Attachment 01 PWS - 250 RLC - revised 9-26.pdf
PDF 338 KB Posted
- Attached to
- RESPONDER LODGING CAPSULES DISASTER RESPONSE Federal contract opportunity
- Solicitation number
- 70FA4020R00000031
- Issued by
- Federal Emergency Management Agency
About this file
This performance work statement outlines requirements for responder lodging capsules disaster response services. The contractor shall provide 250 turn-key lodging capsule units containing beds, showers, restrooms and sinks to house FEMA and FEMA-approved responders for up to 60 days at a pre-positioned location in Selma, Alabama. The units must be operational at disaster response camp locations within 48-168 hours depending on the number of units, with all wrap-around support services including catering, laundry, janitorial, waste removal and onsite medical support. The performance period is 60 days for pre-positioning with optional 30-day periods for operational location services. The contractor must meet response times for repairs and comply with all applicable health, safety, security and accessibility standards.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 02 IGCE - 500 RLC - 9-28.xlsx | XLSX spreadsheet | |
| 09-28-2020 Amendment 0005- 70FA4020R00000031.pdf | ||
| 09-28-2020 SOLICITATION 70FA4020R00000031.pdf | ||
| Attachment 01 PWS - 500 RLC - revised 9-28.pdf | ||
| 70FA4020R00000031 0004 (Amendment).pdf | ||
| Pricing Schedule.xlsx | XLSX spreadsheet | |
| SOLICITATION 70FA4020R00000031.pdf | ||
| 70FA4020R00000031 0003.pdf | ||
| 70FA4020R00000031 0002 (Amendment).pdf | ||
| Revised 70FA4020R00000031.pdf | ||
| ATTACHMENT 03 Revised PRICING SCHEDULE.xlsx | XLSX spreadsheet | |
| Attachment 01 Revised 9-22 SOW 250 RLC_09222020.pdf | ||
| QA 70FA4020R00000031 - revised 9-22.pdf | ||
| REVISED QA 70FA4020R00000031 (002).pdf | ||
| QA 70FA4020R00000031 (002).pdf | ||
| 70FA4020R00000031 0001 (Amendment).pdf | ||
| ATTACHMENT 03 PRICING SCHEDULE.xlsx | XLSX spreadsheet | |
| 70FA4020R00000031.pdf | ||
| Attachment 01 SOW 250 RLC - 9-18.pdf | ||
| Attachment 02 SCA Wages.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FOR
RESPONDER LODGING CAPSULES
1.0 BACKGROUND
The Department of Homeland Security (DHS) Federal Emergency Management Agency’s (FEMA) mission is helping people before, during, and after disasters. One of FEMAs’ responsibilities is to ensure the effectiveness of emergency response personnel in responding to emergencies and disasters. Types of disasters and emergencies that could happen in the Continental United States (CONUS), as well as outside the Continental United States (OCONUS) locations include, but are not limited to, hurricanes, floods, earthquakes, cyclones, tornadoes, blizzards, acts of terrorism, tsunamis, and avalanches.
2.0 PURPOSE
The Contractor shall provide 250 turn-key Lodging Capsule units to house FEMA and FEMA-approved responders to be pre-positioned in Selma, Alabama for up to 60 days. Lodging Capsules must be individual sleeping units containing beds, showers, power outlet, restrooms and sinks.
FEMA does not know the exact location of the operational site once mobilized from the prepositioned location. Once activated the units will be transported and set up to a create lodging camps, which will include wrap-around support services including wash and fold laundry, janitorial, equipment, staff, onsite medical unit and catering services. Operational services must include ablution, wastewater, and waste and dumpster services. The site must be demobilized and restored upon the end of the period of performance.
3.0 SCOPE
3.1 Unit Configurations and Requirements
a. Contractor shall furnish 250 private cabin sleeping units* containing beds, showers, toilets and sinks upon award to FEMA for pre-positioning, and forward movement to operational location Units must be equipped with en suite shower, sink, and toilet accommodations.
b. Each Lodging Capsule unit must contain private one-person rooms with locking exterior door, bed, storage for clothing, adequate lighting and a minimum of one (1) standard duplex power outlet in each sleeping area.
c. The Contractor shall have configuration flexibility as to the number of sites that can be supported. Configuration examples include, but are not limited, to one 250-person site or two 125-person sites. Maximum number is 2 sites operating simultaneously.
d. Sinks with mirrors and one (1) duplex power outlet for hairdryers and shaving equipment shall be provided. The Contractor shall ensure showers comply at a minimum with OSHA 29 CFR and 1910 and 29 Code of Federal Regulations (CFR) 1926, as well as Uniform Federal
Accessibility Standards (UFAS). Units shall have hot and cold water and shall be serviced with an American Society of Mechanical Engineers (ASME) rated propane or electric water heater and an anti-scald valve for user safety. Heated water shall be provided at a minimum of 120 degrees Fahrenheit. All showers and sink facilities shall be sanitized daily with a disinfecting solution.
e. New mattresses shall be used and must be Standard Twin 36” W x 75” L x 6”H, or larger, with inner-springs or coils. Zipped mattress covers are acceptable in lieu of new mattresses. Foam mattresses may be substituted if approved in advance by the onsite Contracting Officer Representative (COR) and the Contracting Officer. Sheets and blankets shall be provided according to mattress size.
f. The Contractor shall make best efforts to meet American with Disabilities Act (ADA) requirements and ensure that 5 percent of the units at each site are ADA compliant. Alternative solutions to meet ADA compliancy for the units will be considered.
https://www.ada.gov/2010ADAstandards_index.htm
g. Units shall have under the bed storage space, a closet and desk space. All living quarters shall be equipped with windows the total of which shall not be less than one-tenth of the floor area.
At least one-half of each window shall be so constructed that it can be opened for purposes of ventilation in accordance with OSHA 1910.142(b)(7).
*As these units are expected to be provided upon award to FEMA for the duration of the period of performance, the Principal of the Contractor shall be required to sign a statement verifying that they possess 250 private cabin sleeping units in their on-hand inventory. If the units are being provided by a subcontractor, or other entity other than the prime an agreement outlining the sub and the prime arrangements verifying they’re part of the primes capability to meet the terms of the requirement to the government. This agreement will need to be provided by the Principal of the subcontractor. . If the units are being purchased, but not yet in the Offeror’s inventory, a copy of the sales agreement or suitable document must be provided to indicate the units are ready to be mobilized.
3.2 Transportation of Units to Pre-Positioned Site & Operational Site
For the purposes of this Performance Work Statement (PWS), Contractor provided transportation is defined as all necessary contractor provided/contracted resources required to transport Contractor personnel, equipment and supplies to both suitable pre-designated sites (Selma Al pre-positioned site & Operational/Camp Site(s) (no farther than 300 miles from Selma AL). The Contractor and/or driver shall be responsible for all of their own fuel, meals and wrap around services.
a. The Contractor shall provide all transportation and shuttling of trailers to the site locations as identified by FEMA..
b. The Contractor must maintain enough power units to meet the government’s timelines.
c. The Contractor must maintain operational and wrap-around services to be ready to move forward the units to the operational sites within the timelines prescribed in section 4.1(b).
3.3 Mobilization and Demobilization
a. Site services shall be inclusive of mobilizations, site preparation, installation, management and operations, and demobilization.
b. The Contractor shall be responsible for set up and removal of each site.
3.4 Primary Wrap Around Services for Responder Support Camp
a. Locations shall be completely self-sufficient to include all toiletries, shower curtains, toilet paper, bedding, towels, fuel, water, and power. Locations shall operate 24 hours a day, seven days a week. If two sites are required, all wrap around services will be needed for each individual site.
b. Locations shall have wash and fold laundry for responder clothing and janitorial services provided. Pillows, blanket, sheets and pillowcases shall be provided with each bed. Bedding shall be replaced with a clean set every three calendar days. The Contractor shall support turnover of sleeping units by ensuring each bed is made with fresh linens to all incoming responders. Clean bedding shall be available for exchange, at the request of the responder 24 hours a day, seven days a week.
c. The Contractor shall provide bedding, shower toiletries (bath soap, facial soap, shampoo, conditioner) , shower curtains, toilet paper and hand washing liquid.
d. The Contractor shall provide daily logs to the FEMA COR by 1800. Daily logs shall include:
Daily occupancy counts;
Summary of any technical direction taken by the Contractor;
Summary of daily menu;
Number of meals served per day;
Any billeting issues, reports of any medical issues, communicable disease incidents or food poisoning cases, most current water testing samples (when tested);
Summary of significant changes related to laundry, shower facilities or janitorial issues, update on any contracted solid waste removals (e.g., trash and/or wastewater pickup, etc.)
and/or any identified environmental compliance issues (e.g., any oil spills/clean ups, etc.);
and
The Contractor shall state in report, “no waste transport or environmental compliance issues today” if there is nothing to report.
Any discrepancies in reporting of daily logs shall be corrected by the Contractor at the direction of the COR.
e. The Contractor shall be responsible for ensuring interior temperature between 68-72 degrees Fahrenheit.
f. The Contractor shall provide potable (drinking) water, water purification and manifold distribution systems, toilets, onsite manifold distribution of black and grey water and associated onsite sanitation systems, complete laundry service, trash removal and dumpster service, industrial generators, light towers, fencing and barricades to include maintenance and fuel.
g. The Contractor shall be responsible for any repairs needed. The Contractor has a two-hour inspection and repair window for small repairs and a 10-hour window for major repairs. A small repair is something that can be easily fixed without retrieving any additional parts and do not result in any safety concerns. Major repairs are defined as needing additional parts and/or may involve a third party to resolve. The FEMA COR will have the final say on what is small versus major. If it cannot be repaired, the Contractor shall be responsible for exchanging sleeping and/or other provided accommodations.
3.5 Secondary Wrap Around Services
The Contractor shall provide a dining facility sufficient to support occupancy levels at each lodging Capsule site location.
a. Meal Services and Dining Facility
The Contractor shall provide a dining facility at each Lodging Capsule destination, other than pre-staged locations. which shall meet or exceed OSHA 29 CFR 1910, 29 CFR 1926, and 2006 International Fire Code – Chapter 26 and National Fire Protection Association (NFPA) 101 – Life Safety Code – Chapter 12 – New Assembly occupancy. Hours of operation shall be 0500-2100, seven days a week. All showers and sink facilities shall be sanitized once weekly with a disinfecting solution.
The Contractor shall provide food preparation services capable of providing meals per feeding sufficient to meet Lodging Capsules occupancy levels. All meals shall be prepared in accordance with the Army 14-Day Menu program (or equivalent like the National Interagency Fire Center (NIFC) Mobile Food Services contract http://www.fs.fed.us/fire/contracting/index.htm) and shall be enhanced based on individual chef specialties and skills. The Contractor shall provide three meals per day (breakfast, lunch, and dinner). Breakfast shall be served 0530 am - 0830 am.
Contractor shall provide up to 125 bagged lunches for takeaway by 0530. Lunch meals shall be prepared as “take-away” bagged meals or hot boxed meals. Dinners shall be hot meals served from 1730-2030, seven days a week. The Contractor shall accommodate special meal needs such as vegetarian, vegan, kosher, halal or other special dietary menu needs. Vegetarian meals shall, at a minimum, be prepared for the left-over vegetarian classification level and shall consist of the same quantities and items as regular meals with the exception that no meat, fish, or poultry shall be included. Non-meat protein substitutes shall be in vegetarian sack lunches in lieu of meat, fish or poultry.
Food supplies shall be staged in appropriate storage equipment, dry vans or refrigerated/freezer trailers until prepared. Meal counts for each meal shall be provided to the FEMA National
COR/Task Order COR on a daily basis. The Contractor shall provide a dining facility adequate to feed the Lodging Capsules population within a two-hour window or within a schedule as agreed to by the Contracting Officer via the National COR/Task Order COR. The dining facility shall have adequate seating capacity to accommodate a minimum of 1/3 of the Lodging Capsules occupancy level per location.
The Contractor shall ensure that all personnel entering or working in food preparation and/or serving areas shall follow local and State Health Codes and Regulations (i.e., wearing hairnets or disposable hats, washing hands, etc.). The Contractor shall ensure that food is prepared, stored, served and disposed of in accordance with all local, State, and Federal requirements and is subject to inspections from applicable public health personnel. Single-use, food-grade gloves shall be worn when serving meals.
The Contractor shall ensure that each Mobile Food Service Unit Manager and Supervisory Cook has a current Certificate of Completion for food service management, handling, and sanitation training.
Snacks: Hot coffee, tea, bottled water and assorted snacks shall be made available twenty-four hours per day.
b. Meal Payment
The Contractor is also authorized to provide meals to authorized holders of Lodging Capsule Non- Occupant Visitor identification cards. These meals must be provided on a self-pay basis and the Contractor shall accept payment directly from the authorized Lodging Capsule visitors. No costs associated with providing this service shall be passed on to FEMA.
c. Sanitation Inspections
In addition to evaluations by the National COR/FEMA Safety, Health and Medical Readiness (SHMR) HMR representatives shall have access to the kitchen and dining area(s) to check for compliance with sanitation standards as required by local, State, and Federal regulations. This access shall be provided prior to the commencement of operations and randomly throughout the operations of the facilities.
The cleanliness of each space and related equipment shall be measured by means of the Food Service Sanitation Ordinance and Code, Part V of the Food Service Sanitation Manual, U.S. Public Health Service Publication 934 (1965) and all other applicable Federal, State, and local standards and requirements. When a food establishment exceeds critical violation limits, the establishment may be shut down until required sanitation standards are restored. The Contractor shall be responsible for any and all costs associated with closure due to the Contractor’s failure to maintain acceptable sanitation standards. The Contractor must have a plan in place to immediately mitigate deficiencies (e.g. remove food) upon notification of violation of regulations and complete remedy the situation within 24 hours.
d. Hand-Washing Stations
The Contractor is responsible to ensure that the hand wash stations remain stocked with water (hot and/or cold), hand soap and paper towels throughout the dining period. Hand sanitizing stations may be used in addition to hand-washing stations. Service shall be included in the wrap around services optional task price.
e. Morale Welfare and Recreation (MWR)
MWR services will not be required due to current COVID environment.
f. Medical Support
The Contractor shall provide a medical unit staffed with, at a minimum, medical personnel certified in Advance Cardiac Life Support (ACLS) procedures 24 hours a day, 7 days a week, unless directed otherwise by the CO. The medical unit shall be licensed in the location they have been requested to establish the camp in. The Medical Unit shall be equipped to provide basic care for minor illness and injury; this shall include dispensing of common over the counter medications.
Medical conditions that the medical unit must be prepared to respond to include but are not limited to frostbite, hypothermia, heat stroke and other conditions brought on by extreme temperature conditions. Medical personnel shall provide medical services to occupants and contractor employees 24 hours a day, seven days a week and ability to maintain applicable personnel medical records as required for such services. The Medical unit must also provide sufficient, dedicated refrigerated storage space and/or other controls for occupant medication.
The Contractor shall immediately notify the agency point of contact of any occupant injuries or illnesses requiring any level of documentation and shall forward completed forms (to include all required information on the accident or illness, including medical documentation, fund code and type of hire (Ex: RSV, PFT, CORE, OFA etc.) to FEMA management via the agency’s point of contact within 24 hours of the notice to the Agency.
g. Cleaning and Disinfecting in accordance with GSA and CDC Guidelines
Provide enhanced cleaning services at least once daily, in response to COVID-19 following the current GSA Cleaning and Disinfecting Procedures as well as CDC Guidelines.
The contractor shall provide all management, supervision, labor, administrative support, materials, tools, parts, supplies, equipment and transportation necessary to perform all services and achieve all required performance levels as described herein. Services are to be provided in accordance with the specifications and information contained below.
Enhanced Building Cleaning and Disinfecting in accordance with GSA and CDC Guidelines
This scope is intended to be used in a facility or portion of a facility where additional cleaning and disinfection are needed during the Novel Coronavirus SARS-CoV-2 pandemic (additional routine cleaning and disinfection).
1. The contractor shall wear disposable gloves (e.g., latex, nitrile, etc..), and any other personal protective equipment (PPE) as recommended by the cleaning and disinfectant product manufacturer.
2. The contractor shall clean all visibly dirty surfaces using general detergents or cleaning products compatible with the surface materials being cleaned and in accordance with directions provided by the product manufacturer.
3. The contractor shall wipe down all solid, high contact surfaces using a disinfectant from the EPA-registered list of products identified as effective against Novel Coronavirus SARS-CoV-2 (see list) , or other product containing the same active ingredient(s) at the same or greater concentration than those on the list. Contractor shall use the product in accordance with directions provided by the manufacturer. Examples of solid, high contact surfaces include but are not limited to: handrails, doorknobs, key cards, light switches, countertops, water faucets and handles, work surfaces, computer keypads and mouse, elevator buttons, sinks, toilets and control handles, restroom stall handles, toilet paper and other paper dispensers, door handles and push plates, water cooler and drinking fountain controls. Disinfected surfaces should be allowed to air dry.
Detailed Cleaning and Disinfection of a facility directly impacted by a Novel Coronavirus SARS- CoV-2 event.
This scope is intended to be used in a facility or portions of a facility directly impacted by a Novel Coronavirus SARS-CoV-2 event. An impacted facility is one where one or more individuals meeting the following criteria have been in the facility:
The individual(s) has a confirmed or suspected COVID-19 illness, or
The individual(s) is ill and has traveled to a location of community disease outbreak within the past 14 days, or
The individual(s) is ill and has been in direct contact with someone confirmed to have COVID-19.
1. The contractor performing this work shall be experienced in performing microbial-related remediation or similar work (e.g., crime scene cleanup, mold abatement, etc.). Contractor staff shall at minimum have current training in blood-borne pathogens, as defined by
OSHA (29 C.F.R. 1910.1030).
2. The contractor shall submit to the Contracting Officer’s Representative or their designee for review and approval, any proposed disinfectants, prior to use. All cleaners and disinfectants shall be used in accordance with the manufacturer’s recommendations.
3. Prior to entering the area, the contractor shall don appropriate personal protective equipment (PPE) required for the specific cleaners and disinfectants used. At minimum, contractors shall wear nitrile, latex or similar non-cloth disposable gloves.
4. The contractor shall clean any visible dirt or debris from all surfaces using cleaning or detergent products compatible with the surfaces being cleaned. Products shall be used in accordance with the manufacturer’s directions.
5. Following cleaning, the contractor shall disinfect all solid, high contact surfaces with either a product identified by EPA as effective against Novel Coronavirus SARS-CoV- 2 (see
Link to EPA) or other product containing the same active ingredient(s) in the same or greater concentration as one on the list. Solid, high contact surfaces include but are not limited to: handrails, door knobs, key cards, light switches, countertops, water faucets and handles, work surfaces, computer keypads and mouse, elevator buttons, sinks, toilets and control handles, restroom stall handles, toilet paper and other paper dispensers, door handles and push plates, water cooler and drinking fountain controls. Disinfectant fogging or ionizing spray applications are not required, but may be used under the following conditions: the disinfectant meets the requirements just described, the application is performed according to the manufacturer’s recommendation including worker protection, and the application will not damage surface materials in the area.
6. The contractor shall apply sufficient disinfectant on solid, high contact surfaces such that the surfaces are visibly damp. The disinfectant shall be left to air dry on the surfaces.
7. When cleaning and disinfecting of the area is complete, the contractor shall remove and dispose of cloths, gloves, any other PPE and other cleaning and disinfecting waste materials and dispose of in a sealed plastic trash bag. Trash may be disposed of as ordinary waste.
Contractor must supply PPE for three FEMA staff who will monitor the work being completed within the facility.
4.0 PERFORMANCE REQUIREMENTS
4.1 Activation/Period of Performance
The Contractor shall mobilize and establish operations along the following timeline:
a) Pre-Positioning of Units - All 250 Contractor units will be pre-positioned at their own location or at the FEMA designated location in Selma, AL, (to be decided by FEMA) within 240 hours of task order award. Longer staging timelines will be considered if the Contractor cannot meet this deadline, but the units must be pre-positioned no later than 320 hours. Units will be pre-positioned up to 60 days.
b) Lodging Capsule units must be operational at the designed responder support camp operational locations within the below timelines, plus transportation time from staging location to operational location. Therefore, the Wrap-Around services must be ready to be activated within the following timelines as well.
1. 50 Units within 48 hours
2. 100 Units within 72 hours
3. 250 Units within 168 hours
The Period of Performance for this contract will be a 60 Day period for pre-positioning, with optional 30-day periods for operational location services.
4.2 Hours of Operation
a. All locations shall operate 24 hours a day, seven days a week.
4.3 Communication
a. The Contractor shall ensure that communications are established and maintained between personnel and the Government throughout the duration of support services.
4.4 Staffing and Equipment
Management for all beds on site. This management shall include coordination with staff and senior leaders requesting the sites documented procedures, daily accountability, monitoring, direction, and synchronized actions needed for operating, sustaining, and managing an existing base camp. Provide lighting and signage as required.
DAILY LOGS
The Contractor shall maintain daily camp logs. Copies of the logs shall be made available to the CO/COR and FEMA CONUS RSC Coordinator. Daily logs shall include, but not be limited to:
ꞏ Daily occupancy counts;
ꞏ Summary of any technical direction provided by the National COR/Task Order COR and contractor action taken;
ꞏ Occupant list including name, agency, date and room number
ꞏ Any billeting issues;
ꞏ Maintenance reports to include, room numbers, type of issue and repair times
ꞏ Summary of any significant issues
a. The Contractor shall staff the sites with billeting specialists to establish, operate, and manage the site 24 hours a day. Billeting shall include check in and check of occupants. The Contractor must also include two key personnel: 1) Onsite Manager and 2) Repairman. The Onsite Manager shall be responsible for the performance of work. The name of this person, and an alternate(s), who shall act for the Contractor on all contract matters relating to the operation of this contract. The Onsite Manager shall also be responsible for the management (generation, transport and disposal) of any onsite generated solid waste (e.g., municipal trash, grey water from showers, waste oil, etc.). The Onsite Manager shall provide a documented waste disposal documents to the COR for FEMA’s historical records. The Repairman shall maintain and repair machines, mechanical equipment and buildings, fix or replace faulty electrical switches, outlets and circuit breakers, inspect and diagnose problems and figure out the best way to correct them, and perform routine preventive maintenance to ensure that machines and equipment continue to run smoothly.
b. Key Personnel may travel between sites, as well as any additional staff needed to manage and operate each location.
4.5 Key Personnel Requirements
a. Certain skilled experienced professional and/or technical personnel are essential for successful Contractor accomplishment of the work to be performed under the contract. These are defined as "Key Personnel" and are those persons whose resumes were submitted for evaluation of the proposal. The Contractor agrees that such personnel shall not be removed from the contract or replaced without compliance with paragraphs (b) and (c) hereof.
b. If one or more of the key personnel for whatever reason becomes, or is expected to become, unavailable for work under the contract for a continuous period exceeding ten calendar days, or is expected to devote substantially less effort to the work than indicated in the proposal or initially anticipated, the Contractor shall immediately notify the CO and shall, subject to the concurrence of the CO or his/her authorized representative, promptly replace such personnel with personnel of at least substantially equal ability and qualifications.
c. All requests for approval of substitutions hereunder must be in writing and provide a detailed explanation of the circumstances necessitating the proposed substitutions. They must contain a complete resume for the proposed substitute, and any other information requested or needed by the CO to approve or disapprove the proposed substitution. The CO or his/her authorized representative will evaluate such requests and promptly notify the Contractor in writing of his approval or disapproval thereof.
d. If the CO determines that suitable and timely replacement of key personnel who have been reassigned, terminated or have otherwise become unavailable for the contract is not reasonably forthcoming, or that the resultant reduction of productive effort would be so substantial as to impair the successful completion of the contract or the services ordered, the contract may be terminated at the discretion of the CO for default or for the convenience of the Government, as appropriate, if he/she finds the Contractor at fault for the condition. The contract price may be equitably adjusted downward to compensate the Government for any resultant delay, loss, or damage, and liquidated damages may be imposed.
The following individuals are defined as Key Management Personnel:
TITLE NAME
Onsite Manager Repairman
It is not required that the Contractor provide personnel with these exact titles, rather the collection of Contractor personnel shall meet the functional requirements consistent with the PWS.
4.6 Conduct
a. Contractor employees shall not access any area that is not pertinent or necessary to the fulfillment of their duties in accomplishing this contract. Contractor employees shall adhere to all instructions and warnings, communicated or posted, regarding their work area and the facilities that occupy this area.
4.7 Inspections
a. Contractor performance shall be inspected by the COR 100% for contract compliance.
PERFORMANCE REQUIREMENTS SUMMARY
PRS
No.
Performance Requirement Performance Threshold Inspection Method
1 250 units arrive at pre-positioned location
Within 240 Hours 100% visual inspection
2 Maintain availability for 250 units to be moved while stationed at Selma, Al.
100% of Units ready to be moved within two hours
100% visual inspection
3 Set up operational camps 1. 50 Units within 48 hours
2. 100 Units within 72 hours
3. 250 Units within 168 hours
100% visual inspection
4 Environmental Safety and Health Security Inspection EEO/ADR for
ADA
Must meet OSHA, Environmental Compliance (legislative) National Historic Preservation and ADA Requirements, State and Local Law
100% visual inspection
5 Provide response time as stated for repairs
Within 2 hours of notification of problem (small repair) and within 10 hours if major repair
100% visual inspection
6 Emergency Site Demobilization and Site Restoration
Within 24 hours of receiving CO notification in emergency demobilization procedures
100% visual inspection
7 Daily Log Submitted in accordance with Section 3.2.d
Reviewed daily by
COR
5.0 GOVERNMENT FURNISHED PROPERTY/EQUIPMENT/SERVICES
a. As necessary for all facilities, the Government will furnish land and be responsible for the site lease. The site conditions may vary significantly.
b. Security will be provided by the Government. The Government reserves the right to provide any other equipment or services to support operations.
6.0 CONTRACTOR FURNISHED EQUIPMENT AND SUPPLIES
To the maximum extent practical, the Contractor shall furnish all other supplies, equipment and personnel to accomplish the requirements listed in the PWS. The Contractor shall comply with environmental purchasing regulations and Presidential Executive Order 13423 when acquiring products and services in performance of the contract. Specifically, the Contractor shall acquire bio-based, environmentally preferable, energy-efficient, water-efficient, and recycled-content products, and use paper of at least 30 percent post-consumer fiber content.
7.0 SAFETY STANDARDS
The lodging Capsules , laundry, shower, common and meal areas units shall be kept in compliance with applicable OSHA rules in 29 CFR Part 1926 & 29 CFR 1910, specifically 29 CFR 1910.142 Environmental Protection Agency (EPA) regulations outlined in 40 CFR and all other local, state and Federal regulatory standards and conditions for safety, health, and environmental management.
7.1 Code Adherence/Compliance Report
a. The Contractor is responsible for adherence to applicable Federal, state, territorial, commonwealth and local regulations and laws. This includes, but is not limited to, all local, state, territorial and commonwealth Occupational Safety Health and Environmental Management Department regulations, the 2006 International Building Code, 2006 International Fire Code – Chapter 24 and NFPA 101 – Life Safety Code for the occupancies being constructed.
b. FEMA will support the Contractor’s efforts to expedite the permit process responsible for obtaining all required permits prior to acceptance. The Contractor shall notify the Contracting Officer and COR immediately if the circumstances raise any concerns about the Contractor’s ability to obtain the necessary permits. In addition, throughout all phases of the responder support lifecycle, the Contractor shall comply with all applicable local, State, territorial, commonwealth, and Federal rules and regulations associated with the operation of support systems and operate within the conditions of any permits obtained or applied for. This includes, but is not limited to, the operation of potable water systems, wastewater treatment systems, collection, storage, and disposal of hazardous and regulated waste, and collection and disposal of solid waste.
c. The Contractor shall be responsible for meeting manufacturer recommend installation specifications. The Contractor shall perform a local code review of the jurisdictional area where the Lodging Capsule is located and implement any requirements determined to be more stringent than the National Codes indicated in this PWS. A written compliance report shall be provided to the Government upon completion of this code review within seven days of the award or seven days form the identified operating camp. This is not needed at staging.
d. Access and Functional Needs: The Contractor shall be responsible for accommodating individuals with functional needs. This includes, at a minimum, the application of Uniform Federal Accessibility Standards (UFAS) along with any other Federal, state, territorial, commonwealth or local regulations. The facilities within the Lodging Capsule units that must meet these standards include, but are not limited to, billeting areas, administrative areas, restrooms, shower facilities and hand-washing stations. 5 percent of the facility must meet the UFSA standard.
e. Automatic External Defibrillators: Automatic External Defibrillators (AEDs) shall be placed in all areas of assembly (i.e., dining facility, MWR, billeting, etc.). AEDs shall be in proximity to the main entrance door and be marked with a large predominant sign.
f. Restroom Facilities: The Contractor shall provide en suite restroom facilities with flushing toilets to each single bedroom or one shared toilet between two bedrooms to ensure compliance with all applicable OSHA 29 CFR 1910 and 29 CFR 1926 standards and requirements and all other Federal, state, and local requirements. These units shall be designed and certified for use by the Portable Sanitation Association International. All wastewater shall be collected with vacuum trucks and transported offsite and disposed at permitted treatment facilities. When available, public utilities shall be utilized. In addition to each unit having a restroom, the Contractor shall provide eight outside restrooms for use.
g. Shower Facilities: The Contractor shall provide en suite shower facilities and curtains, one per single bedroom or one shared shower between two bedrooms to ensure compliance at a minimum with OSHA 29 CFR 1910 and 29 CFR 1926 as well as UFAS standards. Units shall have hot and cold water and shall be serviced with an ASME rated propane water heater and an anti-scaled valve for user safety. Heated water shall be provided at a minimum of 120 degrees Fahrenheit 24/7. Shower cleaning solution shall be provided for daily disinfecting of shower areas by the tenants if they so choose. In addition to each unit having a shower, the Contractor shall provide eight outside showers for use.
h. Handwashing Facilities: The Contractor shall provide en suite sinks, one per single bedroom or one shared sink between two bedrooms in accordance with 29 CFR 1910 or 29 CFR 1926 requirements. Sinks with mirrors and outlets for hairdryers and shaving equipment shall be provided. The Contractor shall also furnish sufficient hand-washing stations at each entrance to the dining area (if one is requested for activation) for personnel to use prior to entering, ensuring compliance at a minimum with OSHA 29 CFR 1910 and 29 CFR 1926. Personnel shall not have to wait in line for more than five minutes to use a hand-washing station.
i. Linen Services: The Contractor shall provide laundry services and shall ensure that clean, fresh linens and towels are available daily upon request by each occupant. This includes all towels for showers, bedding and any linens for the dining facility. These basic services shall be provided to all occupants and shall be included in the daily contract price.
j. Laundry Services: A drop and fold service for occupants’ personal laundry shall be available for daily drop-off and pick-up. Laundry shall be done separately and individually for sanitation concerns. Drop off and pick up service for occupants shall be provided twice a week with a maximum 48-hour turn-around time. Service shall be included in wrap around services base price. Laundry units do not have to be on site. The Contractor is also authorized to provide self-pay drop off and pick-up laundry service to authorized holders of Non-Occupant Visitor Identification cards. This service must be provided on a self-pay basis and the Contractor shall accept payment directly from the authorized visitors. No costs associated with providing this service shall be passed on to FEMA.
k. Fencing and Barricades: The Contractor shall provide fencing and barricades around the perimeter of terrestrial lodging area as set forth in the contract. The Contractor shall also provide fencing and barricades around areas which are “off limits” to occupants. Fencing and barricades are required within 48 hours for “phased” setup timeframes, and 72 hours for the rest of the initial setup timeframe. This is to ensure the health and safety of occupants. Fences, barriers, and implemented separation mechanisms shall comply with Federal, state, commonwealth, territorial, and other local regulations as applicable. Building codes, and regulations, as well as any applicable FEMA security requirements as defined by the Joint Field Office (JFO) Security Officer. All fences or barriers shall comply as a minimum with the requirements set forth in UFAS or the Americans with Disabilities Act or other Federal, state, commonwealth, territorial and or the local requirements. For non-territorial solutions such as barges or ships, the Contractor shall provide fencing and barricades to secure the entrance of the Lodging Capsule site.
l. The contractor shall be responsible for providing lighting solutions for the sites outdoors areas and will maintain all light towers or other equipment used to provided lighted areas after dark.
m. FEMA COR, Logistics and Safety must have access to all camp areas 24/7 for no-notice inspection purposes with no limitations.
8.0 Operation and Demobilization of Sites/Equipment Inventory List
The Contractor shall have the capability to provide assets that can be expanded and reduced based on mission needs of the population. The Contractor shall provide an Equipment Inventory Report weekly to the Contracting Officer and COR. The Equipment Inventory Report shall include all equipment used to erect and operate the Lodging Capsule site. The report shall state if the equipment is owned/leased. The Contractor shall have sufficient equipment available for rapid deployment and preventative maintenance programs to ensure optimum equipment readiness levels always.
a. Power and HVAC Units: The Contractor shall provide power and HVAC as required to power the requirements of the Lodging Capsules. Available site utilities shall be specified in each task order. Temporary power and HVAC, when needed, shall be provided via mobile diesel generators and heating and cooling units sized to support the facility as required. Units shall be self-contained, and mobile and over the road transportable. Units shall be sound attenuated with noise levels rated at no higher than 69 dBA and a reasonable distance from the billeting to allow for proper sleep of occupants. Panels and transformers shall be placed as required by the site configuration. Distribution shall be provided with cam lock connectors and sized to applications. GFCI outlet boxes shall be placed throughout the facility as design requires.
Wherever cabling crosses roadways or pedestrian areas, cable ramps shall be used for safety and protection. All electrical equipment shall be Underwriters Laboratories (UL) Listed and rated for National Electrical Manufacturers Association (NEMA) 3R and 4 applications.
Electrical systems shall be installed to National Electrical Codes (NEC) standard by licensed electrical personnel. When required, HVAC shall be provided for all structures in sufficient capacities to meet different environmental conditions. All mobile HVAC units shall be operated on a digital thermostat control.
b. Environmental Control: The Contractor shall ensure that all facilities within the Lodging Capsule site are equipped with reverse cycle (Heat and A/C) Environmental Control Units (ECUs) or comparable environmental control system capable of maintaining the ambient temperature inside the facilities between 68-72 degrees Fahrenheit. Camp shall have adequate drainage in accordance with OSHA 1910.142(a)(1) and shall be of adequate size in accordance with OSHA 1910.142(a)(2).
c. Ablution: The Contractor shall provide a potable water supply, en suite restroom with flushing toilet, shower, and sink, laundry services, and wastewater collection systems at each Lodging Capsule location. All water supply equipment shall be rated for potable water supply in accordance with ANSI/NSF 42, 53, & 61 standards and applicable EPA and state and local regulations for potable water. Water systems shall be operated in accordance with all Federal, state and local standards and requirements. Water Quality samples shall be obtained as required by the EPA and analyzed at a state certified lab for compliance with Safe Drinking Water Act requirements. All water resting reports shall be provided or emailed to the COR and Contracting Officer within 48 hours of request and within 48 hours after testing.
d. Wastewater: The Contractor shall ensure that wastewater from showers, laundry, hand-washing stations, restroom/toilet facilities and any other source shall be collected into pump stations and pumped to storage tanks. All on-site wastewater shall be collected. Vacuum trucks shall maintain a service schedule to remove the wastewater from the tanks and transport offsite to dispose of at a permitted treatment facility. The collection and use of graywater for an-site purposes may be permitted if authorized by local authorities and implemented via a contract modification. Use of Containerized On-Site Wastewater Systems may be used if authorized by the Contracting Officer through the National COR. When available, public utilities shall be utilized.
e. Solid Waste Collection and Disposal (Dumpsters): The Contractor shall provide all necessary solid waste collection and disposal for the Lodging Capsule sites in accordance with EPA 40 CFR 243 and any additional state, and local regulations at least once per day. Lodging Capsule Contractors shall establish recycling programs in accordance with Presidential Executive Order 13423 and have a goal to recycle 35% of waste generated from Lodging Capsule operations. Collections shall be maintained in a clean and sanitary condition free from rubbish, debris, wastepaper, garbage, or other refuse. Items recycled must include at a minimum the following:
Toner cartridges Batteries
Scrap metal Fluorescent light bulbs Paper (white paper, mixed paper, newspaper) Cardboard Aluminum Wood pallets Plastic Glass
f. Janitorial Services: The Contractor shall provide janitorial services for all components of the
Lodging Capsules. Clean provide shall be GREEN low Volatile Organic Compound (VOC) emitting and meet the requirements found on the General Services Administration (GSA) approved list. Safety Data Sheets (SDS) shall be provided to the safety official. All sleeping areas shall be cleaned once per week or more frequently if needed. Contractor shall make beds during weekly cleaning and each time a unit is turned over from previous occupant. The room shall be disinfected upon each change of occupancy. The Contractor shall provide the cleaning products and supplies needed to maintain the sanitary environment.
g. Site Restoration: The Contractor shall demobilize the Lodging Capsule units, clean the site, grade soil (if required), remove/dispose of all garbage and used materials and return the site to its original condition, minus reasonable wear and tear, within seven days of the demobilization notice. The Contractor shall meet any special conditions established in the Environmental Health Perspective (EHP) review process for the return of the site to its original conditions.
h. Demobilization or Site Relocation: The Contractor shall have the capability to demobilize or relocate the site outside of harm’s way for immediate redeployment when a threatening situation puts the Lodging Capsule units or responders at risk. The Contractor shall be capable of demobilization or moving assets within 24 hours after receiving Contracting Officer’s notification. All associated costs for time and travel from the disaster incident after demobilization of Lodging Capsules must be incorporated into the overall demobilization costs.
9.0 DELIVERABLES
The Contractor shall prepare the deliverables below and submit them to the entities specified in the chart:
Deliverable Item
PWS
REF
TYPE WHAT TO INCLUDE
HOW
OFTEN/WHEN
TO WHO
3.2.d
Daily Log
Daily Occupancy Counts Summary of any technical direction provided by the National COR/Task Order COR and Contractor action taken •Results of water testing
Daily
CO,
National COR and Task Order
COR
samples (when tested) •Summary of the daily menu •Number of meals served per meal per day •Number, type, and severity of medical incidents •Summary of any significant OCONUS RSC daily laundry services, cleaning of shower facilities, janitorial
2 7.1 Written Compliance Report
Compliance with codes of jurisdictional area Implementation of requirements determined to be more stringent than the National Codes indicated in this Statement of Work (see Code Adherence)
Within 7 days of task order award after completion of jurisdictional code review
CO, ACO
3 7.2 Equipment Inventory
All equipment (itemized used to erect and operate the
OCONUS RSC
Whether the equipment is owned/leased
Weekly CO
10.0 SECURITY
10.1 Background Investigations
All contractor personnel who require access to DHS or FEMA information systems, routine access to DHS or FEMA facilities, or access to sensitive information, including but not limited to Personally Identifiable Information (PII), shall be subject to a full background investigation commensurate with the level of the risk associated with the job function or work being performed.
FEMA’s Personnel Security Division (PSD) will determine the risk designation for each contractor position by comparing the functions and duties of the position against those of a same or similar federal position, applying the same standard for evaluating the associated potential for impact on the integrity and efficiency of federal service.
Low Risk without Information System Access Contractor personnel occupying positions or performing functions with a Low Risk designation and who do not require access to DHS or FEMA information systems may undergo a Tier 1 investigation with a credit check and must receive a favorable adjudication thereof from FEMA PSD prior to performing work under this contract. (Also reference Facility Access).
Low Risk with Information System Access
Contractor personnel occupying positions or performing functions with a Low Risk designation and who require access to DHS or FEMA information systems shall undergo a Tier 2 Suitability Background Investigation (T2) and must receive a favorable adjudication thereof from FEMA PSD prior to performing work under this contract.
Moderate Risk Contractor personnel occupying positions or performing functions with a Moderate Risk designation shall undergo a Tier 2 Suitability Background Investigation (T2) and must receive a favorable adjudication thereof from FEMA PSD prior to performing work under this contract.
High Risk Contractor personnel occupying positions or performing functions with a High Risk designation shall undergo a Tier 4 Suitability Background Investigation (T4) and must receive a favorable adjudication thereof from FEMA PSD prior to performing work under this contract.
Background Investigation Process To initiate the request to process contractor personnel, the Contractor shall provide the FEMA Contracting Officer’s Representative (COR) with all required information and comply with all necessary instructions to complete Section II of the FEMA Form 121-3-1-6, “Contract Fitness/Security Screening Request.” The FEMA COR shall ensure that all other applicable sections of the FEMA Form 121-3-1-6 are complete prior to submitting the form to FEMA PSD for processing. The Contractor shall also provide the FEMA COR with completed OF 306, “Declaration for Federal Employment,” forms for all contractor personnel.
Contractor personnel who already have a favorably adjudicated background investigation, may be eligible to perform work under this contract without further processing by FEMA PSD if:
the investigation was completed within the last five years, it meets or exceeds the minimum requirement for the position they will occupy or functions they will perform on this contract, the contractor personnel have not had a break in employment since the prior favorable adjudication, and, FEMA PSD has verified the investigation and confirmed that no new derogatory information has been disclosed which may require a reinvestigation.
FEMA PSD will notify the COR of the names of the contractor personnel eligible to work based on prior, favorable adjudication. The COR will, in turn, notify the Contractor of the names of the favorably adjudicated contractor personnel, at which time the favorably adjudicated contractor personnel will be eligible to begin work under this contract.
For those contractor personnel who do not have an acceptable, prior, favorable adjudication or who otherwise require reinvestigation, FEMA PSD will issue an electronic notification via email directly to the contractor applicant/personnel that contains the following documents, which are incorporated into this contract by reference, along with a link to the Office of Personnel Management’s (OPM) Electronic Questionnaires for Investigation Processing (e-QIP) system and instructions for submitting the necessary information:
Standard Form 85P, “Questionnaire for Public Trust Positions” Optional Form 306, “Declaration for Federal Employment” SF 87, “Fingerprint Card” (2 copies) DHS Form 11000-6, “Non-Disclosure Agreement” DHS Form 11000-9, “Disclosure and Authorization Pertaining to Consumer Reports Pursuant to the Fair Credit Reporting Act”
FEMA PSD will only accept complete packages consisting of all of the above document and Standard Form 85P, which must be completed electronically through the Office of Personnel Management’s e-QIP system.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .