Bid Tabulation CA PRA LABE 10(1) Main Road.pdf

PDF 673 KB Posted

Attached to
CA PRA LABE 10(1) Main Road Federal contract opportunity
Solicitation number
6982AF21B000029
Issued by
Department of Transportation Federal Highway Administration

About this file

This document contains a bid tabulation report and related federal contract opportunity solicitation for the CA PRA LABE 10(1) Main Road project. The bid tabulation report evaluates three bids received by the deadline of December 1, 2021 to rehabilitate, restore, and resurface approximately 28.8 kilometers of Main Road and associated parking areas within the Lava Beds National Monument in California. The lowest responsive bidder was Hat Creek Construction & Materials, Inc. at $10,582,799 for the base schedule, with options to add additional road segments and a parking area. The engineer's estimate was $12,441,200 for the base schedule. The related solicitation provides additional details on the project scope, which involves 3R work including minor widening, drainage improvements, and concrete work along the 17.9 mile roadway corridor. The solicitation was issued by the Federal Highway Administration with number 6982AF21B000029.

View the file

Other files for this federal contract opportunity

Other files attached to CA PRA LABE 10(1) Main Road, newest first.
File Type Posted
Bid Opening Summary CA PRA LABE 10(1).pdf PDF
QnA 11.30.2021.pdf PDF
QnA 11.29.2021.pdf PDF
A002.pdf PDF
A001 CA PRA LABE.pdf PDF
QnA 10.25.21 CA PRA LABE.pdf PDF
6982AF21B000029.pdf PDF
LABE 10(1) - plan set.pdf PDF
CA PRA LABE 10(1) Lava Beds Main Road Pavement Memo.pdf PDF
FINAL LABE 10(1)_Site Visit Geotech Obsv.pdf PDF
fp-03met.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 12/07/21

1 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Contractor Responsive?

Engineer's Estimate

Hat Creek Construction & Materials, Inc.

Herback General Engineering, LLC

Base Schedule A

$12,441,200.00

$10,582,799.00

$15,652,531.38

Option: V

$2,115,000.00

$1,595,317.00

$2,522,486.17

Option: Y

$1,136,010.00

$485,318.00

$613,185.56

Contractor Responsive?

Engineer's Estimate

Hat Creek Construction & Materials, Inc.

Herback General Engineering, LLC

Option: Z

$620,300.00

$722,555.00

$585,908.80

2 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Contractor Responsive?

Engineer's Estimate

Hat Creek Construction & Materials, Inc.

Herback General Engineering, LLC

Total Base Schedule A and Option(s): V

$14,556,200.00

$12,178,116.00

$18,175,017.55

Total Base Schedule A and Option(s): VY

$15,692,210.00

$12,663,434.00

$18,788,203.11

Total Base Schedule A and Option(s): VYZ

$16,312,510.00

$13,385,989.00

$19,374,111.91

Contractor Responsive?

Engineer's Estimate

Hat Creek Construction & Materials, Inc.

Herback General Engineering, LLC

Total Base Schedule A and Option(s): VZ

$15,176,500.00

$12,900,671.00

$18,760,926.35

Total Base Schedule A and Option(s): Y

$13,577,210.00

$11,068,117.00

$16,265,716.94

Total Base Schedule A and Option(s): YZ

$14,197,510.00

$11,790,672.00

$16,851,625.74

3 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Contractor Responsive?

Engineer's Estimate

Hat Creek Construction & Materials, Inc.

Herback General Engineering, LLC

Total Base Schedule A and Option(s): Z

$13,061,500.00

$11,305,354.00

$16,238,440.18

4 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF21B000029

Division: Central Federal Lands

State: CA County: Modoc, Siskiyou

Federal Land: Lava Beds National Monument Opened at: Lakewood, CO

Opened by: Sheri Walsh

Date: 12/01/21

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Hat Creek Construction & Materials, Inc. $10,582,799.00 24339 Highway 89 N Burney, CA 96013

Herback General Engineering, LLC $15,652,531.38 2531 Nowlin Road Minden, NV 89423

Engineer's Estimate $12,441,200.00

Contract Specialist

12/07/2021

5 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1000 15101-0000 Mobilization

Hat Creek Construction & Materials, Inc. Lump Sum $1,055,000.00 Herback General Engineering, LLC Lump Sum $1,520,800.00 Engineer's Estimate ALL LPSM Lump Sum $1,252,822.20

A1020 15210-3000 Centerline, verification and staking

Hat Creek Construction & Materials, Inc. $1,500.00 $38,133.00 Herback General Engineering, LLC $5,040.00 $128,126.88 Engineer's Estimate 25.422 km $1,650.00 $41,946.30

A1040 15215-3000 Survey and staking, drainage structure

Hat Creek Construction & Materials, Inc. $1,350.00 $2,700.00 Herback General Engineering, LLC $1,230.00 $2,460.00 Engineer's Estimate 2 Each $2,000.00 $4,000.00

A1060 15215-7000 Survey and staking, parking area

Hat Creek Construction & Materials, Inc. $3,370.00 $43,810.00 Herback General Engineering, LLC $3,880.00 $50,440.00 Engineer's Estimate 13 Each $15,000.00 $195,000.00

A1080 15301-0000 Contractor quality control

Hat Creek Construction & Materials, Inc. Lump Sum $645,206.00 Herback General Engineering, LLC Lump Sum $322,000.00 Engineer's Estimate ALL LPSM Lump Sum $325,000.00

A1100 15401-0000 Contractor testing

Hat Creek Construction & Materials, Inc. Lump Sum $745,000.00 Herback General Engineering, LLC Lump Sum $247,000.00 Engineer's Estimate ALL LPSM Lump Sum $600,000.00

A1120 15501-0000 Construction schedule

Hat Creek Construction & Materials, Inc. Lump Sum $20,000.00 Herback General Engineering, LLC Lump Sum $12,300.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

6 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1140 15703-1500 Soil erosion control, temporary soil tackifier

Hat Creek Construction & Materials, Inc. $7,232.00 $18,080.00 Herback General Engineering, LLC $18,600.00 $46,500.00 Engineer's Estimate 2.500 ha $13,834.60 $34,586.50

A1160 15705-0100 Soil erosion control, silt fence

Hat Creek Construction & Materials, Inc. $50.00 $5,000.00 Herback General Engineering, LLC $35.00 $3,500.00 Engineer's Estimate 100 m $20.00 $2,000.00

A1180 15705-1400 Soil erosion control, sediment log

Hat Creek Construction & Materials, Inc. $85.00 $4,250.00 Herback General Engineering, LLC $31.00 $1,550.00 Engineer's Estimate 50 m $40.00 $2,000.00

A1200 15801-0000 Watering for dust control

Hat Creek Construction & Materials, Inc. $0.15 $11,250.00 Herback General Engineering, LLC $1.53 $114,750.00 Engineer's Estimate 75,000 m3 $6.50 $487,500.00

A1220 20301-1900 Removal of pipe culvert

Hat Creek Construction & Materials, Inc. $1,250.00 $2,500.00 Herback General Engineering, LLC $1,310.00 $2,620.00 Engineer's Estimate 2 Each $5,000.00 $10,000.00

A1240 20302-1700 Removal of paved waterway, asphalt

Hat Creek Construction & Materials, Inc. $18.00 $2,700.00 Herback General Engineering, LLC $20.75 $3,112.50 Engineer's Estimate 150 m $35.00 $5,250.00

A1260 20303-1600 Removal of pavement, asphalt

Hat Creek Construction & Materials, Inc. $15.00 $112,500.00 Herback General Engineering, LLC $5.95 $44,625.00 Engineer's Estimate 7,500 m2 $19.00 $142,500.00

7 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1280 20303-3000 Removal of sidewalk, asphalt

Hat Creek Construction & Materials, Inc. $24.00 $12,000.00 Herback General Engineering, LLC $5.95 $2,975.00 Engineer's Estimate 500 m2 $20.00 $10,000.00

A1300 20402-0000 Subexcavation

Hat Creek Construction & Materials, Inc. $155.00 $155,000.00 Herback General Engineering, LLC $157.00 $157,000.00 Engineer's Estimate 1,000 m3 $300.00 $300,000.00

A1320 20420-0000 Embankment construction

Hat Creek Construction & Materials, Inc. $45.00 $58,500.00 Herback General Engineering, LLC $39.00 $50,700.00 Engineer's Estimate 1,300 m3 $100.00 $130,000.00

A1340 25101-2000 Placed riprap, class 2

Hat Creek Construction & Materials, Inc. $300.00 $1,500.00 Herback General Engineering, LLC $364.00 $1,820.00 Engineer's Estimate 5 m3 $550.00 $2,750.00

A1360 30306-2500 Pulverizing, 125mm depth

Hat Creek Construction & Materials, Inc. $6.50 $1,217,450.00 Herback General Engineering, LLC $4.70 $880,310.00 Engineer's Estimate 187,300 m2 $8.00 $1,498,400.00

A1380 30802-2000 Roadway aggregate, method 2

Hat Creek Construction & Materials, Inc. $75.00 $46,875.00 Herback General Engineering, LLC $104.00 $65,000.00 Engineer's Estimate 625 t $75.00 $46,875.00

A1400 40101-5600 Superpave pavement, 12.5mm or 19mm nominal maximum size aggregate, 0.3 to <3 million ESAL

Hat Creek Construction & Materials, Inc. $125.00 $4,250,000.00 Herback General Engineering, LLC $285.85 $9,718,900.00 Engineer's Estimate 34,000 t $132.00 $4,488,000.00

8 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1440 40105-3000 Antistrip additive, type 3

Hat Creek Construction & Materials, Inc. $460.00 $184,000.00 Herback General Engineering, LLC $1.40 $560.00 Engineer's Estimate 400.0 t $890.00 $356,000.00

A1480 40920-1000 Fog seal, emulsified asphalt grade CSS-1 or CSS-1h, SS-1 or SS-1h

Hat Creek Construction & Materials, Inc. $1,350.00 $135,000.00 Herback General Engineering, LLC $678.00 $67,800.00 Engineer's Estimate 100 t $1,100.00 $110,000.00

A1500 41105-0000 Blotter

Hat Creek Construction & Materials, Inc. $30.00 $51,000.00 Herback General Engineering, LLC $95.00 $161,500.00 Engineer's Estimate 1,700 t $115.00 $195,500.00

A1520 41201-1000 Tack coat grade CSS-1, CSS-1h, SS-1, or SS-1h

Hat Creek Construction & Materials, Inc. $790.00 $150,100.00 Herback General Engineering, LLC $895.00 $170,050.00 Engineer's Estimate 190 t $1,500.00 $285,000.00

A1540 50101-0900 Reinforced rigid pavement, 200mm depth, type C smoothness/roughness

Hat Creek Construction & Materials, Inc. $350.00 $140,000.00 Herback General Engineering, LLC $256.00 $102,400.00 Engineer's Estimate 400 m2 $285.00 $114,000.00

A1560 60110-0000 Concrete coloring agent

Hat Creek Construction & Materials, Inc. $28.00 $21,560.00 Herback General Engineering, LLC $14.00 $10,780.00 Engineer's Estimate 770 kg $11.00 $8,470.00

A1580 60201-0600 450mm pipe culvert

Hat Creek Construction & Materials, Inc. $1,000.00 $6,000.00 Herback General Engineering, LLC $607.00 $3,642.00 Engineer's Estimate 6 m $1,000.00 $6,000.00

9 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1600 60210-0600 End section for 450mm pipe culvert

Hat Creek Construction & Materials, Inc. $400.00 $800.00 Herback General Engineering, LLC $850.00 $1,700.00 Engineer's Estimate 2 Each $800.00 $1,600.00

A1620 60403-0000 Inlet

Hat Creek Construction & Materials, Inc. $12,500.00 $25,000.00 Herback General Engineering, LLC $7,000.00 $14,000.00 Engineer's Estimate 2 Each $10,000.00 $20,000.00

A1640 60801-0500 Paved waterway, type 5

Hat Creek Construction & Materials, Inc. $155.00 $10,075.00 Herback General Engineering, LLC $123.00 $7,995.00 Engineer's Estimate 65 m2 $400.00 $26,000.00

A1660 60902-1000 Curb and gutter, concrete, 300mm depth

Hat Creek Construction & Materials, Inc. $400.00 $70,000.00 Herback General Engineering, LLC $253.00 $44,275.00 Engineer's Estimate 175 m $175.00 $30,625.00

A1680 61501-0100 Sidewalk, concrete

Hat Creek Construction & Materials, Inc. $215.00 $107,500.00 Herback General Engineering, LLC $166.00 $83,000.00 Engineer's Estimate 500 m2 $175.00 $87,500.00

A1700 61504-1000 Accessibility ramp, concrete

Hat Creek Construction & Materials, Inc. $2,000.00 $50,000.00 Herback General Engineering, LLC $180.00 $4,500.00 Engineer's Estimate 25 m2 $350.00 $8,750.00

A1720 61509-0000 Detectable warning panels

Hat Creek Construction & Materials, Inc. $370.00 $29,600.00 Herback General Engineering, LLC $225.00 $18,000.00 Engineer's Estimate 80 m2 $400.00 $32,000.00

10 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1740 62201-0200 Dump truck, 8 cubic meter minimum capacity

Hat Creek Construction & Materials, Inc. $135.00 $16,200.00 Herback General Engineering, LLC $195.00 $23,400.00 Engineer's Estimate 120 Hour $175.00 $21,000.00

A1760 62201-0450 Backhoe loader, 120 liter minimum rated capacity bucket, 450mm width

Hat Creek Construction & Materials, Inc. $135.00 $16,200.00 Herback General Engineering, LLC $180.00 $21,600.00 Engineer's Estimate 120 Hour $195.00 $23,400.00

A1780 62201-0900 Wheel loader, 2 cubic meter minimum rated capacity

Hat Creek Construction & Materials, Inc. $190.00 $22,800.00 Herback General Engineering, LLC $250.00 $30,000.00 Engineer's Estimate 120 Hour $225.00 $27,000.00

A1800 62201-2800 Motor grader, 2.4 meter minimum blade

Hat Creek Construction & Materials, Inc. $210.00 $25,200.00 Herback General Engineering, LLC $250.00 $30,000.00 Engineer's Estimate 120 Hour $250.00 $30,000.00

A1820 62201-3100 Hydraulic excavator, 2.2 cubic meter minimum capacity bucket, 125kW minimum flywheel power

Hat Creek Construction & Materials, Inc. $180.00 $21,600.00 Herback General Engineering, LLC $250.00 $30,000.00 Engineer's Estimate 120 Hour $230.00 $27,600.00

A1840 62202-1000 Materials transfer vehicle

Hat Creek Construction & Materials, Inc. Lump Sum $95,000.00 Herback General Engineering, LLC Lump Sum $161,700.00 Engineer's Estimate ALL LPSM Lump Sum $175,000.00

A1860 62301-0000 General labor

Hat Creek Construction & Materials, Inc. $80.00 $24,000.00 Herback General Engineering, LLC $98.00 $29,400.00 Engineer's Estimate 300 Hour $90.00 $27,000.00

11 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1880 62302-1100 Special labor, hired survey services

Hat Creek Construction & Materials, Inc. $187.00 $18,700.00 Herback General Engineering, LLC $290.00 $29,000.00 Engineer's Estimate 100 Hour $285.00 $28,500.00

A1900 63404-0200 Pavement markings, type B

Hat Creek Construction & Materials, Inc. $12.75 $51,000.00 Herback General Engineering, LLC $14.75 $59,000.00 Engineer's Estimate 4,000 l $27.75 $111,000.00

A1920 63405-0050 Pavement markings, symbols

Hat Creek Construction & Materials, Inc. $125.00 $2,625.00 Herback General Engineering, LLC $145.00 $3,045.00 Engineer's Estimate 21 Each $950.00 $19,950.00

A1940 63501-1000 Temporary traffic control, traffic and safety supervisor

Hat Creek Construction & Materials, Inc. Lump Sum $100,000.00 Herback General Engineering, LLC Lump Sum $128,663.00 Engineer's Estimate ALL LPSM Lump Sum $225,000.00

A1960 63502-1050 Temporary traffic control, tubular marker

Hat Creek Construction & Materials, Inc. $30.00 $6,000.00 Herback General Engineering, LLC $80.00 $16,000.00 Engineer's Estimate 200 Each $50.00 $10,000.00

A1980 63502-1300 Temporary traffic control, drum

Hat Creek Construction & Materials, Inc. $75.00 $17,625.00 Herback General Engineering, LLC $136.00 $31,960.00 Engineer's Estimate 235 Each $85.00 $19,975.00

A2000 63502-1600 Temporary traffic control, warning light type B

Hat Creek Construction & Materials, Inc. $500.00 $1,000.00 Herback General Engineering, LLC $835.00 $1,670.00 Engineer's Estimate 2 Each $260.00 $520.00

12 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A2020 63503-0300 Temporary traffic control, barricade type 3

Hat Creek Construction & Materials, Inc. $200.00 $3,600.00 Herback General Engineering, LLC $373.00 $6,714.00 Engineer's Estimate 18 m $350.00 $6,300.00

A2040 63504-1000 Temporary traffic control, construction sign

Hat Creek Construction & Materials, Inc. $300.00 $16,200.00 Herback General Engineering, LLC $640.00 $34,560.00 Engineer's Estimate 54 m2 $300.00 $16,200.00

A2060 63505-1000 Temporary traffic control, pavement markings

Hat Creek Construction & Materials, Inc. $1,700.00 $82,960.00 Herback General Engineering, LLC $1,310.00 $63,928.00 Engineer's Estimate 48.8 km $850.00 $41,480.00

A2080 63506-0500 Temporary traffic control, flagger

Hat Creek Construction & Materials, Inc. $80.00 $384,000.00 Herback General Engineering, LLC $109.00 $523,200.00 Engineer's Estimate 4,800 Hour $87.75 $421,200.00

A2100 63506-0600 Temporary traffic control, pilot car

Hat Creek Construction & Materials, Inc. $100.00 $240,000.00 Herback General Engineering, LLC $130.00 $312,000.00 Engineer's Estimate 2,400 Hour $125.00 $300,000.00

A2120 63602-6020 System installation, traffic detector wire loop

Hat Creek Construction & Materials, Inc. $5,000.00 $10,000.00 Herback General Engineering, LLC $25,000.00 $50,000.00 Engineer's Estimate 2 Each $12,500.00 $25,000.00

Total Schedule - All Items

Hat Creek Construction & Materials, Inc. $10,582,799.00 Herback General Engineering, LLC $15,652,531.38 Engineer's Estimate $12,441,200.00

13 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: V

Schedule Type: Options

Solcitation No: 6982AF21B000029

Division: Central Federal Lands

State: CA County: Modoc, Siskiyou

Federal Land: Lava Beds National Monument Opened at: Lakewood, CO

Opened by: Sheri Walsh

Date: 12/01/21

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Hat Creek Construction & Materials, Inc. $1,595,317.00 24339 Highway 89 N Burney, CA 96013

Herback General Engineering, LLC $2,522,486.17 2531 Nowlin Road Minden, NV 89423

Engineer's Estimate $2,115,000.00

14 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: V

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

V1000 15101-0000 Mobilization

Hat Creek Construction & Materials, Inc. Lump Sum $157,000.00 Herback General Engineering, LLC Lump Sum $380,589.00 Engineer's Estimate ALL LPSM Lump Sum $226,344.75

V1020 15210-3000 Centerline, verification and staking

Hat Creek Construction & Materials, Inc. $1,500.00 $5,472.00 Herback General Engineering, LLC $5,040.00 $18,385.92 Engineer's Estimate 3.648 km $1,650.00 $6,019.20

V1040 15215-7000 Survey and staking, parking area

Hat Creek Construction & Materials, Inc. $2,370.00 $2,370.00 Herback General Engineering, LLC $8,740.00 $8,740.00 Engineer's Estimate 1 Each $15,000.00 $15,000.00

V1060 15301-0000 Contractor quality control

Hat Creek Construction & Materials, Inc. Lump Sum $57,000.00 Herback General Engineering, LLC Lump Sum $50,255.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00

V1080 15401-0000 Contractor testing

Hat Creek Construction & Materials, Inc. Lump Sum $68,700.00 Herback General Engineering, LLC Lump Sum $51,050.00 Engineer's Estimate ALL LPSM Lump Sum $125,000.00

V1100 15501-0000 Construction schedule

Hat Creek Construction & Materials, Inc. Lump Sum $5,000.00 Herback General Engineering, LLC Lump Sum $3,506.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

V1120 15703-1500 Soil erosion control, temporary soil tackifier

Hat Creek Construction & Materials, Inc. $7,250.00 $3,625.00 Herback General Engineering, LLC $18,600.00 $9,300.00 Engineer's Estimate 0.500 ha $13,834.60 $6,917.30

15 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: V

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

V1140 15705-1400 Soil erosion control, sediment log

Hat Creek Construction & Materials, Inc. $80.00 $720.00 Herback General Engineering, LLC $31.00 $279.00 Engineer's Estimate 9 m $40.00 $360.00

V1160 15801-0000 Watering for dust control

Hat Creek Construction & Materials, Inc. $0.15 $2,250.00 Herback General Engineering, LLC $1.53 $22,950.00 Engineer's Estimate 15,000 m3 $6.50 $97,500.00

V1180 20302-1700 Removal of paved waterway, asphalt

Hat Creek Construction & Materials, Inc. $18.00 $4,320.00 Herback General Engineering, LLC $20.75 $4,980.00 Engineer's Estimate 240 m $35.00 $8,400.00

V1200 20402-0000 Subexcavation

Hat Creek Construction & Materials, Inc. $155.00 $31,000.00 Herback General Engineering, LLC $157.00 $31,400.00 Engineer's Estimate 200 m3 $300.00 $60,000.00

V1220 30306-2500 Pulverizing, 125mm depth

Hat Creek Construction & Materials, Inc. $6.00 $210,000.00 Herback General Engineering, LLC $4.70 $164,500.00 Engineer's Estimate 35,000 m2 $8.00 $280,000.00

V1240 30802-2000 Roadway aggregate, method 2

Hat Creek Construction & Materials, Inc. $75.00 $42,750.00 Herback General Engineering, LLC $104.00 $59,280.00 Engineer's Estimate 570 t $75.00 $42,750.00

V1260 40101-5600 Superpave pavement, 12.5mm or 19mm nominal maximum size aggregate, 0.3 to <3 million ESAL

Hat Creek Construction & Materials, Inc. $130.00 $715,000.00 Herback General Engineering, LLC $250.00 $1,375,000.00 Engineer's Estimate 5,500 t $132.00 $726,000.00

16 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: V

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

V1300 40105-3000 Antistrip additive, type 3

Hat Creek Construction & Materials, Inc. $460.00 $25,300.00 Herback General Engineering, LLC $1.40 $77.00 Engineer's Estimate 55.0 t $890.00 $48,950.00

V1340 40920-1000 Fog seal, emulsified asphalt grade CSS-1 or CSS-1h, SS-1 or SS-1h

Hat Creek Construction & Materials, Inc. $1,350.00 $20,250.00 Herback General Engineering, LLC $805.00 $12,075.00 Engineer's Estimate 15 t $1,100.00 $16,500.00

V1360 41105-0000 Blotter

Hat Creek Construction & Materials, Inc. $30.00 $7,500.00 Herback General Engineering, LLC $95.00 $23,750.00 Engineer's Estimate 250 t $115.00 $28,750.00

V1380 41201-1000 Tack coat grade CSS-1, CSS-1h, SS-1, or SS-1h

Hat Creek Construction & Materials, Inc. $790.00 $23,700.00 Herback General Engineering, LLC $895.00 $26,850.00 Engineer's Estimate 30 t $1,500.00 $45,000.00

V1400 60801-0500 Paved waterway, type 5

Hat Creek Construction & Materials, Inc. $100.00 $12,000.00 Herback General Engineering, LLC $123.00 $14,760.00 Engineer's Estimate 120 m2 $400.00 $48,000.00

V1420 61509-0000 Detectable warning panels

Hat Creek Construction & Materials, Inc. $430.00 $4,300.00 Herback General Engineering, LLC $225.00 $2,250.00 Engineer's Estimate 10 m2 $400.00 $4,000.00

V1440 62201-0200 Dump truck, 8 cubic meter minimum capacity

Hat Creek Construction & Materials, Inc. $135.00 $4,050.00 Herback General Engineering, LLC $195.00 $5,850.00 Engineer's Estimate 30 Hour $175.00 $5,250.00

17 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: V

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

V1460 62201-0450 Backhoe loader, 120 liter minimum rated capacity bucket, 450mm width

Hat Creek Construction & Materials, Inc. $135.00 $4,050.00 Herback General Engineering, LLC $180.00 $5,400.00 Engineer's Estimate 30 Hour $195.00 $5,850.00

V1480 62201-0900 Wheel loader, 2 cubic meter minimum rated capacity

Hat Creek Construction & Materials, Inc. $190.00 $5,700.00 Herback General Engineering, LLC $250.00 $7,500.00 Engineer's Estimate 30 Hour $225.00 $6,750.00

V1500 62201-2800 Motor grader, 2.4 meter minimum blade

Hat Creek Construction & Materials, Inc. $210.00 $6,300.00 Herback General Engineering, LLC $250.00 $7,500.00 Engineer's Estimate 30 Hour $250.00 $7,500.00

V1520 62201-3100 Hydraulic excavator, 2.2 cubic meter minimum capacity bucket, 125kW minimum flywheel power

Hat Creek Construction & Materials, Inc. $180.00 $5,400.00 Herback General Engineering, LLC $250.00 $7,500.00 Engineer's Estimate 30 Hour $230.00 $6,900.00

V1540 62202-1000 Materials transfer vehicle

Hat Creek Construction & Materials, Inc. Lump Sum $22,000.00 Herback General Engineering, LLC Lump Sum $28,297.50 Engineer's Estimate ALL LPSM Lump Sum $17,500.00

V1560 62301-0000 General labor

Hat Creek Construction & Materials, Inc. $80.00 $24,000.00 Herback General Engineering, LLC $98.00 $29,400.00 Engineer's Estimate 300 Hour $90.00 $27,000.00

V1580 62302-1100 Special labor, hired survey services

Hat Creek Construction & Materials, Inc. $187.00 $5,610.00 Herback General Engineering, LLC $290.00 $8,700.00 Engineer's Estimate 30 Hour $285.00 $8,550.00

18 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: V

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

V1600 63404-0200 Pavement markings, type B

Hat Creek Construction & Materials, Inc. $13.00 $10,725.00 Herback General Engineering, LLC $14.75 $12,168.75 Engineer's Estimate 825 l $27.75 $22,893.75

V1620 63405-0050 Pavement markings, symbols

Hat Creek Construction & Materials, Inc. $125.00 $250.00 Herback General Engineering, LLC $145.00 $290.00 Engineer's Estimate 2 Each $950.00 $1,900.00

V1640 63501-1000 Temporary traffic control, traffic and safety supervisor

Hat Creek Construction & Materials, Inc. Lump Sum $25,000.00 Herback General Engineering, LLC Lump Sum $39,600.00 Engineer's Estimate ALL LPSM Lump Sum $22,500.00

V1660 63502-1050 Temporary traffic control, tubular marker

Hat Creek Construction & Materials, Inc. $30.00 $1,500.00 Herback General Engineering, LLC $80.00 $4,000.00 Engineer's Estimate 50 Each $50.00 $2,500.00

V1680 63502-1300 Temporary traffic control, drum

Hat Creek Construction & Materials, Inc. $75.00 $4,125.00 Herback General Engineering, LLC $136.00 $7,480.00 Engineer's Estimate 55 Each $85.00 $4,675.00

V1700 63503-0300 Temporary traffic control, barricade type 3

Hat Creek Construction & Materials, Inc. $200.00 $3,600.00 Herback General Engineering, LLC $373.00 $6,714.00 Engineer's Estimate 18 m $350.00 $6,300.00

V1720 63505-1000 Temporary traffic control, pavement markings

Hat Creek Construction & Materials, Inc. $2,500.00 $9,750.00 Herback General Engineering, LLC $1,310.00 $5,109.00 Engineer's Estimate 3.9 km $850.00 $3,315.00

19 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: V

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

V1740 63506-0500 Temporary traffic control, flagger

Hat Creek Construction & Materials, Inc. $80.00 $40,000.00 Herback General Engineering, LLC $109.00 $54,500.00 Engineer's Estimate 500 Hour $87.75 $43,875.00

V1760 63506-0600 Temporary traffic control, pilot car

Hat Creek Construction & Materials, Inc. $100.00 $25,000.00 Herback General Engineering, LLC $130.00 $32,500.00 Engineer's Estimate 250 Hour $125.00 $31,250.00

Total Schedule - All Items

Hat Creek Construction & Materials, Inc. $1,595,317.00 Herback General Engineering, LLC $2,522,486.17 Engineer's Estimate $2,115,000.00

20 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Y

Schedule Type: Options

Solcitation No: 6982AF21B000029

Division: Central Federal Lands

State: CA County: Modoc, Siskiyou

Federal Land: Lava Beds National Monument Opened at: Lakewood, CO

Opened by: Sheri Walsh

Date: 12/01/21

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Hat Creek Construction & Materials, Inc. $485,318.00 24339 Highway 89 N Burney, CA 96013

Herback General Engineering, LLC $613,185.56 2531 Nowlin Road Minden, NV 89423

Engineer's Estimate $1,136,010.00

21 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y1000 15101-0000 Mobilization

Hat Creek Construction & Materials, Inc. Lump Sum $47,000.00 Herback General Engineering, LLC Lump Sum $107,000.00 Engineer's Estimate ALL LPSM Lump Sum $110,016.40

Y1020 15210-3000 Centerline, verification and staking

Hat Creek Construction & Materials, Inc. $2,000.00 $1,078.00 Herback General Engineering, LLC $5,040.00 $2,716.56 Engineer's Estimate 0.539 km $1,650.00 $889.35

Y1040 15215-7000 Survey and staking, parking area

Hat Creek Construction & Materials, Inc. $3,330.00 $3,330.00 Herback General Engineering, LLC $7,300.00 $7,300.00 Engineer's Estimate 1 Each $15,000.00 $15,000.00

Y1060 15301-0000 Contractor quality control

Hat Creek Construction & Materials, Inc. Lump Sum $47,000.00 Herback General Engineering, LLC Lump Sum $14,025.00 Engineer's Estimate ALL LPSM Lump Sum $65,000.00

Y1080 15401-0000 Contractor testing

Hat Creek Construction & Materials, Inc. Lump Sum $63,375.00 Herback General Engineering, LLC Lump Sum $10,600.00 Engineer's Estimate ALL LPSM Lump Sum $60,000.00

Y1100 15501-0000 Construction schedule

Hat Creek Construction & Materials, Inc. Lump Sum $5,000.00 Herback General Engineering, LLC Lump Sum $1,760.00 Engineer's Estimate ALL LPSM Lump Sum $2,500.00

Y1120 15703-1500 Soil erosion control, temporary soil tackifier

Hat Creek Construction & Materials, Inc. $7,000.00 $455.00 Herback General Engineering, LLC $18,600.00 $1,209.00 Engineer's Estimate 0.065 ha $13,834.60 $899.25

22 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y1140 15801-0000 Watering for dust control

Hat Creek Construction & Materials, Inc. $0.02 $1,500.00 Herback General Engineering, LLC $1.53 $114,750.00 Engineer's Estimate 75,000 m3 $6.50 $487,500.00

Y1160 20303-1600 Removal of pavement, asphalt

Hat Creek Construction & Materials, Inc. $30.00 $7,500.00 Herback General Engineering, LLC $5.95 $1,487.50 Engineer's Estimate 250 m2 $19.00 $4,750.00

Y1180 20402-0000 Subexcavation

Hat Creek Construction & Materials, Inc. $155.00 $15,500.00 Herback General Engineering, LLC $157.00 $15,700.00 Engineer's Estimate 100 m3 $300.00 $30,000.00

Y1200 30306-2500 Pulverizing, 125mm depth

Hat Creek Construction & Materials, Inc. $8.00 $30,400.00 Herback General Engineering, LLC $4.70 $17,860.00 Engineer's Estimate 3,800 m2 $8.00 $30,400.00

Y1220 30802-2000 Roadway aggregate, method 2

Hat Creek Construction & Materials, Inc. $75.00 $10,125.00 Herback General Engineering, LLC $104.00 $14,040.00 Engineer's Estimate 135 t $75.00 $10,125.00

Y1240 40101-5600 Superpave pavement, 12.5mm or 19mm nominal maximum size aggregate, 0.3 to <3 million ESAL

Hat Creek Construction & Materials, Inc. $140.00 $119,000.00 Herback General Engineering, LLC $254.00 $215,900.00 Engineer's Estimate 850 t $132.00 $112,200.00

Y1280 40105-3000 Antistrip additive, type 3

Hat Creek Construction & Materials, Inc. $460.00 $39,100.00 Herback General Engineering, LLC $1.40 $119.00 Engineer's Estimate 85 t $890.00 $75,650.00

23 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y1320 40920-1000 Fog seal, emulsified asphalt grade CSS-1 or CSS-1h, SS-1 or SS-1h

Hat Creek Construction & Materials, Inc. $2,500.00 $6,250.00 Herback General Engineering, LLC $1,600.00 $4,000.00 Engineer's Estimate 2.5 t $1,100.00 $2,750.00

Y1340 41105-0000 Blotter

Hat Creek Construction & Materials, Inc. $30.00 $1,200.00 Herback General Engineering, LLC $95.00 $3,800.00 Engineer's Estimate 40 t $115.00 $4,600.00

Y1360 41201-1000 Tack coat grade CSS-1, CSS-1h, SS-1, or SS-1h

Hat Creek Construction & Materials, Inc. $790.00 $3,950.00 Herback General Engineering, LLC $1,140.00 $5,700.00 Engineer's Estimate 5.0 t $1,500.00 $7,500.00

Y1380 60915-1000 Wheelstop, concrete

Hat Creek Construction & Materials, Inc. $120.00 $720.00 Herback General Engineering, LLC $170.00 $1,020.00 Engineer's Estimate 6 Each $185.00 $1,110.00

Y1400 61109-1000 Relocate manhole

Hat Creek Construction & Materials, Inc. $3,000.00 $12,000.00 Herback General Engineering, LLC $1,220.00 $4,880.00 Engineer's Estimate 4 Each $5,000.00 $20,000.00

Y1420 61109-2000 Relocate water valve

Hat Creek Construction & Materials, Inc. $2,200.00 $17,600.00 Herback General Engineering, LLC $1,140.00 $9,120.00 Engineer's Estimate 8 Each $2,800.00 $22,400.00

Y1440 62201-0200 Dump truck, 8 cubic meter minimum capacity

Hat Creek Construction & Materials, Inc. $135.00 $2,700.00 Herback General Engineering, LLC $195.00 $3,900.00 Engineer's Estimate 20 Hour $175.00 $3,500.00

24 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y1460 62201-0450 Backhoe loader, 120 liter minimum rated capacity bucket, 450mm width

Hat Creek Construction & Materials, Inc. $135.00 $2,700.00 Herback General Engineering, LLC $180.00 $3,600.00 Engineer's Estimate 20 Hour $195.00 $3,900.00

Y1480 62201-0900 Wheel loader, 2 cubic meter minimum rated capacity

Hat Creek Construction & Materials, Inc. $190.00 $3,800.00 Herback General Engineering, LLC $250.00 $5,000.00 Engineer's Estimate 20 Hour $225.00 $4,500.00

Y1500 62201-2800 Motor grader, 2.4 meter minimum blade

Hat Creek Construction & Materials, Inc. $210.00 $4,200.00 Herback General Engineering, LLC $250.00 $5,000.00 Engineer's Estimate 20 Hour $250.00 $5,000.00

Y1520 62201-3100 Hydraulic excavator, 2.2 cubic meter minimum capacity bucket, 125kW minimum flywheel power

Hat Creek Construction & Materials, Inc. $180.00 $3,600.00 Herback General Engineering, LLC $250.00 $5,000.00 Engineer's Estimate 20 Hour $230.00 $4,600.00

Y1540 62202-1000 Materials transfer vehicle

Hat Creek Construction & Materials, Inc. Lump Sum $11,000.00 Herback General Engineering, LLC Lump Sum $4,042.50 Engineer's Estimate ALL LPSM Lump Sum $17,500.00

Y1560 62301-0000 General labor

Hat Creek Construction & Materials, Inc. $80.00 $3,200.00 Herback General Engineering, LLC $98.00 $3,920.00 Engineer's Estimate 40 Hour $90.00 $3,600.00

Y1580 62302-1100 Special labor, hired survey services

Hat Creek Construction & Materials, Inc. $187.00 $5,610.00 Herback General Engineering, LLC $290.00 $8,700.00 Engineer's Estimate 30 Hour $285.00 $8,550.00

25 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y1600 63404-0200 Pavement markings, type B

Hat Creek Construction & Materials, Inc. $30.00 $1,800.00 Herback General Engineering, LLC $35.00 $2,100.00 Engineer's Estimate 60 l $27.75 $1,665.00

Y1620 63405-0050 Pavement markings, symbols

Hat Creek Construction & Materials, Inc. $125.00 $625.00 Herback General Engineering, LLC $145.00 $725.00 Engineer's Estimate 5 Each $950.00 $4,750.00

Y1640 63503-0300 Temporary traffic control, barricade type 3

Hat Creek Construction & Materials, Inc. $200.00 $2,400.00 Herback General Engineering, LLC $373.00 $4,476.00 Engineer's Estimate 12 m $350.00 $4,200.00

Y1660 63505-1000 Temporary traffic control, pavement markings

Hat Creek Construction & Materials, Inc. $4,000.00 $2,000.00 Herback General Engineering, LLC $1,310.00 $655.00 Engineer's Estimate 0.500 km $850.00 $425.00

Y1680 63506-0500 Temporary traffic control, flagger

Hat Creek Construction & Materials, Inc. $80.00 $9,600.00 Herback General Engineering, LLC $109.00 $13,080.00 Engineer's Estimate 120 Hour $87.75 $10,530.00

Total Schedule - All Items

Hat Creek Construction & Materials, Inc. $485,318.00 Herback General Engineering, LLC $613,185.56 Engineer's Estimate $1,136,010.00

26 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Z

Schedule Type: Options

Solcitation No: 6982AF21B000029

Division: Central Federal Lands

State: CA County: Modoc, Siskiyou

Federal Land: Lava Beds National Monument Opened at: Lakewood, CO

Opened by: Sheri Walsh

Date: 12/01/21

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Herback General Engineering, LLC $585,908.80 2531 Nowlin Road Minden, NV 89423

Hat Creek Construction & Materials, Inc. $722,555.00 24339 Highway 89 N Burney, CA 96013

Engineer's Estimate $620,300.00

27 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Z

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Z1000 15101-0000 Mobilization

Herback General Engineering, LLC Lump Sum $100,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $70,000.00 Engineer's Estimate ALL LPSM Lump Sum $59,952.40

Z1020 15210-3000 Centerline, verification and staking

Herback General Engineering, LLC $5,040.00 $478.80 Hat Creek Construction & Materials, Inc. $4,000.00 $380.00 Engineer's Estimate 0.095 km $1,650.00 $156.75

Z1040 15215-7000 Survey and staking, parking area

Herback General Engineering, LLC $9,700.00 $9,700.00 Hat Creek Construction & Materials, Inc. $3,770.00 $3,770.00 Engineer's Estimate 1 Each $25,000.00 $25,000.00

Z1060 15301-0000 Contractor quality control

Herback General Engineering, LLC Lump Sum $14,025.00 Hat Creek Construction & Materials, Inc. Lump Sum $83,000.00 Engineer's Estimate ALL LPSM Lump Sum $65,000.00

Z1080 15401-0000 Contractor testing

Herback General Engineering, LLC Lump Sum $10,600.00 Hat Creek Construction & Materials, Inc. Lump Sum $95,000.00 Engineer's Estimate ALL LPSM Lump Sum $60,000.00

Z1100 15501-0000 Construction schedule

Herback General Engineering, LLC Lump Sum $1,760.00 Hat Creek Construction & Materials, Inc. Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,500.00

Z1120 15703-1500 Soil erosion control, temporary soil tackifier

Herback General Engineering, LLC $18,600.00 $186.00 Hat Creek Construction & Materials, Inc. $8,000.00 $80.00 Engineer's Estimate 0.010 ha $13,834.60 $138.35

28 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Z

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Z1140 15801-0000 Watering for dust control

Herback General Engineering, LLC $1.53 $11,475.00 Hat Creek Construction & Materials, Inc. $0.20 $1,500.00 Engineer's Estimate 7,500 m3 $6.50 $48,750.00

Z1160 20302-0300 Removal of curb and gutter, concrete

Herback General Engineering, LLC $44.00 $1,540.00 Hat Creek Construction & Materials, Inc. $215.00 $7,525.00 Engineer's Estimate 35 m $23.00 $805.00

Z1180 20303-3000 Removal of sidewalk, asphalt

Herback General Engineering, LLC $5.95 $892.50 Hat Creek Construction & Materials, Inc. $50.00 $7,500.00 Engineer's Estimate 150 m2 $20.00 $3,000.00

Z1200 20402-0000 Subexcavation

Herback General Engineering, LLC $157.00 $15,700.00 Hat Creek Construction & Materials, Inc. $155.00 $15,500.00 Engineer's Estimate 100 m3 $300.00 $30,000.00

Z1220 30306-2500 Pulverizing, 125mm depth

Herback General Engineering, LLC $4.70 $26,320.00 Hat Creek Construction & Materials, Inc. $13.00 $72,800.00 Engineer's Estimate 5,600 m2 $8.00 $44,800.00

Z1240 30802-2000 Roadway aggregate, method 2

Herback General Engineering, LLC $107.00 $4,280.00 Hat Creek Construction & Materials, Inc. $200.00 $8,000.00 Engineer's Estimate 40 t $75.00 $3,000.00

Z1260 40101-5600 Superpave pavement, 12.5mm or 19mm nominal maximum size aggregate, 0.3 to <3 million ESAL

Herback General Engineering, LLC $254.00 $273,050.00 Hat Creek Construction & Materials, Inc. $145.00 $155,875.00 Engineer's Estimate 1,075 t $132.00 $141,900.00

29 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Z

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Z1300 40105-3000 Antistrip additive, type 3

Herback General Engineering, LLC $1.40 $14.00 Hat Creek Construction & Materials, Inc. $460.00 $4,600.00 Engineer's Estimate 10.0 t $890.00 $8,900.00

Z1320 40920-1000 Fog seal, emulsified asphalt grade CSS-1 or CSS-1h, SS-1 or SS-1h

Herback General Engineering, LLC $1,600.00 $4,800.00 Hat Creek Construction & Materials, Inc. $2,500.00 $7,500.00 Engineer's Estimate 3.0 t $1,100.00 $3,300.00

Z1340 41105-0000 Blotter

Herback General Engineering, LLC $95.00 $4,750.00 Hat Creek Construction & Materials, Inc. $30.00 $1,500.00 Engineer's Estimate 50 t $115.00 $5,750.00

Z1360 41201-1000 Tack coat grade CSS-1, CSS-1h, SS-1, or SS-1h

Herback General Engineering, LLC $1,140.00 $6,840.00 Hat Creek Construction & Materials, Inc. $790.00 $4,740.00 Engineer's Estimate 6.0 t $1,500.00 $9,000.00

Z1380 60110-0000 Concrete coloring agent

Herback General Engineering, LLC $14.00 $3,360.00 Hat Creek Construction & Materials, Inc. $30.00 $7,200.00 Engineer's Estimate 240 kg $11.00 $2,640.00

Z1400 60902-1000 Curb and gutter, concrete, 300mm depth

Herback General Engineering, LLC $253.00 $10,120.00 Hat Creek Construction & Materials, Inc. $685.00 $27,400.00 Engineer's Estimate 40 m $175.00 $7,000.00

Z1420 61501-0100 Sidewalk, concrete

Herback General Engineering, LLC $166.00 $24,900.00 Hat Creek Construction & Materials, Inc. $550.00 $82,500.00 Engineer's Estimate 150 m2 $175.00 $26,250.00

30 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Z

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Z1440 61504-1000 Accessibility ramp, concrete

Herback General Engineering, LLC $180.00 $1,440.00 Hat Creek Construction & Materials, Inc. $1,800.00 $14,400.00 Engineer's Estimate 8 m2 $350.00 $2,800.00

Z1460 62201-0200 Dump truck, 8 cubic meter minimum capacity

Herback General Engineering, LLC $195.00 $3,900.00 Hat Creek Construction & Materials, Inc. $135.00 $2,700.00 Engineer's Estimate 20 Hour $175.00 $3,500.00

Z1480 62201-0450 Backhoe loader, 120 liter minimum rated capacity bucket, 450mm width

Herback General Engineering, LLC $180.00 $3,600.00 Hat Creek Construction & Materials, Inc. $135.00 $2,700.00 Engineer's Estimate 20 Hour $195.00 $3,900.00

Z1500 62201-0900 Wheel loader, 2 cubic meter minimum rated capacity

Herback General Engineering, LLC $250.00 $5,000.00 Hat Creek Construction & Materials, Inc. $190.00 $3,800.00 Engineer's Estimate 20 Hour $225.00 $4,500.00

Z1520 62201-2800 Motor grader, 2.4 meter minimum blade

Herback General Engineering, LLC $250.00 $5,000.00 Hat Creek Construction & Materials, Inc. $210.00 $4,200.00 Engineer's Estimate 20 Hour $250.00 $5,000.00

Z1540 62201-3100 Hydraulic excavator, 2.2 cubic meter minimum capacity bucket, 125kW minimum flywheel power

Herback General Engineering, LLC $250.00 $5,000.00 Hat Creek Construction & Materials, Inc. $180.00 $3,600.00 Engineer's Estimate 20 Hour $230.00 $4,600.00

Z1560 62202-1000 Materials transfer vehicle

Herback General Engineering, LLC Lump Sum $8,085.00 Hat Creek Construction & Materials, Inc. Lump Sum $8,000.00 Engineer's Estimate ALL LPSM Lump Sum $17,500.00

31 out of 31

Project No: CA PRA LABE 10(1)

Project Name: Main Road

Schedule: Z

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Z1580 62301-0000 General labor

Herback General Engineering, LLC $98.00 $7,840.00 Hat Creek Construction & Materials, Inc. $80.00 $6,400.00 Engineer's Estimate 80 Hour $90.00 $7,200.00

Z1600 62302-1100 Special labor, hired survey services

Herback General Engineering, LLC $290.00 $8,700.00 Hat Creek Construction & Materials, Inc. $187.00 $5,610.00 Engineer's Estimate 30 Hour $285.00 $8,550.00

Z1620 63404-0200 Pavement markings, type B

Herback General Engineering, LLC $14.75 $3,687.50 Hat Creek Construction & Materials, Inc. $13.00 $3,250.00 Engineer's Estimate 250 l $27.75 $6,937.50

Z1640 63405-0050 Pavement markings, symbols

Herback General Engineering, LLC $145.00 $145.00 Hat Creek Construction & Materials, Inc. $125.00 $125.00 Engineer's Estimate 1 Each $950.00 $950.00

Z1660 63506-0500 Temporary traffic control, flagger

Herback General Engineering, LLC $109.00 $8,720.00 Hat Creek Construction & Materials, Inc. $80.00 $6,400.00 Engineer's Estimate 80 Hour $87.75 $7,020.00

Total Schedule - All Items

Herback General Engineering, LLC $585,908.80 Hat Creek Construction & Materials, Inc. $722,555.00 Engineer's Estimate $620,300.00

File details come from the government source that posted it. Updated .