Base Year
| Instructions: Fill in the shaded boxes only. All other numbers will automatically calculate. Use the tabs at the bottom to provide pricing for the base period through option year four. If your company has any additional charges or fees, prompt payment discounts, etc., clearly state what these are in your proposal. CLINs 0001-0002 pricing is to be calculated as 75% of the Field Service Engineer (FSE) rate for CLIN 0001 and 25% of FSE rate for CLIN 0002 for one (1) FSE. If you have any questions when completing this worksheet, please contact Chaz Leslie at Charles.E.Leslie2@uscg.mil. |
| PERIOD OF PERFORMANCE: BASE PERIOD |
| EFFECTIVE DATE OF CONTRACT AWARD FOR ONE CALENDAR YEAR PERIOD |
| CLIN | ITEM DESCRIPTION | EST QTY | UNIT OF ISSUE | UNIT PRICE | EST AMOUNT |
| 0001 | Field Service Engineer (Short Range | 12 | MO | | $ - 0 |
| Recovery (SRR), OE) | | | | |
| IAW SOW Section 7.1 | | | | |
| 0002 | Field Service Engineer (SRR, AC&I) | 12 | MO | $ - 0 |
| IAW SOW Section 7.1 | | | |
| 0003 | Field Service Engineer (Medium Range | 12 | MO | $ - 0 |
| Recovery (MRR), OE) | | | |
| IAW SOW Section 7.2 | | | |
0004 RESERVED
| 0005 | Program Management (OE) | 12 | MO | $ - 0 |
| IAW SOW Section 6.1.3 | | | |
| 0006 | Travel | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 10.2.2 | | | |
| 0007 | Government Property Reports | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 4.1.1 | | | |
| 0008 | Quarterly Progress Reports | 4 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.3 | | | |
| 0009 | Sustaining Engineering Support | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 6.2.1 | | | |
| 0010 | Monthly Activity Reports | 12 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 7.4.1 | | | |
| 0011 | Equipment | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6 | | | |
| 0012 | Reimbursable Material Costs | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6.1 | | | |
| 0013 | Post Award Conference Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.1 | | | |
| 0014 | Program Review Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.2 | | | |
ESTIMATED TOTAL BASE PERIOD $ - 0
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation HSCG38-18-R-200002 Base Period
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation 70Z03818RB2000002 Base Period
&"Times New Roman,Regular"&12 2
&"Times New Roman,Regular"&12 1
Opt Period 1
| Instructions: Fill in the shaded boxes only. All other numbers will automatically calculate. Use the tabs at the bottom to provide pricing for the base period through option year four. If your company has any additional charges or fees, prompt payment discounts, etc., clearly state what these are in your proposal. If you have any questions when completing this worksheet, please contact Chaz Leslie at Charles.E.Leslie2@uscg.mil. |
| PERIOD OF PERFORMANCE: OPTION PERIOD ONE |
| EFFECTIVE DATE OF CONTRACT AWARD FOR ONE CALENDAR YEAR PERIOD |
| CLIN | ITEM DESCRIPTION | EST QTY | UNIT OF ISSUE | UNIT PRICE | EST AMOUNT |
| 1001 | Field Service Engineer (SRR, OE) | 12 | MO | | $ - 0 |
| IAW SOW Section 7.1 | | | | |
| 1002 | Field Service Engineer (MRR,OE) | 12 | MO | $ - 0 |
| IAW SOW Section 7.2 | | | |
1003 RESERVED
| 1004 | Program Management (OE) | 12 | MO | $ - 0 |
| IAW SOW Section 6.1.3 | | | |
| 1005 | Travel | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 10.2.2 | | | |
| 1006 | Government Property Reports | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 4.1.1 | | | |
| 1007 | Quarterly Progress Reports | 4 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.3 | | | |
| 1008 | Sustaining Engineering Support | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 6.2.1 | | | |
| 1009 | Monthly Activity Reports | 12 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 7.4.1 | | | |
| 1010 | Equipment | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6 | | | |
| 1011 | Reimbursable Material Costs | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6.1 | | | |
| 1012 | Post Award Conference Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.1 | | | |
| 1013 | Program Review Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.2 | | | |
ESTIMATED TOTAL OPTION PERIOD ONE $ - 0
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation HSCG38-18-R-200002 Base Period
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation 70Z03818RB2000002 Option Period One
&"Times New Roman,Regular"&12 2
&"Times New Roman,Regular"&12 2
Opt Period 2
| Instructions: Fill in the shaded boxes only. All other numbers will automatically calculate. Use the tabs at the bottom to provide pricing for the base period through option year four. If your company has any additional charges or fees, prompt payment discounts, etc., clearly state what these are in your proposal. If you have any questions when completing this worksheet, please contact Chaz Leslie at Charles.E.Leslie2@uscg.mil. |
| PERIOD OF PERFORMANCE: OPTION PERIOD TWO |
| EFFECTIVE DATE OF CONTRACT AWARD FOR ONE CALENDAR YEAR PERIOD |
| CLIN | ITEM DESCRIPTION | EST QTY | UNIT OF ISSUE | UNIT PRICE | EST AMOUNT |
| 2001 | Field Service Engineer (SRR, OE) | 12 | MO | | $ - 0 |
| IAW SOW Section 7.1 | | | | |
| 2002 | Field Service Engineer (MRR,OE) | 12 | MO | $ - 0 |
| IAW SOW Section 7.2 | | | |
2003 RESERVED
| 2004 | Program Management (OE) | 12 | MO | $ - 0 |
| IAW SOW Section 6.1.3 | | | |
| 2005 | Travel | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 10.2.2 | | | |
| 2006 | Government Property Reports | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 4.1.1 | | | |
| 2007 | Quarterly Progress Reports | 4 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.3 | | | |
| 2008 | Sustaining Engineering Support | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 6.2.1 | | | |
| 2009 | Monthly Activity Reports | 12 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 7.4.1 | | | |
| 2010 | Equipment | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6 | | | |
| 2011 | Reimbursable Material Costs | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6.1 | | | |
| 2012 | Post Award Conference Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.1 | | | |
| 2013 | Program Review Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.2 | | | |
ESTIMATED TOTAL OPTION PERIOD TWO $ - 0
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation HSCG38-18-R-200002 Base Period
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation 70Z03818RB2000002 Option Period Two
&"Times New Roman,Regular"&12 2
&"Times New Roman,Regular"&12 3
Opt Period 3
| Instructions: Fill in the shaded boxes only. All other numbers will automatically calculate. Use the tabs at the bottom to provide pricing for the base period through option year four. If your company has any additional charges or fees, prompt payment discounts, etc., clearly state what these are in your proposal. If you have any questions when completing this worksheet, please contact Chaz Leslie at Charles.E.Leslie2@uscg.mil. |
| PERIOD OF PERFORMANCE: OPTION PERIOD THREE |
| EFFECTIVE DATE OF CONTRACT AWARD FOR ONE CALENDAR YEAR PERIOD |
| CLIN | ITEM DESCRIPTION | EST QTY | UNIT OF ISSUE | UNIT PRICE | EST AMOUNT |
| 3001 | Field Service Engineer (SRR, OE) | 12 | MO | | $ - 0 |
| IAW SOW Section 7.1 | | | | |
| 3002 | Field Service Engineer (MRR,OE) | 12 | MO | $ - 0 |
| IAW SOW Section 7.2 | | | |
3003 RESERVED
| 3004 | Program Management (OE) | 12 | MO | $ - 0 |
| IAW SOW Section 6.1.3 | | | |
| 3005 | Travel | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 10.2.2 | | | |
| 3006 | Government Property Reports | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 4.1.1 | | | |
| 3007 | Quarterly Progress Reports | 4 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.3 | | | |
| 3008 | Sustaining Engineering Support | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 6.2.1 | | | |
| 3009 | Monthly Activity Reports | 12 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 7.4.1 | | | |
| 3010 | Equipment | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6 | | | |
| 3011 | Reimbursable Material Costs | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6.1 | | | |
| 3012 | Post Award Conference Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.1 | | | |
| 3013 | Program Review Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.2 | | | |
ESTIMATED TOTAL OPTION PERIOD THREE $ - 0
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation HSCG38-18-R-200002 Base Period
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation 70Z03818RB2000002 Option Period Three
&"Times New Roman,Regular"&12 2
&"Times New Roman,Regular"&12 3
Opt Period 4
| Instructions: Fill in the shaded boxes only. All other numbers will automatically calculate. Use the tabs at the bottom to provide pricing for the base period through option year four. If your company has any additional charges or fees, prompt payment discounts, etc., clearly state what these are in your proposal. If you have any questions when completing this worksheet, please contact Chaz Leslie at Charles.E.Leslie2@uscg.mil. |
| PERIOD OF PERFORMANCE: OPTION PERIOD FOUR |
| EFFECTIVE DATE OF CONTRACT AWARD FOR ONE CALENDAR YEAR PERIOD |
| CLIN | ITEM DESCRIPTION | EST QTY | UNIT OF ISSUE | UNIT PRICE | EST AMOUNT |
| 4001 | Field Service Engineer (SRR, OE) | 12 | MO | | $ - 0 |
| IAW SOW Section 7.1 | | | | |
| 4002 | Field Service Engineer (MRR,OE) | 12 | MO | $ - 0 |
| IAW SOW Section 7.2 | | | |
4003 RESERVED
| 4004 | Program Management (OE) | 12 | MO | $ - 0 |
| IAW SOW Section 6.1.3 | | | |
| 4005 | Travel | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 10.2.2 | | | |
| 4006 | Government Property Reports | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 4.1.1 | | | |
| 4007 | Quarterly Progress Reports | 4 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.3 | | | |
| 4008 | Sustaining Engineering Support | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 6.2.1 | | | |
| 4009 | Monthly Activity Reports | 12 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 7.4.1 | | | |
| 4010 | Equipment | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6 | | | |
| 4011 | Reimbursable Material Costs | TBD | EA | To be Determined on Individual Task Orders |
| IAW SOW Section 7.6.1 | | | |
| 4012 | Post Award Conference Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.1 | | | |
| 4013 | Program Review Agenda and Minutes | 1 | EA | NOT SEPARATELY PRICED |
| IAW SOW Section 5.2.1.2 | | | |
| ESTIMATED TOTAL OPTION PERIOD FOUR | $ - 0 |
| ESTIMATED CONTRACT TOTAL | $ - 0 |
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation HSCG38-18-R-200002 Base Period
&"Arial,Bold"Attachment 1 &"Arial,Bold"Solicitation 70Z03818RB2000002 Option Period Four
&"Times New Roman,Regular"&12 2
&"Times New Roman,Regular"&12 3