About this file

This amendment provides clarification to solicitation number 693C73-24-B-000006 for a bridge replacement project located in Pictured Rocks National Lakeshore in Michigan. The project involves removing and reconstructing the Miners River Bridge, replacing guardrails, reconstructing pavement, improving drainage, and other miscellaneous work. The estimated cost range is $700,000 to $2,000,000. The bid opening date remains February 20, 2024. The amendment summarizes seven questions received from potential bidders pertaining to construction periods, traffic control plans, impacts from endangered species, contractor qualification requirements, VETS-4212 reporting, winter shutdowns, and field office needs. Clarification is provided on these topics.

View the file

Other files for this federal contract opportunity

Other files attached to Pictured Rocks National Lakeshore, newest first.
File Type Posted
Results of Bid Opening - MI NP PIRO 11(2).pdf PDF
Plans - MI NP PIRO 11(2).pdf PDF
ADV_Bidders Qualifications Form.doc DOC document
VETS-4212 - Form - 2021.pdf PDF
MI_NP_PIRO_11(2)_PVT_Memo.pdf PDF
MI_NP_PIRO_11(2)_Bridge_Insp_Rpt.pdf PDF
IFB Solicitation - MI NP PIRO 11(2).pdf PDF
MI_NP_PIRO_11(2)_HYD_Memo.pdf PDF
Categorical Exclusion Form (NEPA).pdf PDF
FP14_Eng.pdf PDF
MI_NP_PIRO_11(2)_GEO_Memo.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

693C7324B000006 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ASHBURN VA 20147

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

ASHBURN VA 20147

ATTN:ACQUISITIONS

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

See Block 1402/06/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

01/18/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project MI NP PIRO 11(2):

The purpose of this Amendment is to:

1) Provide a summary of responses to questions/clarifications asked by potential bidders.

The Bid Opening date of Tuesday February 20, 2024, at 2:00 p.m. EST remains unchanged.

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment 0001

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

Amendment No. 0001

MI NP PIRO 11(2)

Replacement of Miners River Bridge Solicitation: 693C73-24-B-000006

The purpose of this Amendment is to:

1) Provide a summary of responses to questions/clarifications asked by potential bidders.

The Bid Opening date of Tuesday February 20, 2024, at 2:00 p.m. EST remains unchanged.

Questions / Clarifications

The following questions and issues were submitted via email. The Government response or clarification is provided.

1. On previous bridge projects we have worked on for the Hiawatha National Forest, “in stream work” according to the FWS can only occur between 5/15 and 9/15, due to concerns of water levels.

Additionally, the Categorical Exclusion Form noted that work is to be performed between Sept. 2024 and April 2025, many of the months being during heavy snowfall and access to the site being very limited due to road closures. Often times in these remote locations, roads are also not plowed, and soil conditions do not allow for adequate working conditions. Can the construction period of performance be adjusted to only allow work during the 5/15 – 9/15 period?

Response: The period of September 2024 to April 2025 in the categorical exclusion is a tentative duration for the overall construction project. In accordance with Subsection 108.01, construction activities may begin August 15, 2024. The contract provided 350 calendar days to complete the work. See Subsection 156.04 of Special Contract Requirements for road closure restrictions.

2. Shall the traffic control sign locations be determined by the prime contractor or does the Department of Transportation have an MUTCD plan already in place?

Response: See Plan sheets N01, N02 and S15 for traffic control sign locations. The contractor stakes the locations of the signs in the field. Final location and spacing of signs may be changed to fit field conditions as approved by the CO.

3. If an endangered species does come in close contact to the job site, or breeding does occur which may impact further construction efforts, shall the prime contractor demobilize from the site until the site is clear of the species? If so, will costs and efforts of demobilization and remobilization be reimbursed to the prime contractor?

Response: Section 7 consultation indicated that there are no critical habitats for threatened or endangered species within the project area. The Categorical Exclusion Form indicates that there are no expected impacts to endangered or threatened species. If an endangered species is observed on site notify the CO. Do not demobilize without written directive from the CO. Every effort will be made to continue work on the project in compliance with applicable regulations. If

Amendment 0001 the Government orders a stop work order for endangered species, impacts to time may be evaluated under Subsection 108.03 and costs may be evaluated under Subsection 109.06.

4. Section 9A of the ADV Bidders Qualification form requires the prime contractor to provide information of all active contracts the prime contractor holds. Many general contractors currently hold up to 25 or more contracts at a time. Can this requirement be limited to only “active bridge contracts” or 5 active contracts that are similar in scope, as this requirement seems very extensive and beyond what may be required to deem a contractor fit for award.

Response: Contractors are to provide the detailed information as requested on the form for as many active contracts deemed necessary, as long as the listed projects are similar in size and scope to the project being advertised.

5. Does the VETS4212 reporting form attached with the solicitation still need to be filled out if the prime contract already reported for the 2023 cycle? Sinc the filing period is only from 8/1 through 9/30, are we to assume this does NOT need to be included in the proposal package.

Response: Contractors are to include with their bid submission a copy of their most current completed Form VETS-4212 that is on file with the Veteran’s Employment and Training Service Center at the Department of Labor National Contact Center.

6. The supplemental spec states under 108.01C that the project may undergo a winter shutdown from 11/1/24 through 4/30/25, which is immediately within the contractual period the government is suggesting. If a winter shutdown does occur, will a no cost time extension be added to the contract?

Response: No time extension will be provided for a winter shutdown from 11/1/24 to 4/30/25.

The current contract duration of 350 calendar days already accounts for this winter shutdown.

7. Per the supplemental specifications, a field office trailer is required for the project. Please advise if this is applicable.

Response: The contract includes pay item 63701-0000 Field Office. See Section 637. Locate the Government field office within 15 miles of the project site and where high-speed Internet service is available. The field office may be a mobile field office or a rental office space. Obtain approval from the CO before delivery of a mobile field office or any rental agreements are signed.

U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0001
Solicitation: 693C73-24-B-000006