USCGC WILLIAM TRUMP (WPC 1111)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2019

Developed By: Kent W Ross (Rev-0, 02 JULY 2018)

TABLE OF CONTENTS

iiiRevisions Record ivConsolidated List of References vConsolidated List of Government-furnished Property viConsolidated List of Critical Inspection Items viiPrincipal Characteristics

1General Requirements

13WORK ITEM 1: 154WPC MDEs, Maintain

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 154WPC 085-201 Rev -, PROPULSION SYSTEM, SSDG, EDG INSTALLATION DRAWINGS

Coast Guard Drawing 154WPC 200-301 Rev -, MACHINERY ARRANGEMENT DRAWINGS

Coast Guard Drawing 154WPC 204-301 Rev E, EQUIPMENT REMOVAL PLAN

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication 8019 (TP-8019), Section D, Main Propulsion Engine MTU 20V4000M93L, Volume 4, Maintenance and Overhaul Manual MS2205/00E, MS68001/02E, MA50075/02E, MA25014/01E, and MA20011/01E

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

Consolidated List of Government-furnished Property

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

This section is not applicable to this package.

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item
Title
1
154WPC MDEs, Maintain

Principal Characteristics

154' WPC (Sentinel Class)

Physical

Anchor
ROCNA, anchor, 150 KG/ 331 LB, Stainless Steel
Bulkheads
(7), Watertight Bulkheads located below the Main Deck
Displacement, delivery, light ship
302 Metric Tons
Draft, full load
2.58 Meters (8.46 Feet)
End of service life displacement
353 Metric Tons
Framing
Longitudinal
Full load displacement
353 Metric Tons
Height of highest projection
17.22 Meters (56.5 Feet)
Length overall (loa)
46.80 Meters (153.5 Feet)
Maximum beam
7.75 Meters (25.43 Feet)
Minimum operating displacement
314 Metric Tons
Waterline length (lwl)
44.35 Meters (145.5 Feet)

Hull

Hull/main weatherdeck material
AH-36 Steel
Superstructure
5456-H1111 Aluminum

Machinery

Bow thruster
Schottel STT 60 LK
Diameter of propeller
1900 mm
Emergency service generator (edg)
Cummins 6BTA5.9-DM Diesel with Stanford 93KW Generator
Fin stabilizer
(2), Quantum QC1500
Main propulsion
(2), MTU 20V4000 M93L, Sequential Turbo-Charged Diesels
Number of blades
6
Number of propellers
(2) Michigan Wheel Marine
Propeller pitch capability
Fixed
Propulsion shafts
(2), Electralloy Nitronic 50HS (9430mm) Shafts
Reduction gears
(2), ZF 23560C/D Series
Rudders
(2), 316L Stainless Steel
Shaft rotations per minute
478
Shaft(s) bearing, aft
(2), Duramax Bearings
Shaft(s) bearing, intermediate
(2), Duramax Bearings
Shaft(s) diameter
8 Inches
Shaft(s) Seal
(2), Wartsila Mechanical Seals
Ship service generators
(2), Cummins QSM11-DM Diesels with Stanford 317KW Generator

Tank Capacities at 95% LIQUID LOAD (22,958 total Gallons)

Fresh water tank, port (3-38-2-w)
708 gal
Fresh water tank, stbd (3-38-1-w)
756 gal
Fuel oil edg day tank (1-10-1-f)
134 gal
Fuel oil gen. ovrflw tnk, ctr. (3-40-0-f)
1,159 gal
Fuel oil overflow tank, center (3-10-0-f)
616 gal
Fuel oil service tank, #1 port (3-17-2-f)
1,750 gal
Fuel oil service tank, #1 stbd (3-17-1-f)
1,750 gal
Fuel oil service tank, #2 port (3-40-2-f)
890 gal
Fuel oil service tank, #2 stbd (3-40-1-f)
890 gal
Fuel oil storage tank, #1 center (3-11-0-f)
5,040 gal
Fuel oil storage tank, #2 center (3-23-0-f)
5,350 gal

Tank Capacities at 95% LIQUID LOAD (22,958 total Gallons)

Grey water tank, (3-17-0-w)
2,668 gal.
Lube oil storage tank, (2-35-2-f)
146 gal.
Oily water tank, (3-34-1-w)
336 gal.
Sewage collection tank, (3-6-0-w)
429 gal.
Waste oil tank, (3-34-2-f)
336 gal.

00000_0618_FLT

REC_00000_FLT_Commercial Project @ CG Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

Coast Guard Drawings

None

Coast Guard Publications

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Other References

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

· Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is small.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

· Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

· National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

· Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope."

3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading (mils)

Mean Reading (mils) IAW ASTM DD4417).

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

Date
Test Locations
Conductivity (Microsiemens/CM)
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

20000_JLW_0916_154WPC

WORK ITEM 1: 154WPC MDEs, Maintain

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform maintenance tasks on the 154WPC MDEs at the 6000 operational hour interval.

1.2 Government-furnished property.

None

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 154WPC 085-201 Rev -, PROPULSION SYSTEM, SSDG, EDG INSTALLATION DRAWINGS Coast Guard Drawing 154WPC 200-301 Rev -, MACHINERY ARRANGEMENT DRAWINGS Coast Guard Drawing 154WPC 204-301 Rev E, EQUIPMENT REMOVAL PLAN Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Coast Guard Technical Publication 8019 (TP-8019), Section D, Main Propulsion Engine MTU 20V4000M93L Other References

None.

3. REQUIREMENTS

3.1 Perform 6000 Engine Hour Maintenance (Both Port and Stbd Engines). The Contractor shall perform the following, which includes all MTU 6,000 hour and under (i.e. 3000, 1000, and 500 hrs maintenance).

3.1.1 Refer to TP-8019 and Coast Guard Drawings 154WPC 085-201, 154WPC 200-301, 154WPC 204-301.

3.1.2 Qualifications. At least one technician on site shall be QL3 certified on 20VMTU4000/M93L series engines with prior experience on that engine, and shall possess a legal 1B dongle certification on ECU-7 series governor.

3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Requirements specific to executing this item in conjunction with warranty contracts occurring at Tampa Ship, LLC. Tampa Ship LLC is executing a separate USCG dry docking contract contemporaneously with this contract. Prior to performing the services specified herein, the Contractor shall obtain all the necessary agreements with Tampa Ship LLC that will ensure both contracts are executed in accordance with all requirements (e.g. use of Tampa Ship LLC cranes and other equipment in the performance of this contract, potential use of Tampa Ship LLC HASMAT disposal, vessel/compartment access agreements, Contractor parking agreements, info needed to meet all Tampa Ship LLC pass office requirements and procedure, etc.) and then proceed in accordance with those agreements.

3.1.5 Maintenance Tasks. Perform the following.

NOTE

Ship’s Force will perform electrical isolation, tag-out procedures, etc. Coordinate with Ship’s Force and ensure all of this work is complete prior to performing any maintenance.

· During the course of disassembly and reassembly in conjunction with performing the tasks specified below renew all disturbed seals, gaskets, o-rings, rubber sleeves, and all other soft wearing parts.

· Remove and re-install all interferences, as required, to perform the following maintenance.

· Perform a sea trial and pre-test. Upon completion of the sea trial submit a CFR that includes a list of discrepancies and a minimum of 30 min of ECU engine data.

· Clean and inspect air flexible ducting leading to the air turbo inlets from the transition piece.

NOTE

The charge air cooler is too large to be removed as a unit from the vessel. It must first be disassembled and the core must be removed separately.

· Clean the charge air cooler and inspect for leakage. Prior to disassembling the charge air cooler submit a CFR detailing a disassembly and removal plan. Initiate disassembly after the Coast Guard approves the plan.

· Drain and dispose of jacket water/coolant and engine oil, flush both systems in conjunction to remove all loose contaminates.

· Inspect each cylinder chamber on both engines and submit a CIR detailing the condition of each.

· Renew the high-pressure fuel sensor on each engine.

· Inspect centrifugal oil filter and check bearing for wear. (refer to MA25014, Instruction for overhaul of assemblies)

· Renew both starters on each engine.

· Clean each engine coolant/fuel cooler.

· Clean each engine oil cooler.

· Renew the coolant pump on each engine.

· Renew the raw water pump on each engine.

· Inspect all rocker arms and valve bridges for wear. Insert an endoscope through the pushrod bore to visually inspect swing followers and camshaft running surfaces.

· Renew the thermostats and verify proper thermal actuation.

· Inspect all engine mounts. Measure the buffer clearance of the resilient mounts and verify proper seating of securing screws. Check for cracks in the rubber elements, measure the size of any cracks found. Measure the height of each rubber elements. Submit a CFR detailing all findings and describe all recommended repairs.

· Renew all cylinder head wearing components (e.g. springs, seals, etc.) and repair all defects found to all other cylinder head components, i.e. overhaul all cylinder heads (e.g. repair individual defects, or provide new or remanufactured heads, etc.). Submit a report detailing the maintenance actions taken to each head.

· Renew all turbocharger wearing components (e.g. springs, seals, etc.) and repair all defects found to all other turbocharger components (e.g. repair individual defects, or provide new or remanufactured turbochargers, etc.). Submit a report detailing the maintenance actions taken to each turbocharger.

· Renew all fuel injectors.

· Inspect and clean oil indicator filter.

· Renew the jacket water/coolant, engine oil, and primary and secondary fuel filters.(engine mounted)

· Perform a final sea trial and post maintenance test, conducting a 2hr full power trial run. After completion of the sea trail submit a minimum of 30 minutes of ECU engine data. Submit a final report.

· All reports, except the final sea trail test report are due no later than 2/3 through the contract performance period. The final sea trial test report is due no later than 1 week after completion of sea trials.

4. NOTES