7_Rework_And_Repair_ES7034.pdf

PDF 290 KB Posted

Attached to
F-15 Initiators Federal contract opportunity
Solicitation number
FA8213-23-R-5008
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

This document outlines rework and repair procedures for nonconforming materials on federal contracts. The contractor must document rework procedures and submit them to the Government Quality Assurance Representative for review before implementing. Repair procedures require submission of a Request for Deviation/Waiver to the Contracting Officer for written approval. For any rework or repair submission, the contractor must include a description of the original nonconformance and corrective actions to prevent recurrence. The procedure must also specify a reinspection process taking precedence over technical data and providing assurance that reworked or repaired items meet requirements. Rework and repair requirements flow down to all subcontractors and suppliers.

The related federal contract opportunity is a solicitation from the Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base for F-15 initiators.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 5

(ES7034)

REWORK AND REPAIR OF NONCONFORMING MATERIAL

Jan 2012 (version)

(a) Rework and Repair are defined as follows:

(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.

(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.

(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.

(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.

(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.

(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.

(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.

(End of clause)