This document is a Statement of Work (SOW) for the United States Coast Guard's initial certification of a 154' Fast Response Cutter (FRC) Docking Cart Assembly. The SOW requires a third-party contractor to conduct comprehensive inspections and provide certification for the docking cart, with all work to be performed at the USCG Yard in Baltimore, Maryland. The contractor must complete all inspections and deliver a detailed certification report within 30 days of load testing, including specific appendices from SFLC Standard Specification 8634, an inspection overview, proof testing documentation, and a professional engineer's signed endorsement.

The related federal contract opportunity is a Firm Fixed Price Purchase Order (Solicitation Number 70Z04026Q60362) issued by the Department of Homeland Security's US Coast Guard Surface Forces Logistics Center. The solicitation requires the contractor to mark materials per MIL-STD-129R, use Military Packaging according to MIL-STD-2073-1E, and deliver supplies to the receiving room at 2401 Hawkins Point Rd in Baltimore. The point of contact is Keith Hare, who can be reached at keith.f.hare@uscg.mil or (410) 456-7926, though he is not a warranted Contracting Officer.

View the file

Other files

File Type Posted
SOW FRC RDAP Cart Cert_Updated 12-4-25.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PR# 2126406Y61P3399001

Statement of Work WI-001: 154’ FRC Docking Cart - Initial Certification

1. SCOPE

Intent: The Contractor shall provide services to certify 01 WPC Docking Cart Assembly.

2. REFERENCES

COAST GUARD PUBLICATIONS

· Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking

· United States Coast Guard Drawing No. YD-085-050, Rev – FRC Docking Cart and Block Tower Fabrication.

OTHER REFERENCES – Available post-award upon request

· Non-Destructive Testing (Visual) Inspection, conducted by CG Yard upon fabrication

· Non-Destructive Testing (Magnetic Particle) Inspection, conducted by CG Yard upon fabrication

· Documentation of Load Testing conducted in accordance with above references.

· Non-Destructive Testing (Magnetic Particle) Inspection, conducted by CG Yard post-load testing.

3. REQUIREMENTS

3.1 The Contractor shall conduct all necessary inspections required to issue initial certification for 01 FRC Docking Cart Assembly, constructed in accordance with referenced drawings. Certification shall meet requirements stated within SFLC STD Spec 8634. Certifying Authority shall provide requirements for type of weld inspection and length of weld inspection required for certification.

3.2 Location: All inspections shall be conducted at USCG Yard, Baltimore MD 21226.

3.3 Period of Performance: All work and applicable deliverables shall be provided within 30 days of load testing, conducted in accordance with paragraph 3.5, below.

3.4 Deliverable Requirements: Contractor shall provide a Certification Report, which shall include – at minimum – the following:

3.4.1 Appendix B-2 (of SFLC STD Spec 8634), signed and sealed by a Professional Engineer (State of Maryland)

3.4.2 Appendix B-23 and Appendix B-24 of SFLC STD Spec 8634, completed.

3.4.3 Inspection Overview

3.4.4 Proof Testing, as applicable.

3.4.5 Inspection Findings with supporting documentation, as applicable.

3.4.6 Surveyor’s Endorsement, annotated as “SATISFACTORY” or “UNSATISFACTORY”. Any contingencies to endorsement must be clearly noted.

3.4.7 NDT Weld Test Report