CONSTRUCTION SCHEDULE CONSULTING SERVICES Federal contract opportunity
Solicitation number
69056721Q000044
Issued by
Department of Transportation Federal Highway Administration

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCTION SCHEDULE CONSULTING SERVICES, newest first.
File Type Posted
69056721Q000044_A0002.pdf PDF
21Q000044 QandA_8-19-2021.pdf PDF
21Q000044 QandA_8-17-2021.pdf PDF
21Q000044 QandA_8-16-2021.pdf PDF
21Q000044 QandA_8-12-2021.pdf PDF
69056721Q000044_A0001.pdf PDF
21Q000044 QandA_8-01-2021.pdf PDF
21Q000044 QandA_7-29-2021.pdf PDF
69056721Q000044.pdf PDF
Attachment 0001_PPR Questionnaire.pdf PDF
Attachment 0002_eAuthorization Application.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VENDOR QUESTIONS AND ANSWERS

Solicitation No.:

Project Name:

# General Technical Question Answer Date

1 X

Could you inform me if this is a new requirement or a follow-on to an existing contract? If the latter, could you please provide me with the Contractor Name and Contract #?

This is a new requirement. 27-Jul-2021

2 X What scheduling software will be required for the schedule support? (MS Project and/or Primavera)

Anticipate Bentley Synchro (a free software), Primavera P6, and Microsoft Project

29-Jul-2021

3 X Is the evaluation Factor 1 - Subfactor 1 requirement (current certification as a PMI or PSP professional) required at the time of submission or contract award?

Assuming this question relates to Evaluation Factor 2, Subfactor 1, refer to the last paragraph under Evaluation Factor 2 which states “… subfactor (1) will be evaluated on a pass/fail.” Therefore, all of the Scheduling Professional’s submitted with the RFQ will require a current certification at the time of submission.

29-Jul-2021

4 X

Evaluation Factor 1 – Technical Compliance with Solicitation Requirements states, “… Offerors must submit ALL items identified in Part I of the solicitation.”. Please clarify whether or not there is a particular writeup requested for Factor 1 within the proposal or will it be determined by FHWA whether or not Evaluation Factor 1 has been met following review of all the other evaluation factors of the proposal?

There is no “particular writeup” for Factor 1. The preceding paragraph states “Quotations shall be submitted in two parts consisting of a (1) non-price and

(2) price section.” So, to pass Factor 1, a quotation must include:

• Non-Price Section o Resume(s) not-to-exceed ten (10) single-sided pages for a maximum of three (3) Scheduling Professionals (see Factor 2); and o Narrative describing the methods, techniques, and tools to be used to schedule and accomplish the work (see Factor 3); and o A minimum of three (3) customers complete the Past Performance Reference Questionnaire (Attachment 0001) and submit such surveys to FHWA (see Factor 4);

• Price Section o Completed Cost Schedule (see Factor 5); and o Completed copy of the representations and certifications at FAR 52.204-24, FAR 52.204-26, FAR 52.209-11, and FAR 52.212-3 as applicable -OR- if updated after 10/26/2020, a copy of the Contractor’s FAR Report from SAM.gov; and o Completed copy of the certification at TAR 1252.237-71.

5-Aug-2021

5 X When does FHWA anticipate the baseline scheduling meeting occurring for the 24 separate projects?

Between December 2021 and June 2022 (See amendment 0001 posted to SAM.gov on 8/09/2021 which increases the approximate number of projects to 34).

10-Aug-2021

6 X

If the baseline scheduling meeting for each project is planned to take place around the same time as the preconstruction meeting, in what months have the preconstruction meetings generally occurred in the past?

Preconstruction meetings are typically held within 21 days of project award.

10-Aug-2021

7 X Is there an estimate of the maximum number of baseline schedules that will be submitted in one month?

Currently we estimate February through May 2022 will have somewhere between a maximum of 6 and 13 Initial (baseline) meetings each.

10-Aug-2021

8 X

Is it possible that all 24 baseline schedules could be submitted in a one or two month window, or will the baseline schedule submissions be spread out over the course of several months?

No, they will be distributed over the months of December and June.

10-Aug-2021

CONSTRUCTION SCHEDULE CONSULTING SERVICES

69056721Q000044

VENDOR QUESTIONS AND ANSWERS

NOTE: The actual meeting schedules are based on estimated contract award dates and therefore the exact number of meetings to be attended in any given month is not known at this time. In addition, Amendment 0001 revised the SOW to include participation in the initial (baseline) scheduling meeting and one schedule update meeting on each project. The table below reflects the maximum meetings to be anticipated. Some of the update meetings may be shifted to later months in the contract (verses Jan thru July as shown). This will depend on project needs. Several update meetings may be attended on 1 project and none on another. Plan for no more than 2 meetings to be shifted to any given month (i.e. Aug to the end of the contract) in which case the numbers shown for Jan through July would be decreased accordingly. No more than 68 (Initial + Update) meetings will be attended.