2.2.1_UPDATED DRAFT_Attachment 2_Cost and Pricing Summary.xlsx

XLSX spreadsheet 214 KB Posted

Attached to
Port Isabel Detention Center - Draft RFP Federal contract opportunity
Solicitation number
70CDCR21R00000007
Issued by
Immigration and Customs Enforcement

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

[Offeror Name]
[Date]
Attachment 2 - Pricing Template

Please see RFP Section L, Price Quotation, for complete instructions.

In accordance with RFP Section L, the offeror shall complete Attachment 2: Pricing Template of this RFP and return it with their price quote submission.
All pricing proposed prices will used as the contract price.
The following instructions shall be used in completing the Pricing Template Tabs.
1) "1. Total Evaluated Price" tab - Offerors are to propose prices for all CLINs. Offerors shall utilize the relevant CLIN estimated quantities to estimate the cost associated with each CLIN. Quantities listed are estimates and shall be utilized for evaluating purposes only. CLIN X0004 does not require vendor input as the price of $1 is set in accordance with PBNDS 2011 with 2016 revisions. The yellow shaded areas to be completed as needed.
2) "2. Section B" tab - Pricing from tab 1 will be utilized to fill out Section B. Section B quantities represent that maximum value of that CLIN and the total price of each CLIN shall represent the maximum for that CLIN. Option Period 2 has included 1 extra day for Leap Day.
3) For tabs "3. BOE X001A Detention Tier 1", “4. BOE X0001A Detention Tier2”, "5. BOE X0001B Variable Tier 1" , “6. BOE X0001B Detention Tier 2”, "7. BOE X002", "8.BOE X003a", "9.BOE X003b", and "10. BOE 0005," Offerors shall propose their Basis of Estimates (BOE) for each CLIN. The BOE are to be used to support the CLIN pricing indicated and will be used to ensure the Offerors understand the requirement. Offerors shall include all the proposed staff and total costs proposed and identify if a DoL WD or CBA applies to each position proposed. For all other expenses and profit, Offerors are to list each unique cost or profit separately, provide a detail description, quantity required, unit price, and total cost proposed. The BOE should be filled out for each period of performance (Base and all Option Periods). Offerors can modify the tabs, as needed. Offerors that provide limited information may be determined to lack understanding of the requirement.

On each of these tabs, Offerors must show the calculations used to arrive at the proposed unit price.

For X0001A Fixed, the Offeror shall propose Detention Services/Food Services/Consummables costs which are fixed for providing services for a monthly Average Detainee Population (ADP) of 650 and a monthly ADP of 650-1,175 detainees. Food for transfers and releases should be included in this price. The price will be considered firm fixed price.

For X0001B Variable, the Offeror shall propose a bed day rate per detainee based on the variable costs associated with housing a monthly ADP of 650 and a monthly ADP of 650-1,175 detainees

Monthly ADP is calculated by the number of beds occupied each evening/per day, totaled and averaged for the month.

4) "11. Summary of Wage Data" - Offeror shall provide a summary of all proposed staff for all option periods to which a DoL WD or CBA applies.
5) Offerors may submit a separate 5 page maximum pricing narrative in word format to provide a pricing narrative.
6) Failure to follow these instructions and/or fully provide the Price/Cost proposal Volume III information in accordance with this Attachment and the solicitation in the prescribed format may result in the Offeror’s disqualification from the competition.

1. Total Evaluated Price Total Evaluated Price (Based on Estimated Quantities)

Base Period (12 months)(Includes 2-month transition):
CLINDescriptionUnitEstimated QTYUnit CostTotal
0001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO10$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO10$0.00
0001bVariable Price Bed Day Rate (BDR) for ADP of 650
Detention Services/Food Services/ConsumablesEA198,250$0.00$0.00
Variable Price for BDR ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA137,250$0.00
0002On-Call Stationary Guard ServicesHR290$0.00$0.00
0003aTransportation - LaborMO10$0.00$0.00
0003bTransportation - MileageMiles (DH)150,000$0.00$0.00
0004Detainee Work ProgramEA60,000$1.00$60,000.00
0005TransitionMO2$0.00$0.00
Total Base Period$60,000.00
Option Period 1 (12 months):
CLINDescriptionUnitQTYUnit CostTotal
1001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO12$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO12$0.00
1001bVariable Price BDR for ADP of 650
Detention Services/Food Services/ConsumablesEA237,250$0.00$0.00
Variable Price for BDR ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA164,250$0.00
1002On-Call Stationary Guard ServicesHR350$0.00$0.00
1003aTransportation - LaborMO12$0.00$0.00
1003bTransportation - MileageMiles (DH)180,000$0.00$0.00
1004Detainee Work ProgramEA72,000$1.00$72,000.00
Total Option Period 1$72,000.00
Option Period 2 (12 months):
CLINDescriptionUnitQTYUnit CostTotal
2001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO12$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO12$0.00
2001bVariable Price BDR for ADP of 650
Detention Services/Food Services/ConsumablesEA237,900$0.00$0.00
Variable Price for BDR ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA164,700$0.00
2002On-Call Stationary Guard ServicesHR350$0.00$0.00
2003aTransportation - LaborMO12$0.00$0.00
2003bTransportation - MileageMiles (DH)180,000$0.00$0.00
2004Detainee Work ProgramEA72,000$1.00$72,000.00
Total Option Period 2$72,000.00
Option Period 3 (12 months):
CLINDescriptionUnitQTYUnit CostTotal
3001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO12$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO12$0.00
3001bVariable Price BDR for ADP of 650
Detention Services/Food Services/ConsumablesEA237,900$0.00$0.00
Variable Price for BDR ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA164,700$0.00
3002On-Call Stationary Guard ServicesHR350$0.00$0.00
3003aTransportation - LaborMO12$0.00$0.00
3003bTransportation - MileageMiles (DH)180,000$0.00$0.00
3004Detainee Work ProgramEA72,000$1.00$72,000.00
Total Option Period 3$72,000.00
Option Period 4 (12 months):
CLINDescriptionUnitQTYUnit CostTotal
4001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO12$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO12$0.00
4001bVariable Price BDR for ADP of 650
Detention Services/Food Services/ConsumablesEA237,900$0.00$0.00
Variable Price for BDR ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA164,700$0.00
4002On-Call Stationary Guard ServicesHR350$0.00$0.00
4003aTransportation - LaborMO12$0.00$0.00
4003bTransportation - MileageMiles (DH)180,000$0.00$0.00
4004Detainee Work ProgramEA72,000$1.00$72,000.00
Total Option Period 4$72,000.00
FAR 52.217-8 (6 months) (Not to be filled out by vendor; Table autopopulates based on above values)
CLINDescriptionUnitQTYUnit CostTotal
5001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO6$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO6$0.00
5001bVariable Price BDR for ADP of 650
Detention Services/Food Services/ConsumablesEA237,900$0.00
Variable Price for BDR ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA164,700$0.00
5002On-Call Stationary Guard ServicesHR175$0.00$0.00
5003aTransportation - LaborMO6$0.00$0.00
5003bTransportation - MileageMiles (DH)90,000$0.00$0.00
5004Detainee Work ProgramEA36,000$1.00$36,000.00
Total FAR 52.217-8 Period$36,000.00
Total Values
(Not to be filled out by vendor; autopopulates)
Base Period$60,000.00
Option Period 1$72,000.00
Option Period 2$72,000.00
Option Period 3$72,000.00
Option Period 4$72,000.00
Total Contract Amount$348,000.00
FAR 52.217-8$36,000.00
Total Evaluated Price$384,000.00

2. Section B Section B (Based on Maximum Quantities)

Base Period (12 months)(Includes 2-month transition):
CLINDescriptionUnitQTYUnit CostTotal
0001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO10$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO10$0.00
0001bVariable Price for ADP of 650
Detention Services/Food Services/ConsumablesEA198,250$0.00$0.00
Variable Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA160,125$0.00
0002On-Call Stationary Guard ServicesHR400$0.00$0.00
0003aTransportation - LaborMO10$0.00$0.00
0003bTransportation - MileageMiles (DH)187,500$0.00$0.00
0004Detainee Work ProgramEA83,000$1.00$83,000.00
0005TransitionMO2$0.00$0.00
Total Base Period$83,000.00
Option Period 1 (12 months):
CLINDescriptionUnitQTYUnit CostTotal
1001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO12$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO12$0.00
1001bVariable Price for ADP of 650
Detention Services/Food Services/ConsumablesEA237,250$0.00$0.00
Variable Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA191,625$0.00
1002On-Call Stationary Guard ServicesHR500$0.00$0.00
1003aTransportation - LaborMO12$0.00$0.00
1003bTransportation - MileageMiles (DH)225,000$0.00$0.00
1004Detainee Work ProgramEA100,000$1.00$100,000.00
Total Option Period 1$100,000.00
Option Period 2 (12 months):
CLINDescriptionUnitQTYUnit CostTotal
2001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO12$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO12$0.00
2001bVariable Price for ADP of 650
Detention Services/Food Services/ConsumablesEA237,900$0.00$0.00
Variable Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA192,150$0.00
2002On-Call Stationary Guard ServicesHR500$0.00$0.00
2003aTransportation - LaborMO12$0.00$0.00
2003bTransportation - MileageMiles (DH)225,000$0.00$0.00
2004Detainee Work ProgramEA100,000$1.00$100,000.00
Total Option Period 2$100,000.00
Option Period 3 (12 months):
CLINDescriptionUnitQTYUnit CostTotal
3001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO12$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO12$0.00
3001bVariable Price for ADP of 650
Detention Services/Food Services/ConsumablesEA237,250$0.00$0.00
Variable Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA191,625$0.00
3002On-Call Stationary Guard ServicesHR500$0.00$0.00
3003aTransportation - LaborMO12$0.00$0.00
3003bTransportation - MileageMiles (DH)225,000$0.00$0.00
3004Detainee Work ProgramEA100,000$1.00$100,000.00
Total Option Period 3$100,000.00
Option Period 4 (12 months):
CLINDescriptionUnitQTYUnit CostTotal
4001aFixed Price for ADP of 650
Detention Services/Food Services/ConsumablesMO12$0.00$0.00
Fixed Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesMO12$0.00
4001bVariable Price for ADP of 650
Detention Services/Food Services/ConsumablesEA237,250$0.00$0.00
Variable Price for ADP of 651-1,175
Detention Services/Food Services/ConsumablesEA191,625$0.00
4002On-Call Stationary Guard ServicesHR500$0.00$0.00
4003aTransportation - LaborMO12$0.00$0.00
4003bTransportation - MileageMiles (DH)225,000$0.00$0.00
4004Detainee Work ProgramEA100,000$1.00$100,000.00
Total Option Period 4$100,000.00
Total Values
(Not to be filled out by vendor; autopopulates)
Base Period$83,000.00
Option Period 1$100,000.00
Option Period 2$100,000.00
Option Period 3$100,000.00
Option Period 4$100,000.00
Total Maximum Amount of Contract$483,000.00

3. BOE X001A Detention Tier I

Base YearOption Year 1Option Year 2Option Year 3Option Year 4
Contractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee Classifications
Position DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or Price
Other Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit Proposed
Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)

4. BOE 0001A Detention Tier 2

Base YearOption Year 1Option Year 2Option Year 3Option Year 4
Contractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee Classifications
Position DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or Price
Other Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit Proposed
Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)

5. BOE X0001B Detention Tier I

Base YearOption Year 1Option Year 2Option Year 3Option Year 4
Contractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee Classifications
Position DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or Price
Other Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit Proposed
Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)

6. X001B Detention Tier II

Base YearOption Year 1Option Year 2Option Year 3Option Year 4
Contractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee Classifications
Position DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or Price
Other Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit Proposed
Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)

7. BOE X002

Base YearOption Year 1Option Year 2Option Year 3Option Year 4
Contractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee Classifications
Position DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or Price
Other Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit Proposed
Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)

8. BOE X003a

Base YearOption Year 1Option Year 2Option Year 3Option Year 4
Contractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee Classifications
Position DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or Price
Other Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit Proposed
Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)

9. BOE X003b

Base YearOption Year 1Option Year 2Option Year 3Option Year 4
Contractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee ClassificationsContractor Proposed Employee Classifications
Position DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or PricePosition DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or Price
Other Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit ProposedOther Direct Costs/Indirect Costs Profit Proposed
Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)Expense NameDetail DescriptionQuantity RequiredUnit Price ( if Applcable)Total Price (if Applicable)

10. BOE 0005 Transition

Proposed Direct Labor
Position DescriptionNumber of StaffDoes CBA /SCA Apply?CBA or WD Number (if applicable)Proposed Hourly RateHealth & WelfareTotal Cost or Price
Other Direct Costs/Indirect Costs/ Profit Proposed
Expense NameDetail DescriptionQuantity Required (if applicable)Unit Price ( if Applcable)Total Price (if Applicable)
Yes
No

11. Summary Wage Data

Summary of all Contractor Proposed Wage Data
Position DescriptionNumber of StaffDoL or CBA NumberProposed Hourly RateHealth & WelfareFully Burdened Rate
BASE YEAR

OPTION YEAR 1

OPTION YEAR 2

OPTION YEAR 4

OPTION YEAR 4

File details come from the government source that posted it. Updated .