QnA_2.27.2019_Part_II.pdf

PDF 75 KB Posted

Attached to
CA FLAP MER CR337(1) Wolfsen Road
Solicitation number
6982AF19B000003
Issued by

View the file

Other files

File Type Posted
Bid_Tabs.pdf PDF
CA_FLAP_MER_CR337(1)_Wolfsen_Road_Bid_Opening_Summary.pdf PDF
A002.pdf PDF
A001.pdf PDF
QnA_2.27.2019.pdf PDF
6982AF19B000003.pdf PDF
CA_FLAP_MER_337(1)_Pavement_Report_-_signed.pdf PDF
FP-14.pdf PDF
CA_FLAP_MER_CR337(1)_Wolfsen_Road_-_Final_Plans_and_Cross_Sections.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

CA FLAP MER CR 337(1), Wolfsen Road

February 27, 2019

Questions Answers

1 Can we send the final bid schedule proposal in electronically? In the past, we have been able to send bonds, and other hard copy items via Fed Ex and send the final bid schedule electronically on the bid date.

Modifications to the bid schedule may be submitted electronically via email, faxed or mailed in - see page A-iii.

2 The specs call for a biologist to clear the work area daily. This would prove costly as you would have to pay someone drive time and work time everyday at a premium rate. Can the biologist train the superintendent or foreman to conduct the daily clearances prior to starting work?

No. Submit bids in accordance with what is stated in the SCR’s. As per

Subsection 108.01(g) the biologist must have a biology degree and 1 year minimum experience with construction monitoring for measures similar to those proposed for the project.

3 Pages E19-E20 of the special provisions do not clarify if there is a full-time or part-time QCM required on the project. Please advise if we are required to provide a full time QCM for this project?

A full-time, on-site QCM is required.

4 Would you please reconsider not making the qualification for the

QCM more restrictive and allow the QCM assigned to the project the ability to meet the qualification outline in section 153.02 of

FP-14?

No, the contractor most provide a QCM that meets or exceeds the qualifications as specified in the solicitation.

5 We just saw this solicitation, is there any chance that you may extend this solicitation by an additional 7 calendar days?

No extensions to the bid opening date are anticipated at this time.

File details come from the government source that posted it.