This sources sought notice and statement of work describe a design-build project to renovate Building 509 at the Hunter Holmes McGuire VA Medical Center in Richmond, Virginia to house a 3D printing manufacturing center. The Department of Veterans Affairs seeks a contractor to upgrade building systems including HVAC, electrical, architectural, structural, communications and fire protection. The renovation will enable onsite production of personal protective equipment and other medical supplies using government-furnished 3D printing and finishing equipment. Interested small businesses, including service-disabled and veteran-owned small businesses, must have the capacity to complete schematic design, design development, construction documents and submissions meeting VA standards within 365 calendar days of notice to proceed. Responses are due by November 10, 2020 and should include firm capabilities, three relevant past project descriptions, and certification status if an SDVOSB or VOSB. The contract value is estimated between $500,000 and $1,000,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 652-20-129 SOW Attachment 1 Concept Drawings.pdf | ||
| 36C24621Q0057.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
652-20-129 Renovate Bldg. 509 for 3D Printing Lab 10/16/2020
DESIGN-BUILD SCOPE OF WORK
Renovate Bldg. 509 for 3D Printing Lab 652-20-129
H.H. MCGUIRE VA MEDICAL CENTER, RICHMOND, VA
PROJECT IDENTIFICATION
Project Title: 652-20-129 Renovate Bldg. 509 for 3D Printing Lab Project Location: Building 509
PROJECT DESCRIPTION
H.H. McGuire VAMC is soliciting the expertise of a Construction and/or A/E firm to execute a design/build (DB) action for the renovation of Building 509 to house a 3D printing manufacturing center. The renovation of Building 509 will allow the facility to house and operate new Government furnished 3D printing and finishing equipment to be used in the production of medical personnel protective equipment (PPE) and other medical supplies currently in short supply due to the COVID 19 pandemic.
The design and subsequent renovating will be based upon the functional layout plan provided in Attachment 1. The upgrades to the facility shall include the areas outlined in the functional layout plans and include but are not limited to the following building systems: heating, ventilation, and air conditioning (HVAC) and controls, electrical distribution system, architectural, structural, communication/data and fire protection systems. The designer shall also consider process flow when laying out the new space.
GENERAL DESIGN REQUIRMENTS
1. The Design Build team shall develop a formal schematic design, design development, construction documents and submissions, to include construction cost estimates in accordance with the VA’s master construction guidelines, outlined in the Technical Information Library (TIL), located here: https://www.cfm.va.gov/TIL/spec.asp.
2. Prior to beginning the construction phase of the project, the design documents shall be at 95% complete and the project shall have the following VA approved documents.
a. Construction Schedule
b. Construction Quality and Safety Plans
c. Construction Phasing Plan
d. Interim Life Safety Measures (ILSM’s)
e. Infection Control Risk Assessment (ICRA)
f. Pre-Construction Risk Assessment (PCRA)
3. The DB team shall conduct a survey of the VA facility and all areas where work will be conducted.
4. The DB team shall provide a complete and usable design for the renovation of Building 509 to prepare it to receive Government furnished equipment as laid out in the attached concept plan.
5. The DB team shall completely survey all existing conditions at building 509 to include architectural, electrical, HVAC, plumbing, and structural systems.
6. The DB team shall meet with site staff to review the details of the concept/equipment drawings and to gather feedback after each design submission. The Contractor shall include Engineering Service, Safety and Physical Medicine and Rehabilitation (PM&R) service in all design meetings. The Contractor shall plan on a kickoff meeting with Engineering Service and PM&R to walk the site, pull as-built drawings, review design requirements and verify understanding of the full scope of the project.
7. New building automation controls shall be included in this project.
8. Design documents shall clearly show all demo, existing, relocated and new raceways, wireways and cabling to/from equipment, lights, smoke detectors, outlets, HVAC grills, etc.
9. Design documents shall clearly show all ICRA barriers. The DB team shall work with VA Infection Control staff to develop infection control measures and perform the ICRA.
10. Provide a phasing plan if feasible coordinated with the infrastructure modifications to keep each phase functional during construction. Discussions during the design will assist in the development of acceptable phasing areas of concern that may require off-hours work.
11. Energy savings is a goal for the VA. The design should incorporate energy saving features such as LED lighting, occupancy sensors and other efficient means of minimizing energy use.
DISCIPLINE SPECIFIC REQUIREMENTS
Architectural
a. Design and construction shall include finishes for immediate and adjacent spaces affected by the construction. Design and construct all spaces using current VA design standards and design standards specific to the site. DB shall field verify all room measurements and impacted existing conditions. All new spaces shall be designed to best house the new equipment in the attached equipment list and to encourage process flow in the space.
b. DB shall provide code compliance review. Drawing set shall include code analysis sheet.
c. Provide a separate Life Safety code compliance drawing – this drawing shall show the fire and smoke barrier boundaries for the associated areas.
d. Doors and Door Hardware
a. The VA Design and Program Guides provide guidance on door hardware and guidance shall be followed unless facility guidance alters this guidance.
b. The VA shall receive a narrative of each hardware group used detailing how the door functions in relation to the hardware/programming that is on the specified door.
c. Provide door and hardware schedules on appropriate drawings.
e. Reflected ceiling plan shall show structural support, ceiling tiles/construction, overhead lighting, HVAC, sprinklers, speakers, detectors, etc.
f. Provide required maintenance and servicing clearances. Clearly indicate on floor plan.
g. Provide ceiling openings for maintenance access as required.
h. Special attention shall be given to areas that have a gypsum board ceiling to ensure access to all required equipment is available.
i. DB shall design and construct all wall blocking for equipment mounting.
j. DB shall be provided with specific purchase orders that will describe accessory items. DB shall be responsible for locating, detailing, and building accessory mounting systems.
k. DB shall coordinate electrical raceways and floor penetrations with all other work.
l. Lighting and structural support modifications shall be included in the design and construction.
m. Relocations and modifications of HVAC, electrical and plumbing shall be included in the design and construction, as necessary to bring up to code or as needed to support new equipment.
n. New data and phone cabling shall be included in the design and construction.
Structural
a. DB shall be responsible for design and detail of floor, wall, and ceiling structures in accordance with the weights, moments, and forces as shown in design documents.
b. The DB shall consider the work on the crawlspace/interstitial and demolition shall minimize the removal or weakening of existing structural members and shall include the addition of structural steel when a loss occurs.
c. The DB design shall provide necessary structural changes as required to be able to support the new Government furnished equipment.
Electrical
a. All existing electrical systems and components shall be field verified by the DB electrical engineer.
b. All electrical work shall meet the current version of the National Electric Code (NEC).
c. Design and Construction shall include all electrical plans, elevations, sections, details, diagrams, and schedules showing upgraded power system, electrical closets, power distribution systems, auxiliary power systems, new power systems, lighting fixtures, and outlets. The current electrical system shall be upgraded from a 208/120v 3ph system to an electrical system capable of supported the Government provided equipment.
d. Design-Build documents shall show all necessary normal and emergency service panels, circuits, cabling, wiring, conduit, relays, switches, and disconnects for a complete and usable electrical system to support the new building function including any new HVAC systems and ancillary equipment. All components shall be identified and labeled on design drawings.
e. Incoming power supply for equipment shall be dedicated back to source, isolated, and insulated from any other equipment such as elevators, generators, HVAC systems, etc.
f. Design-Build documents shall include all low voltage systems necessary to meet code and VA standards. The low voltage systems include; fire alarm, public address, voice, data, wireless systems, and PACS (Personnel Access Control System).
g. Utilize site‐specific construction specifications for low voltage and telecommunications.
h. DB design shall coordinate electrical raceways and floor penetrations with all other work.
i. DB design shall coordinate to ensure the Fire Alarm System meets requirements.
j. DB design shall include fire alarm system with full area smoke coverage that is compatible with system at specific site.
k. DB design shall include necessary cable trays/ducts/conduits, correctly sized and located in accordance with vendor equipment drawings.
l. DB design shall include circuit breakers, emergency off button, warning light and door switch connections.
m. DB design shall include layout for equipment cabling. There are cable length limitations that shall be assessed and described on drawings. Design shall include raceways and floor penetrations.
n. Electrical specifications shall include requirement to test and verify equipment power supply to ensure it meets specifications.
o. DB design shall include all grounding and bonding requirements.
p. Design shall include all lighting, switching, and associated power for area. Designer shall research current lighting best practices to promote efficient and effective workflow and incorporate into the design.
q. Consider LED lighting in all areas.
Mechanical
a. Field verify existing conditions. Design for installation and replacement/repair of AHU’s, ductwork, controls, valves, and all other components, as needed.
b. DB HVAC design shall take into account heat load and ventilation requirements of equipment being installed in the space. HVAC equipment design shall maintain heating, cooling and ventilation conditions as set forth in ASHRAE 62.1-2019 and the VA HVAC Design Manual. System shall also provide enough ventilation air to meet equipment requirements.
c. DB design shall include all mechanical plans, elevations, sections, details, schedules for controls, sequence of operations, pumps, valves, piping systems, gages and other devices to support the installation of the new mechanical systems.
d. DB design shall include a building automation system (BAS) with all necessary hardware and software.
e. DB shall include any required modifications to the fire sprinkler system.
f. Contractor shall provide a commissioning plan with checklists for all HVAC equipment.
g. Contract shall include sinks, bathrooms, piping, connections to existing facility piping, valves, drains, etc.
h. Piping design shall comply with VA Plumbing design manual located at: http://www.cfm.va.gov/til/dManual/dmPlbg.pdf . DB design shall note the design requirements for Legionella prevention and include those in this design.
PROPOSED SCHEDULE (calendar days)
| · Notice to Proceed | S-Day | |
| · Design Initiated | S+14 calendar days | |
| · 30% Submission | S+45 calendar days | |
| · 30% Review by VA | S+66 calendar days | |
| · 95% Submission | S+96 calendar days | |
| · 95% Review by VA | S+117 calendar days | |
| · CD Submission | S+150 calendar days | |
| · CD Review by VA | S+165 calendar days | |
| · Mobilization of Construction Contractor | S+120 days | |
| · Construction Complete | S+365 days |
Total Period of Performance – 365 calendar days from issuance of Notice to Proceed
APPLICABLE REFERENCES
The references listed below are not intended to be all inclusive. The Contractor shall ensure that all applicable references and/or standards are followed.
| # |
| VA Standard Title/Section |
| 1 |
| Master Construction Specifications Index (PG-18-1) |
| 2 |
| VHA PROGRAM GUIDE (PG-18-3 Design and Construction Procedures) |
| 3 |
| Standard Details and CAD Standards (PG-18-4) |
| 4 |
| Equipment Guide List (PG-18-5) |
| 6 |
| VA Handbook H-18-8, Seismic Design Requirements |
| 7 |
| Space and Facility Planning (PG-18-9) |
| 8 |
| Design Manuals (PG-18-10) |
| 9 |
| Design Guides (PG-18-12) |
| 10 |
| Barrier Free Design Standard (PG-18-13) |
| 11 |
| Room Finishes, Door and Hardware Schedule (PG-18-14) |
| 12 |
| A/E Submission Instructions (PG-18-15) |
| 13 |
| A/E Design Submission Requirements (Submittal Guide PG-18-15) |
| 14 |
| Environmental Compliance Manual (PG-18-17) |
| 15 |
| Fire Protection Design Manual - Fourth Edition |
| 16 |
| VA Cost Estimating |
| 17 |
| Physical Security Design Manuals for VA Facilities - Mission Critical Facilities |
| 18 |
| VA Signage Design Guide |
| 19 |
| VA Sustainable Design Manual |
| 20 |
| International Building Code Latest Edition |
| 21 |
| National Electric Code – Latest Edition |
| 22 |
| VHA Directive 1061 |
| 23 |
| VA Plumbing Design Manual |