WFLHD Construction Contract Administration_FY 23 V2.pdf
PDF 162 KB Posted
- Solicitation number
- 69056726B000010
About this file
This document is a Federal Highway Administration (FHWA) compliance report on construction contract administration procedures regarding the definitization of equitable adjustments for change orders.
FHWA reports that it currently has no agency-specific additional policies and procedures beyond Federal Acquisition Regulation (FAR) requirements for definitizing equitable adjustments on construction contracts. The document provides historical performance data for fiscal years 2021 through 2023 on the time required to definitize change order proposals after receipt of adequate definitization proposals. The data shows a three-year trend where definitization timeframes varied considerably: in FY 2021, nine total change orders were processed with two taking 366 or more days and five taking 91-180 days; in FY 2022, only two total change orders were processed with one each in the 0-30 day and 91-180 day categories; and in FY 2023, thirteen total change orders were processed with significant delays, including three in the 181-365 day range and four in the 91-180 day range. Notably, no change orders were definitized within 0-30 days in FY 2023, and no undefinitized equitable adjustments remained pending after contract completion in any of the three fiscal years.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QA_10-16-2026.pdf | ||
| Brand Name Memo - WA NP OLYM 12(8).pdf | ||
| IFB_69056726B000010_WA NP OLYM 12(8).pdf | ||
| olym12-8_plans_IFB.pdf | ||
| Physical Data_WA NP OLYM 12(8).zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WFLHD Construction Contract Administration
FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.
Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.
There are no agency-specific additional policies and procedures that exist at this time.
The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).
Time to definitize after receipt of an adequate change order definitization proposal under construction contracts
Number of change order proposals definitized under construction contracts
FY 2021 FY 2022 FY 2023
0 to 30 days 1 1 0 31 to 60 days 1 0 3 61 to 90 days 0 0 3 91 to 180 days 5 1 4 181 to 365 days 0 0 3 366 or more days 2 0 0 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance
0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4