Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Solicitation Number DTSL5517R0681 for the Hands-Free Mooring (HFM) slot installation project at Snell Lock is amended to Incorporate the Questions and Answers on page 2.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

PAGE OF PAGES

1 2

5. PROJECT NUMBER (If applicable)2. AMENDMENT/MODIFICATION NUMBER

6923G518B0001A00001

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

U.S. Department of Transportation Saint Lawrence Seaway Development Corporation Contracting Office 180 Andrews Street Massena, New York 13662

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NUMBER

6923G518B0001

9B. DATED (SEE ITEM 11)

04/20/2018

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

(X)

4. REQUISITION/PURCHASE REQUISITION NUMBER3. EFFECTIVE DATE

05/14/2018

1. CONTRACT ID CODE

6923G518B0001P00001

HFM EQUIPMENT INSTALLATION @ EISENHOWER LOCK

RFP NO. 6923G518B0001

QUESTIONS AND ANSWERS

MAY 14, 2018

1. Q. Who is responsible for confined space monitoring?

A. The Contractor is responsible for complying with safety requirements for any confined spaces. SLSDC will identify any confined spaces the contractor may need to work in.

2. Q. Who is responsible for fall protection?

A. The Contractor is responsible for complying with safety requirements for fall protection. The Contractor will need to propose and gain approval for installing any fall protection/prevention device(s), or any other means or method, that would interfere with SLSDC Operations.

3. Q. What bid item number do we include the cable tray in?

A. #11. Also include the PLC panel in this bid item.

4. Q. What bid item number do we include the convenience outlets in?

A. #7

5. Q. What bid item number do we include the welding receptacles in?

A. #7