Virtulal Pre-Show TX FW LGA 10(5).pptx

PPTX presentation 8 MB Posted

Attached to
TX FW LGA 10(5) Steve Thompson Wildlife Drive
Solicitation number
6982AF27B000006
Issued by

About this file

This file is a virtual pre-bid conference presentation for Federal Highway Administration solicitation 6982AF27B000006, titled "TX FW LGA 10(5) Steve Thompson Wildlife Drive," scheduled for October 8, 2026. The Central Federal Lands Highway Division (FHWA-CFLHD) is the lead agency for design, acquisitions, and construction, with Contracting Officer Jorey Deml overseeing the project. The solicitation is designated as a Small Business Set-Aside with bids valid for 60 days after bid opening. Bid bonds (originals only) are required, and the Buy American Act applies. The project is located at Laguna Atascosa National Wildlife Refuge in Cameron County, Texas, approximately 25 miles east of Harlingen, Texas, and includes work on Steve Thompson Wildlife Drive and Bayside Drive.

The scope of work involves rehabilitating existing roadways through full-depth reclamation of chip seal and gravel materials, adding new aggregate surface course, installing an aluminum gate, constructing a concrete pad, installing permanent safety signage, and adding speed bumps. Three alternate bid items for aggregate surface course tonnage will be evaluated, with only one awarded: Alternate 1 provides 2-inches of aggregate surfacing terminating at Renee's Overlook Parking Area; Alternate 2 provides 2-inches without the parking area terminus; and Alternate 3 provides 3-inches terminating at the parking area. Environmental restrictions include limiting construction to daylight hours (30 minutes after sunrise to 30 minutes before sunset), enforcing a 20 mph vehicle speed limit, conducting mandatory one-hour wildlife protection training, prohibiting night work, and obtaining temporary traffic control permits from TxDOT. Davis-Bacon Act wage rates apply to this project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TX FW LGA 10(5)

TX FW LGA 10(5) Steve Thompson Wildlife Drive Virtual Pre-bid Conference October 8, 2026

Agenda Introductions Discussion Questions

Introductions - sign in sheet Project presentation – 8-9 Field Site Visit - 9-12 drive most of the site up to the road failure, from there we can walk the rest of the project or can also be visited separately by driving around the open section of loop road, gauge interest from contractors at meeting on best option

Introductions Central Federal Lands Highway Division - Lead agency for design, acquisitions, construction, and construction engineering Contracting Officer – Jorey Deml Contract Specialist – Doug Whitcomb Project Manager – Emilio Burgos Construction Operations Engineer – Grant Matlock

Stakeholders Federal Highway Administration Central Federal Lands Highway Division (FHWA-CFLHD) Lead Agency for Design & Construction Laguna Atascosa National Wildlife Refuge Facility ownership and maintenance responsibilities

Important Considerations All verbal statements, answers to questions, and discussions during this presentation are preliminary, unofficial, and non-binding upon the Government.

Nothing said during this session alters or supersedes the terms, conditions, specifications, or requirements set forth in the solicitation documents.

To be binding, any official response, clarification, or modification from the Government must be provided in writing by the Contracting Officer via a formal solicitation amendment.

Solicitation Small Business Set-Aside Deadline for Questions Site Visit Wage Rate Determination (Davis-Bacon Act) Bids are valid for 60 days after bid opening Bid Bonds – originals only Buy American Act Evaluation & Award Criteria (Bid Alternates)

Location

Scope Steve Thompson Wildlife Drive & Bayside Drive Rehabilitate existing roadway

Aggregate surfacing

Permanent signage

Speed bumps

Concrete pad and utility conduit

Existing Conditions

Proposed Roadway

Schedule Contract completion

Environmental Limit construction working hours to daylight hours 30 minutes after sunrise to 30 minutes before sunset

Limit speed of vehicles to 20 mph or less

All staff will participate in a 1-hour training on protecting wildlife

Traffic Control No night work is allowed

Bayside Drive and Steve Thompson Wildlife Drive may be closed

Keep all entrance gates closed and utilize gate monitors

Obtain permits with TxDOT for temporary traffic control signs on General Grant Highway

Questions TX FW LGA 10(5) Steve Thompson Wildlife Drive Virtual Pre-bid Conference October 8, 2026 image2.png image3.png image4.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png image19.png image20.png image1.png