Tabulation of Bids Report Date: 07/24/19
1 out of 5Source Selection Information - See FAR 2.101 & 3.104
Project No: WY FTFS 23(5)
Project Name: Louis Lake Road
Schedule: A
Schedule Type: Base
Solcitation No:
Division: Central Federal Lands
State: WY County: Fremont
Federal Land: Shoshone National Forest Opened at: Lakewood, CO
Opened by: Leslie Karsten
Date: 07/24/19
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Triple A Building Services, Inc. $1,945,365.00 369 N 4th. St.
Laramie, WY 82072
Construction Solutions Group, LLC $2,894,080.50 5512 Elk Valley Estates Dr St. Louis, MO 63128
Engineer's Estimate $1,100,000.00
2 out of 5Source Selection Information - See FAR 2.101 & 3.104
Project No: WY FTFS 23(5)
Project Name: Louis Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
Triple A Building Services, Inc. Lump Sum $121,000.00 Construction Solutions Group, LLC Lump Sum $226,250.00 Engineer's Estimate ALL LPSM Lump Sum $126,150.00
A0030 15201-0000 CONSTRUCTION SURVEY AND STAKING
Triple A Building Services, Inc. Lump Sum $165,000.00 Construction Solutions Group, LLC Lump Sum $66,550.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00
A0040 15301-0000 CONTRACTOR QUALITY CONTROL
Triple A Building Services, Inc. Lump Sum $85,000.00 Construction Solutions Group, LLC Lump Sum $43,250.00 Engineer's Estimate ALL LPSM Lump Sum $75,000.00
A0050 15401-0000 CONTRACTOR TESTING
Triple A Building Services, Inc. Lump Sum $34,500.00 Construction Solutions Group, LLC Lump Sum $43,250.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00
A0060 15501-0000 CONSTRUCTION SCHEDULE
Triple A Building Services, Inc. Lump Sum $5,500.00 Construction Solutions Group, LLC Lump Sum $13,300.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
A0070 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Triple A Building Services, Inc. $10.00 $10,000.00 Construction Solutions Group, LLC $10.64 $10,640.00 Engineer's Estimate 1,000 LNFT $5.00 $5,000.00
A0080 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Triple A Building Services, Inc. $8.00 $8,000.00 Construction Solutions Group, LLC $10.64 $10,640.00 Engineer's Estimate 1,000 LNFT $5.00 $5,000.00
3 out of 5Source Selection Information - See FAR 2.101 & 3.104
Project No: WY FTFS 23(5)
Project Name: Louis Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0090 15802-0000 WATERING FOR DUST CONTROL
Triple A Building Services, Inc. Lump Sum $54,000.00 Construction Solutions Group, LLC Lump Sum $83,790.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0100 20205-0000 SELECTIVE CLEARING AND GRUBBING
Triple A Building Services, Inc. $4,560.00 $41,040.00 Construction Solutions Group, LLC $6,650.00 $59,850.00 Engineer's Estimate 9.0 ACRE $3,000.00 $27,000.00
A0110 20401-0000 ROADWAY EXCAVATION
Triple A Building Services, Inc. $90.00 $414,000.00 Construction Solutions Group, LLC $11.97 $55,062.00 Engineer's Estimate 4,600 CUYD $60.00 $276,000.00
A0120 30202-2000 ROADWAY AGGREGATE, METHOD 2 (4-INCH DEPTH)
Triple A Building Services, Inc. $88.00 $704,000.00 Construction Solutions Group, LLC $57.19 $457,520.00 Engineer's Estimate 8,000 TON $45.00 $360,000.00
A0130 30301-6000 ROADWAY RECONDITIONING
Triple A Building Services, Inc. $1,200.00 $6,000.00 Construction Solutions Group, LLC $332,500.00 $1,662,500.00 Engineer's Estimate 5.000 MILE $10,000.00 $50,000.00
A0140 60704-0000 CLEANING CULVERT IN PLACE
Triple A Building Services, Inc. $2,200.00 $22,000.00 Construction Solutions Group, LLC $1,330.00 $13,300.00 Engineer's Estimate 10 EACH $1,000.00 $10,000.00
A0150 61801-0000 CONCRETE BARRIER
Triple A Building Services, Inc. $400.00 $32,000.00 Construction Solutions Group, LLC $532.00 $42,560.00 Engineer's Estimate 80 LNFT $80.00 $6,400.00
4 out of 5Source Selection Information - See FAR 2.101 & 3.104
Project No: WY FTFS 23(5)
Project Name: Louis Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0160 62201-0050 DUMP TRUCK, 5 CUBIC YARD MINIMUM CAPACITY
Triple A Building Services, Inc. $200.00 $2,000.00 Construction Solutions Group, LLC $146.30 $1,463.00 Engineer's Estimate 10 HOUR $150.00 $1,500.00
A0170 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH
Triple A Building Services, Inc. $220.00 $2,200.00 Construction Solutions Group, LLC $186.20 $1,862.00 Engineer's Estimate 10 HOUR $140.00 $1,400.00
A0180 62301-0000 GENERAL LABOR
Triple A Building Services, Inc. $100.00 $2,000.00 Construction Solutions Group, LLC $79.80 $1,596.00 Engineer's Estimate 20 HOUR $70.00 $1,400.00
A0190 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Triple A Building Services, Inc. $500.00 $5,000.00 Construction Solutions Group, LLC $166.25 $1,662.50 Engineer's Estimate 10 HOUR $140.00 $1,400.00
A0200 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
Triple A Building Services, Inc. $10,500.00 $31,500.00 Construction Solutions Group, LLC $3,990.00 $11,970.00 Engineer's Estimate 3.0 ACRE $5,000.00 $15,000.00
A0210 62510-1000 SEEDING, DRY METHOD
Triple A Building Services, Inc. $10,000.00 $30,000.00 Construction Solutions Group, LLC $1,995.00 $5,985.00 Engineer's Estimate 3.0 ACRE $3,000.00 $9,000.00
A0220 62515-2000 MULCHING, HYDRAULIC METHOD
Triple A Building Services, Inc. $25,000.00 $75,000.00 Construction Solutions Group, LLC $3,325.00 $9,975.00 Engineer's Estimate 3.0 ACRE $2,000.00 $6,000.00
5 out of 5Source Selection Information - See FAR 2.101 & 3.104
Project No: WY FTFS 23(5)
Project Name: Louis Lake Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0230 63301-0000 SIGN SYSTEM
Triple A Building Services, Inc. $1,400.00 $35,000.00 Construction Solutions Group, LLC $997.50 $24,937.50 Engineer's Estimate 25 EACH $700.00 $17,500.00
A0240 63308-0000 OBJECT MARKER
Triple A Building Services, Inc. $250.00 $5,000.00 Construction Solutions Group, LLC $199.50 $3,990.00 Engineer's Estimate 20 EACH $200.00 $4,000.00
A0250 63309-0100 DELINEATOR, TYPE 1
Triple A Building Services, Inc. $175.00 $7,875.00 Construction Solutions Group, LLC $199.50 $8,977.50 Engineer's Estimate 45 EACH $50.00 $2,250.00
A0260 63501-0000 TEMPORARY TRAFFIC CONTROL
Triple A Building Services, Inc. Lump Sum $32,750.00 Construction Solutions Group, LLC Lump Sum $13,300.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00
A0270 63701-0000 FIELD OFFICE
Triple A Building Services, Inc. $15,000.00 $15,000.00 Construction Solutions Group, LLC $19,900.00 $19,900.00 Engineer's Estimate 1 EACH $5,000.00 $5,000.00
Total Schedule - All Items
Triple A Building Services, Inc. $1,945,365.00 Construction Solutions Group, LLC $2,894,080.50 Engineer's Estimate $1,100,000.00
| 2019-07-24T15:35:34-0600 | |
| LESLIE N KARSTEN |