This statement of work and related solicitation describe a requirement for a District Project Coordinator to support Bipartisan Infrastructure Law projects in the Atlanta District of the Federal Aviation Administration. The statement of work outlines tasks including serving as point of contact on project implementation and coordination issues, facilitating operational and project efforts to maximize efficiency, and strengthening relationships among stakeholders. The solicitation is set aside for qualified vendors on the Atlanta District list for district project coordination and engineer project oversight support. Responses are due by the closing date listed in the solicitation and must include all required documents outlined in section L. The selected vendor will provide monthly progress reports and annual documentation deliverables as specified in the statement of work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0001 - SIR 697DCK-23-R-00189.pdf | ||
| SIR - 697DCK-23-R-00189 - ATL District -DPC.pdf | ||
| SIR - 697DCK-23-R-00189 - ATL District -DPC.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No.: 697DCK-23-R-00189
Attachment 0001 - Statement of Work
District Project Coordinator for the
Atlanta District
STATEMENT OF WORK
Bipartisan Infrastructure LAW (BIL) Atlanta District
Table of Contents
1.0 INTRODUCTION AND OVERVIEW
1.1 BACKGROUND
1.2 SCOPE OF WORK
1.3 OBJECTIVES
1.3.1 Program Management Support - District Project Coordination
1.3.2 Management Analysis – District Project Coordination
1.4 TASKS ............................................................................................................................................. 5-9
1.5 END RESULTS/DELIVERABLES
1.5.1 List of Deliverables by Task
1.5.2 Transmittal/Delivery/Accessibility
1.5.2 OTHER CONSIDERATIONS
1.5.3 PROGRESS/COMPLIANCE.......................................................................................................... 9-10
1.0 Introduction and Overview
This Statement of Work (SOW) is for a District Project Coordinator (DPC) in support of the
Federal Aviation Administration’s portion of the Bipartisan Infrastructure Law (BIL) and reimbursable programs (including those arising from Airport Improvement Program (AIP) appropriations and other directly funded reimbursable projects).
1.1 Background
The Implementation Services Team (AJW-213) is responsible for centralized management and is the single accountable office for the planning, integration, coordination, and implementation of various components. The AJW-213 team Manager is responsible for establishing the necessary infrastructure to ensure timely and efficient program execution. The Implementation Services
Team of the Federal Aviation Administration (AJW-213) plays an important role in implementing and executing programs and projects to safely establish, replace, modernize and sustain the National Airspace System (NAS).
1.2 Scope of Work
The Contractor must provide a DPC to support the AJW-213 PMO and the Atlanta District
Manager in development, transition, and implementation activities. The DPC must perform duties to provide program management, program/financial management, independent cost analysis and support services to ATO for the Atlanta service area to include professional services for project coordination, resource management, business management, communications, operations and integration, and management analysis.
The DPC will work closely with Tech Services NAS Program Managers (NPMs) and PRG
Portfolio Management and Integration (PMI) teams to effectively identify, coordinate and integrate activities within the District.
1.3 Objectives
1.3.1 Technical Work Areas
Types of work that may be performed under this Statement of Work (SOW) are described below.
In performing all work under the Contract, the DPC must adhere to all Occupational Safety and
Health Administration (OSHA) requirements, all FAA occupational safety programs and requirements as set forth in the List of Applicable Documents, all taxation laws, and all applicable federal, state and local government codes, statutes, laws and regulations (including the obtaining of any required permits). Requirements may include but not be limited to project coordination and oversight activities related to new construction or installation, restoration, service life extension, demolition/removal, and refurbishment. The Contractor will be responsible for the scope of work contained in this contract and/or authorized/executed modifications thereto. Projects may originate from within the FAA, such as from the Corporate
Work Plan (CWP), or from reimbursable agreements between the FAA and other entities that involve protection of US national airspace, national defense or the FAA National Airspace
System (NAS).
1.3.2 Program Management Support
The DPC must provide expertise in cross-programmatic planning and coordination of implementation activities as well as operational activities. The DPC must provide resources to work closely with and enhance the current project support entities within Planning and
Requirements Groups (PRG), Engineering Services (ES), Technical Services (TS), System
Support Centers (SSCs) and the Districts. The DPC resources are expected to serve the entire
District and its Air Traffic Services Community and will serve as the joint liaison between the
District Office/SSC (ATS and AJW), Engineering Services, PRG, Headquarters program offices, local Airport District Office personnel, and local commercial airport entities.
1.3.3 Management Analysis
The integrated coordination of activities within the Districts is absolutely critical. This requires a formal integrated program/project coordination presence within the geographical field locations at the District level. The DPC will be a trusted third-party agent, who provides expertise in cross-management planning and coordination of implementation activities as well as operational activities throughout the District. DPC will work closely with and enhance the current project support entities within Planning and Requirements Groups (PRG), Engineering Services (ES), Technical Services (TS), System Support Centers (SSCs) and the Districts. The DPC will serve the entire District and its Air Traffic Services Community. The DPC will be a NAS Program and
Operations Subject Matter Expert (SME) and will serve as the joint liaison between the District
Office/SSC (ATS and AJW), Engineering Services, PRG, Headquarters program offices, local
Airport District Office personnel, and local commercial airport entities. The DPC will be an active advocate for the coordination, integration and planning of all projects and programs within the district. The DPC will use the FAA project management system and tools (e.g., Corporate
Work Plan [CWP]) to identify, coordinate and track implementation activities at the district level. The DPC require strong analytical and critical thinking capabilities with demonstrated ability to compile, assess and analyze large volumes of data from multiple sources (including operational data, project data, and administrative data sources, etc.) to identify key coordination and integration requirements. The DPC will work closely with Tech Services NAS Program
Managers (NPMs) and PRG Portfolio Management and Integration (PMI) teams to effectively identify, coordinate and integrate activities within the District. The DPC will need to reside in or near the District boundaries to facilitate the integration of work activities within the community of responsibility. The DPC must provide management services that ensure the quality, timeliness, and cost efficiency of all technical efforts provided under this Contract.
1.4 Tasks
The contractor must be cognizant of all the tasks dimensions that each labor category will perform in order meet the Government's expectations.
The DPC will perform the following core tasks in support of BIL funded projects for the Atlanta
District:
District Project Coordinator
Core Function Details
Serve as FAA/Airspace District point of contact on project implementation and coordination related issues
Serve as the primary FAA point of contact for the District, SSCs, TSOGs, PRG, AT Management and ES on project related issues
Assist with project coordination and communication efforts
Serve as liaison for District with the local airport authorities and FAA Airport District Offices (ADOs)
Participate in high-visibility or key FAA Stakeholder meetings in support of the District
Help all stakeholders speak with ‘One FAA Voice’
Provide an operational overview to all Stakeholders on all
District implementation activities.
Facilitate/Coordinate operational and project implementation efforts at the District Level to maximize efficiency and resource utilization
Maintain an integrated/coordinated FAA Airspace District
Project plan including program/project implementation activities, operational activities, airport activities and plans, etc.
Coordinate project milestones, constraints, solutions, status of active and future high-visibility projects at the
District level
Compile, assess and analyze large data sets from various sources to identify coordination requirements, impacts, solutions and recommendations
Participate in or lead efforts to align FAA resources at the
District Level to maximize efficiencies
Minimize project implementation impacts on NAS operations
Improve coordination and information sharing among all
FAA stakeholders including, but not limited to, PRG
(PMI, PIMs, Planners, Requirements, Resource Planners, EOSH) ES (Lead Engineers, PIPOCs), TSOG
(NPMs/NIM’s, Ops Engineers), and SSCM/SSC
Coordinators
Anticipate and plan for contingencies for project issues during design, construction and implementation that may adversely affect NAS operations.
Actively explore District initiated ideas and suggestions that improve NAS and Airspace safety and efficiency
Support development of Operational Risk Management
(ORM) documentation and plans
Strengthen relationship of all
FAA participants and stakeholders within the Airspace
Districts
Ensure effective communication among stakeholders
Establish a trustworthy relationship with district personnel and stakeholders
Solicit customer feedback for improvements
Participate in FAA stakeholder functions/meetings such as: quarterly, weekly, monthly, key stakeholder, key projects
1.5 End Results/Deliverables
AJW-213 requires the DPC to provide final report 30 days prior to end of base year and each option year awarded with breakout of all work completed aligning to each task.
1.5.1 List of Deliverables by Task
Deliverable
Quantity Due Date
Monthly Progress Report for Tasks
A,B,C, D
Original plus 1 10 working days after close of month
Property Inventory
Original As required
Standard Operating Procedures
Original; on line and soft copies as required
Annual documentation as needed. Initial SOPs due one month after contract start.
1.5.2 Transmittal/Delivery/Accessibility
The DPC must upload each deliverable to BIL sharepoint, an e-mail attachment to Contracting
Officer Representative and any others as requested.
1.5.3 Other Considerations
In addition to the above deliverables, the DPC must provide the necessary data to support the analyses provided as part of each task. The contractor must develop and prepare executive level data and briefings, documentation for program and budget reviews.
1.5.4 Progress/Compliance
The AJW-213 requires the DPC to provide status reports, attend meetings, quarterly program reviews in order to monitor progress and ensure compliance. The District manager will have list of agreed upon tasks and activities to be completed and report on by the DPC.