck whose inlets face aft). DO NOT perform any work on those ducts via this work item.

This work item only requires work to be performed on vent ducting that is connected to directly to machinery space “compartments”.

3.3 Cleaning requirements. The Contractor shall clean and inspect the interior surfaces of ventilation system ducting runs and components listed in the table beneath paragraph 1.1 above, shown on the Coast

Guard drawings and TPs listed in Section 2, in accordance with SFLC Std Spec 5100. Submit a CFR.

21 (Rev-0)

3.3.1 Duct Interior Images for Final Report. After gaining access to duct interiors, take a digital photo of each duct interior surfaces at the opening created to show the condition of the duct work prior to cleaning.

Then prior to closing the duct work accesses take a final image of the same area post-cleaning. Add these images to the final report submitted in paragraph 3.6 below.

3.3.2 Notification. The Contractor shall give written notification to the COR, 48 hours before starting ventilation cleaning work.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.4 Operational test, post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the ventilation systems included in this work item to be in satisfactory operating condition. Submit a CFR.

22 (Rev-0)

WORK ITEM 3: HVAC Duct System, Clean

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the interior of the following ventilation system components and ducts.

TABLE 1 – AREAS WITH HVAC DUCT OR COMPONENTS TO BE CLEANED

Compartment Items To Be Cleaned.

Pilot House (01-19-0-C) All supply and return ducting and associated grating/louvers, etc.

Main Deck

HVAC Equipment Room (1-24-1-Q) All supply and return ducting and associated grating/louvers, etc.

All surfaces inside of air handler assembly that contact air going out to supply ducts (e.g. coils, filters, plenums, etc.)

Passage (1-23-0-L) All supply and return ducting and associated grating/louvers, etc.

Mess Deck (1-17-0-Q) All supply and return ducting and associated grating/louvers, etc.

Galley (1-18-2-Q) All supply and return ducting and associated grating/louvers, etc.

Office (1-16-1-A) All supply and return ducting and associated grating/louvers, etc.

CO Cabin (1-12-1-L) All supply and return ducting and associated grating/louvers, etc.

XO Stateroom (1-12-2-L) All supply and return ducting and associated grating/louvers, etc.

OPS CPO Stateroom (1-15-2-L) All supply and return ducting and associated grating/louvers, etc.

Second Deck

Climate Controlled Store Room (2-

23-4-A)

All supply and return ducting and associated grating/louvers, etc.

C4ISR Equipment RM (2-23-3-Q) All supply and return ducting and associated grating/louvers, etc.

ENG CPO Stateroom (2-32-2-L) All supply and return ducting and associated grating/louvers, etc.

2 Person Stateroom (2-21-2-L) All supply and return ducting and associated grating/louvers, etc.

4 Person Stateroom (2-20-1-L) All supply and return ducting and associated grating/louvers, etc.

4 Person Stateroom (2-17-2-L) All supply and return ducting and associated grating/louvers, etc.

2 Person Stateroom (2-17-1-L) All supply and return ducting and associated grating/louvers, etc.

2 Person Stateroom (2-15-2-L) All supply and return ducting and associated grating/louvers, etc.

2 Person Stateroom (2-15-1-L) All supply and return ducting and associated grating/louvers, etc.

1 Person Stateroom (2-10-2-L) All supply and return ducting and associated grating/louvers, etc.

1 Person Stateroom (2-10-1-L) All supply and return ducting and associated grating/louvers, etc.

Passage (2-10-0-L) All supply and return ducting and associated grating/louvers, etc.

TABLE 2 – CONTRACTOR FURNISHED TEMP HVAC (PARA 3.3)

YES

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 154 WPC 512-201, Rev -, HVAC Arrangement

23 (Rev-0)

Coast Guard Drawing 154 WPC 512-301, Rev A, HVAC System Diagram

Coast Guard Drawing 154 WPC 512-305, Rev 8, HVAC Equipment List

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean

Shipboard Ventilation Systems

Coast Guard Technical Publication (TP) 8123, 15 SEP 2015, Preliminary - Heating, Ventilation, and Air Conditioning System - Frc-514-P1

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

24 (Rev-0)

The Contractor is reminded to comply with ALL requirements invoked by this work item, such as SFLC Std Spec 0000 and SFLC Std Spec 5100 (e.g.

mark and restore damper positions; remove all intake and exhaust screens, clean vent systems in their entirety from the point where the air enters the system to the point where the air is discharged from the system; restore, renew, or repair all articles or component removed or disturbed to their original condition if damaged or modified during contract work etc).

3.2 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard

Personnel perform an initial operational test of the ventilation systems included in this work item, to demonstrate the existing operational condition. Document all modifications to the system (e.g. new holes in existing duct, etc.) that will be required to perform the cleaning work, do not perform modifications without Coast Guard authorization. Submit a CFR.

3.3 Temporary HVAC. If “YES” is denoted in Table 2 then the Contractor shall provide temporary ventilation to all impacted areas equivalent to the normal zonal ventilation rating for those spaces (i.e.

maintain existing climate control) for the duration of work as described in SFLC Std Spec 0000, otherwise the Coast Guard will furnish any required temporary ventilation.

3.4 Cleaning requirements. The Contractor shall clean and inspect the interior surfaces of ventilation system ducting runs and components listed in the table beneath paragraph 1.1 above, shown on the Coast

Guard drawings and TPs listed in Section 2, in accordance with SFLC Std Spec 5100. Submit a CFR.

3.4.1 Duct Interior Images for Final Report. After gaining access to duct interiors, take a digital photo of each duct interior surfaces at the opening created to show the condition of the duct work prior to cleaning.

Then prior to closing the duct work accesses take a final image of the same area post-cleaning. Add these images to the final report submitted in paragraph 3.6 below.

3.5 Notification. The Contractor shall give written notification to the COR, 48 hours before starting ventilation cleaning work.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.6 Operational test, post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the ventilation systems…