Pictures
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AMENDMENT_01_-_Questions_and_Government_Reponses.pdf | ||
| FBO_posting_-_Amendment_01.pdf | ||
| STT_Bunker_Attach_4_SF25A-16a_Payment_Bond.pd.pdf | ||
| STT_Bunker_Attach_3_DOL_Wage_Determination_VI1_Building.pdf | ||
| STT_Bunker_Attach_4_SF25-16a_Performance_Bond.pd.pdf | ||
| 70FBR218R00000010_STT_Bunker_Solicitation.pdf | ||
| STT_Bunker_Attach_1_Statement_of_Work_(SOW).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation - 70FBR218R00000010
FEMA St Thomas Bunker Restoration Attachment 2 – SOW Pictures
The attached pictures are for references only. If any discrepancies are found between the Attach 1 – SOW and information found within this document, then the Attach 1 - SOW overrides.
Photo 1 – Task 2
• Repair/Replace damaged gate/fence at second level entry point
Photo 2 – Task 3
• Wall repair and replacement‐The 22’ length of block wall has been compromised and needs to be replaced/repaired with reinforced (rebar and cement) concrete block.
Photo 3 – Task 4
• Addition of catch basin at beginning of driveway/end of drainage grate. Add 3’x3’x2’ concrete catch basin complete with rust proof grill into the existing drainage system.
Photo 4 – Tasks 5, 6, 7, 8
Photo 5 – Task 9
• Remove rust, sand, and paint support beams and exterior doors with Rust Proof metal exterior paint
Photo 6 – Task 10
• Repair exterior wiring and install LED high intensity weatherproof motion detector spotlights
Photo 7 – Tasks 11, 13, 14, 18
Photo 8 – Task 12
• Remove remaining tiles at the entrance; paint/seal concrete floor with textured 100% solid epoxy flooring coating
Photo 9 – Tasks 15 & 16
• Interior overhead vents were observed leaking water during the hurricane. Identify water infiltration source and remedy to avoid future leakage.
• Clean all air‐handlers/ventilation systems and paint with Rust proof paint
Photo 10 – Task 19
• Replace all electrical wall switches with new units including dimmable switches for indoor and outdoor lighting.
Photo 11 – Task 20
• Replace interior & exterior emergency lights with LED replacement units
Photo 12 – Task 21
Photos 13 & 14 – Tasks 24 & 25
• Service Air Conditioning units and ensure they are fully operational.
• Construct an elevated platform and a weather resistant protective ventilated cover for outside air conditioning units.
Photos 15 – Task 26
• Replace existing thermostat with WiFi enabled Nest® thermostat – brand name or equal
Photo 16 – Task 27
• Replace outside ventilation cover with Rust Proof Metal replacement unit (approximately 4’ x1.5’)
| Solicitation - 70FBR218R00000010 |
| Photo 1 – Task 2 |
| Photo 2 – Task 3 |
| Photo 3 – Task 4 |
| Photo 4 – Tasks 5, 6, 7, 8 |
| Photo 5 – Task 9 |
| Photo 6 – Task 10 |
| Photo 7 – Tasks 11, 13, 14, 18 |
| Photo 8 – Task 12 |
| Photo 9 – Tasks 15 & 16 |
| Photo 10 – Task 19 |
| Photo 11 – Task 20 |
| Photo 12 – Task 21 |
| Photos 13 & 14 – Tasks 24 & 25 |
| Photos 15 – Task 26 |
| Photo 16 – Task 27 |
File details come from the government source that posted it.