Attachment-3 Technical Evaluation Factors

USCGC JOSEPH TEZANOS FY19 DS Contract

**PLEASE FULLY COMPLETE ALL QUESTIONS AND SUBMIT AS A SEPARATE

ATTACHMENT

General Technical Approach

Submit a brief overview planning document using any means (computer generated, hand written, etc.) that outlines the strategy for ensuring that this requirement is completed on or before the contract completion date. The planning document shall include at least:

1) Proposed schedule, resources, completion-dates, float, and major millstones for the various tasks required to complete this contract and

2) Identify a list of items that may pose the most contract schedule risk and approach to mitigate or eliminate each risk.

Preservation Coatings Certification Requirements

Submit a description of how you intend to meet SFLC Standard Specification

0000 coatings QC/QA requirements for this contract. This plan must include the names of any subcontractors and resumes for any proposed QP1 certified painters and/or independent NACE CIP Level 3 inspectors.