6493-19-001.pdf

PDF 3 MB Posted

Attached to
Flexible Pavement Structure Repair
Solicitation number
6493-19-001
Issued by
Dallas County, Texas

About this file

This is a project description document for the Texas Department of Transportation (TxDOT) Dallas District regarding flexible pavement structure repair work on managed lanes across the Dallas, Denton, and Tarrant County Maintenance Section. The project involves performing pavement repairs on various roadways within this region on a non-site-specific basis, meaning work locations will be determined as needed throughout the contract term. The document outlines the scope of work, technical specifications, and performance requirements for contractors bidding on this opportunity. Specific details regarding response deadlines, bidders' conferences, site visit requirements, and contract award dates are contained within the project specifications.

The project represents a comprehensive maintenance initiative to address flexible pavement structure issues across multiple counties in the North Texas region under TxDOT management. Contractors should review all technical specifications, qualification requirements, and contractual terms detailed in the full solicitation documents to ensure compliance with TxDOT standards and procedures. Pricing, set-asides, funding sources, and contract duration terms are specified in the complete bidding documents and should be reviewed carefully by prospective bidders before submission.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Control 6493-19-001 Project RMC - A00218279 Highway SH 183 County DALLAS

ADDENDUM ACKNOWLEDGMENT

Each bidder is required to acknowledge receipt of an addendum issued for a specific project. This page is provided for the purpose of acknowledging an addendum.

FAILURE TO ACKNOWLEDGE RECEIPT OF AN ADDENDUM WILL RESULT IN THE BID NOT

BEING READ.

In order to properly acknowledge an addendum, place a mark in the box next to the respective addendum.

ADDENDUM NO. 1

ADDENDUM NO. 2

ADDENDUM NO. 3

ADDENDUM NO. 4

ADDENDUM NO. 5

In addition, the bidder by affixing their signature to the signature page of the proposal is acknowledging that they have taken the addendum(s) into consideration when preparing their bid and that the information contained in the addendum will be included in the contract, if awarded by the Commission or other designees.

1-1

This page intentionally left blank.

Project RMC - A00218279 Highway SH 183 County DALLAS

PROPOSAL TO THE TEXAS

TRANSPORTATION COMMISSION

2024 SPECIFICATIONS

Work Consisting of FLEXIBLE PAVEMENT STRUCTURE REPAIR

DALLAS COUNTY, TEXAS

The quantities in the proposal are approximate. The quantities of work and materials may be increased or decreased as considered necessary to complete the work as planned and contemplated.

This project is to be completed in 365 calendar days and will be accepted when fully completed and finished to the satisfaction of the Executive Director or designee.

Provide a proposal guaranty in the form of a Cashier’s Check, Teller’s Check (including an Official Check) or Bank Money Order on a State or National Bank or Savings and Loan Association, or State or Federally chartered Credit Union made payable to the Texas Transportation Commission in the following amount:

FOURTEEN THOUSAND AND 00/100 (Dollars) ( $14,000.00)

A bid bond may be used as the required proposal guaranty. The bond form may be detached from the proposal for completion. The proposal may not be disassembled to remove the bond form. The bond must be in accordance with Item 2 of the specifications.

Any addenda issued amending this proposal and/or the plans that have been acknowledged by the bidder, become part of this proposal.

By signing the proposal the bidder certifies:

1. the only persons or parties interested in this proposal are those named and the bidder has not directly or indirectly participated in collusion, entered into an agreement or otherwise taken any action in restraint of free competitive bidding in connection with the above captioned project.

2. in the event of the award of a contract, the organization represented will secure bonds for the full amount of the contract.

3. the signatory represents and warrants that they are an authorized signatory for the organization for which the bid is submitted and they have full and complete authority to submit this bid on behalf of their firm.

4. that the certifications and representations contained in the proposal are true and accurate and the bidder intends the proposal to be taken as a genuine government record.

• Signed: **

(1) (2) (3) Print Name:

(1) (2) (3) Title:

(1) (2) (3) Company:

(1) (2) (3)

• Signatures to comply with Item 2 of the specifications.

**Note: Complete (1) for single venture, through (2) for joint venture and through (3) for triple venture.

* When the calendar days field contains an asterisk (*) refer to the Special Provisions and General Notes.

NOTICE TO CONTRACTORS

ANY CONTRACTORS INTENDING TO BID ON ANY WORK TO BE AWARDED

BY THIS DEPARTMENT MUST SUBMIT A SATISFACTORY “AUDITED FINANCIAL

STATEMENT” AND “EXPERIENCE QUESTIONNAIRE” AT LEAST TEN DAYS

PRIOR TO THE LETTING DATE.

UNIT PRICES MUST BE SUBMITTED IN ACCORDANCE WITH ITEM 2 OF

THE STANDARD SPECIFICATIONS OR SPECIAL PROVISION TO ITEM 2 FOR

EACH ITEM LISTED IN THIS PROPOSAL.

TEXAS DEPARTMENT OF TRANSPORTATION

BID BOND

KNOW ALL PERSONS BY THESE PRESENTS,

That we, (Contractor Name)

Hereinafter called the Principal, and (Surety Name) a corporation or firm duly authorized to transact surety business in the State of Texas, hereinafter called the Surety, are held and firmly bound unto the Texas Department of Transportation, hereinafter called the Obligee, in the sum of not less than two percent (2%) of the department’s engineer’s estimate, rounded to the nearest one thousand dollars, not to exceed one hundred thousand dollars ($100,000) as a proposal guaranty (amount displayed on the cover of the proposal), the payment of which sum will and truly be made, the said Principal and the said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS, the principal has submitted a bid for the following project identified as:

Control 6493-19-001

Project RMC - A00218279

Highway SH 183

County DALLAS

NOW, THEREFORE, if the Obligee shall award the Contract to the Principal and the Principal shall enter into the Contract in writing with the Obligee in accordance with the terms of such bid, then this bond shall be null and void. If in the event of failure of the Principal to execute such Contract in accordance with the terms of such bid, this bond shall become the property of the Obligee, without recourse of the Principal and/or Surety, not as a penalty but as liquidated damages.

Signed this Day of 20

By:

(Contractor/Principal Name)

(Signature and Title of Authorized Signatory for Contractor/Principal)

*By:

(Surety Name)

(Signature of Attorney-in-Fact) Impressed

*Attach Power of attorney (Surety) for Attorney-in-Fact Surety Seal Only

This form may be removed from the proposal

BIDDER’S CHECK RETURN

IMPORTANT

The space provided for the return address must be completed to facilitate the return of your bidder’s check. Care must be taken to provide a legible, accurate, and complete return address, including zip code. A copy of this sheet should be used for each different return address.

NOTE

Successful bidders will receive their guaranty checks with the executed contract.

RETURN BIDDERS CHECK TO (PLEASE PRINT):

Control 6493-19-001 Project RMC - A00218279 Highway SH 183 County DALLAS

IMPORTANT

PLEASE RETURN THIS SHEET IN ITS ENTIRETY

Please acknowledge receipt of this check(s) at your earliest convenience by signing below in longhand, in ink, and returning this acknowledgement in the enclosed self-addressed envelope.

Check Received By: Date:

Title:

For (Contractor's Name):

Project: County:

NOTICE TO THE BIDDER

In the space provided below, please enter your total bid amount for this project. Only this figure will be read publicly by the Department at the public bid opening.

It is understood and agreed by the bidder in signing this proposal that the total bid amount entered below is not binding on either the bidder or the Department. It is further agreed that the official total bid amount for this proposal will be determined by multiplying the unit bid prices for each pay item by the respective estimated quantities shown in this proposal and then totaling all of the extended amounts.

Total Bid Amount

Control Project Highway County

ALT ITEM DESC SP Bid Item Description Unit Quantity Bid Price Amount Seq

Signed ____________________________________________ Title ____________________________________________ Date ____________________________________________

Additional Signature for Joint Venture:

Signed ____________________________________________ Title ____________________________________________ Date ____________________________________________

Total Bid Amount _______$2,664.00________

EXAMPLE OF BID PRICES SUBMITTED BY COMPUTER PRINTOUT

0001-03-030

STP 2000(938)HES

SH 20

EL PASO

104 509 REMOV CONC (SDWLK) SY 266.400 $10.000 $2,664.00 1

EXAMPLE EXAMPLE EXAMPLE EXAMPLE

EXAMPLES

BID PRICES SUBMITTED BY HAND WRITTEN FORMAT

Unit price for each plant in place

249 014 FLEX BASE(DEL)(DENSCOT)(TY A GR4 CL2) TON 56,787.00 14

ALT

ITEM-CODE

ITEM

NO

DESC

NO

S.P.

NO.

UNIT BID PRICE ONLY

WRITTEN IN WORDS UNIT

APPROX

QUANTITIES

DEPT

USE

ONLY

190 026 RED OAK 1 1/2” - 1 3/4” GAL BB EA 9.000 1

DLRS

CENTS

DLRS

CENTS

Unit price for each ton of Flexible Base

430 001 001 CL A CONC FOR EXT STR (CULV) CY 45.000 27

Unit price for each cubic yard of Concrete

DLRS

CENTS

610 007 001 RDWY ILL ASSEM(TY ST 50T-8-8)(.4 KW)S EA 13.000 7

Unit price of each Roadway Illumination Assembly

DLRS

CENTS

EXAMPLE EXAMPLE EXAMPLE EXAMPLE

RMC - A00218279

Proposal Sheet

DALLAS FORM 234-B I-61-5M

TxDOT PROJECT

COUNTY

ALT

ITEM-CODE

UNIT BID PRICE ONLY.

WRITTEN IN WORDS UNIT APPROX

QUANTITIES

DEPT

USE

ONLY

ITEM

NO.

DESC

CODE

S.P.

No.

344 7020

SP MIXES SP-C SAC-A PG70-22

TON 2,364.390 1 DOLLARS

and CENTS

344 7077

TACK COAT

GAL 2,364.000 2 DOLLARS

and CENTS

351 7011

FLEXIBLE PAVEMENT STRUCTURE REPAIR

(12")

SY 100.000 3 DOLLARS

and CENTS

351 7023

FLEXIBLE PAVEMENT STRUCTURE REPAIR

(24")

SY 700.000 4 DOLLARS

and CENTS

354 7051

PLANE ASPH CONC PAV(2")

SY 21,494.440 5 DOLLARS

and CENTS

500 7002

MOBILIZATION (CALLOUT)

EA 7.000 6 DOLLARS

and CENTS

503 7001

PORTABLE CHANGEABLE MESSAGE SIGN

DAY 30.000 7 DOLLARS

and CENTS

505 7001

TMA (STATIONARY)

DAY 125.000 8 DOLLARS

and CENTS

662 7112

WK ZN PAV MRK SHT TERM (TAB)TY W

EA 100.000 9 DOLLARS

and CENTS

666 7009

REFL PAV MRK TY I (W)6"(DOT)(100MIL)

LF 262.000 10 DOLLARS

and CENTS

666 7024

REFL PAV MRK TY I (W)8"(SLD)(100MIL)

LF 60.000 11 DOLLARS

and CENTS

666 7030

REFL PAV MRK TY I (W)12"(SLD)(100MIL)

LF 256.000 12 DOLLARS

and CENTS

666 7411

REFL PAV MRK TY I (W)6"(SLD)(100MIL)

LF 7,090.000 13 DOLLARS

and CENTS

1-2

RMC - A00218279

Proposal Sheet

DALLAS FORM 234-B I-61-5M

TxDOT PROJECT

COUNTY

ALT

ITEM-CODE

UNIT BID PRICE ONLY.

WRITTEN IN WORDS UNIT APPROX

QUANTITIES

DEPT

USE

ONLY

ITEM

NO.

DESC

CODE

S.P.

No.

666 7423

REFL PAV MRK TY I (Y)6"(SLD)(100MIL)

LF 7,090.000 14 DOLLARS

and CENTS

672 7006

REFL PAV MRKR TY II-C-R

EA 41.000 15 DOLLARS

and CENTS

2-2

CERTIFICATION OF INTEREST IN OTHER BID

PROPOSALS FOR THIS WORK

By signing this proposal, the bidding firm and the signer certify that the following information, as indicated by checking “Yes” or “No” below, is true, accurate, and complete.

A. Quotation(s) have been issued in this firm's name to other firm(s) interested in this work for consideration for performing a portion of this work.

________ YES

________ NO

B. If this proposal is the low bid, the bidder agrees to provide the following information prior to award of the contract.

1. Identify firms which bid as a prime contractor and from which the bidder received quotations for work on this project.

2. Identify all the firms which bid as a prime contractor to which the bidder gave quotations for work on this project.

ENGINEER SEAL

Project RMC - A00218279

Highway SH 183 County DALLAS

The enclosed Texas Department of Transportation Specifications, Special Specifications, Special Provisions, General Notes and Specification Data in this document have been selected by me, or under my responsible supervision as being applicable to this project.

Alteration of a sealed document without proper notification to the responsible engineer is an offense under the Texas Engineering Practice Act.

The seal appearing on this document was authorized by:

Karl Fredrik Fredrickson II P.E.

September 10, 2026

Seal Applies to CSJ(s):

All CSJs within the Contract

155616

Karl Fredrik Fredrickson II

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3A

Specification Data:

Table 1: Soil Constants Requirements

Item Description Plasticity Index

Note Max Min

132 EMBANK (FNL)(DC)(TY C2) 20 10 1

Table 2: Basis of Estimate for Permanent Construction

Item Description Thickness Rate Quantity

SP MIXES SP-C SAC-A

PG70-22

2 Inches 110 Lbs./SY/In 2364.39 Ton

Tack Coat (Undiluted

Application/Spray Rate) Milled HMA 0.11 Gal/SY 2364 Gal

Note:

(1) Asphalt weight based on 110 Lbs./SY/In

General:

This project consists of performing “Flexible Pavement Structure Repair” on various roadways in the Dallas, Denton and Tarrant County Maintenance Section.

Work to be performed under this contract is Non-Site Specific.

Provide and maintain a dedicated email address for receipt of work orders and correspondence throughout the term of this contract. Acknowledgement of emailed work order is required no more than 12 hr. from notification. Begin physical work within 7 days or as directed.

Contractor’s attention is called to the fact that all adjoining pavement sections will be protected during all phases of construction and any damages incurred due to Contractor’s operation will be repaired and replaced at the Contractor’s expense.

No minimum quantity per work order.

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3B

Coordinate work through:

Michael Self

4777 E. Hwy 80

Mesquite, Texas 75150

214-532-9381

Paper bids will be received at 4777 E. Hwy 80, Mesquite, Texas 75150-6643.

Contractor questions on this project are to be addressed to the following individuals:

Karl Fredrickson, P.E. Karl.Fredrickson@txdot.gov

David Morren, P.E. David.Morren@txdot.gov

Questions may be submitted via the Letting Pre-Bid Q&A web page. This webpage can be accessed from the Notice to Contractors dashboard located at the following address:

https://tableau.txdot.gov/views/ProjectInformationDashboard/NoticetoContractors

All contractor questions will be reviewed by the Engineer. All questions and any corresponding responses that are generated will be posted through the same Letting Pre-Bid Q&A web page.

The Letting Pre-Bid Q&A web page for each project can be accessed by using the dashboard to navigate to the project you are interested in by scrolling or filtering the dashboard using the controls on the left. Hover over the blue hyperlink for the project you want to view the Q&A for and click on the link in the window that pops up.

Attention is directed to the possible presence of underground utilities owned by the Texas

Department of Transportation (irrigation, signal, illumination and surveillance, communication, and control) on the right of way. Contact the Department for locates at (214) 320-6682, or DAL-

Locates@txdot.gov a minimum of 72 hours in advance of excavation. The Department is not associated with 811 requests. If city or town owned irrigation facilities are present, contact the appropriate department of the local city or town a minimum of 72 hours in advance of excavation.

If overhead or underground power lines need to be de-energized, contact the electrical service provider to perform this work. Cost associated with de-energizing the power lines or other protective measures required are at no expense to the Department.

If working near power lines, comply with the appropriate sections of Texas State Law and Federal

Regulations relating to the type of work involved.

Item 2 – Instructions to Bidders:

This project includes plan sheets that are not part of the bid proposal.

mailto:Karl.Fredrickson@txdot.gov mailto:David.Morren@txdot.gov https://nam11.safelinks.protection.outlook.com/?url=https%3A%2F%2Ftableau.txdot.gov%2Fviews%2FProjectInformationDashboard%2FNoticetoContractors&data=05%7C01%7CJennifer.Godina%40txdot.gov%7Cde6004deff4b4d5df8bf08daf5a822b1%7C39dba4765c094c6391dace7a3ab5224d%7C0%7C0%7C638092399747995730%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=DXb4Mj2Leer4vJWU8KfwkMamBpxQ0mYw1M2xHRPRwwQ%3D&reserved=0 mailto:DAL-Locates@txdot.gov mailto:DAL-Locates@txdot.gov

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3C

View or download plans at:

http://www.dot.state.tx.us/business/plansonline/agreement.htm

Item 4 – Scope of Work:

Contract extensions will be mutually agreed upon six months prior to the completion of the project.

Unit prices may be adjusted to reflect the current Consumer Price Index for Urban Wage Earners and Clerical Workers (CPI-W).

https://www.ssa.gov/oact/STATS/cpiw.html

Item 7 – Legal Relations and Responsibilities:

Pre-construction safety meeting will be conducted with Contractor’s personnel prior to work beginning on a continuously prosecuted contract or before each work order. Attendance of this meeting will not be paid directly but considered subsidiary to the various bid items.

The Contractor Force Account ‘Safety Contingency’ that has been established for this project is intended to be utilized for work zone enhancements, to improve the effectiveness of the Traffic

Control Plan, which could not be foreseen in the project planning and design stage. These enhancements will be mutually agreed upon by the Engineer and the Contractor’s Responsible

Person based on weekly or more frequent traffic management reviews on the project. The Engineer may choose to use existing bid items if it does not slow the implementation of the enhancement.

Trailer all slow-moving vehicles (designed to operate 25 mph or less) crossing freeway main lanes.

When moving unlicensed equipment on or across any pavement or public highways, protect the pavement from all damages using an acceptable method.

Equipment and materials will not be left on or within 30 ft. of the travel lane during non-working hours, unless approved by the Engineer.

Do not obtain law enforcement personnel without requesting in writing 48 hr. prior to need and the Engineer’s written approval. The Department may compensate the Contractor for providing full time, off-duty, uniformed, law enforcement personnel, and patrol car. The law enforcement personnel may be required for assistance with traffic control for lane or ramp closures or other situations that dictate the need for law enforcement officers as directed. Off-duty law enforcement personnel will have transportation jurisdiction and full police powers. Law enforcement personnel will show proof of certification by the Texas Commission on Law Enforcement (TCOLE).

http://www.dot.state.tx.us/business/plansonline/agreement.htm https://www.ssa.gov/oact/STATS/cpiw.html

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3D

Patrol vehicles must be clearly marked to correspond with the officer’s agency and equipped with appropriate lights to identify them as law enforcement. For patrol vehicles not owned by a law enforcement agency, markings will be retroreflective and legible from 100 ft. from both sides and the rear of the vehicle. Lights will be high intensity and visible from all angles.

Holiday restrictions – the Engineer may decide that no lane closures or construction operations will be allowed during the restricted periods listed in the following holiday schedule. TxDOT has the right to lengthen, shorten, or otherwise modify these restricted periods as actual, or expected, traffic conditions may warrant. Working days will not be charged for these restricted periods. No additional compensation will be allowed for these restricted closures (i.e., overhead, delays, stand-by, barricades or any other associated cost impacts).

• New Year’s Eve and Day (noon on December 31 thru 10 P.M. January 1)

• Easter Holiday weekend (noon on Friday thru 10 P.M. Sunday)

• Memorial Day weekend (noon on Friday thru 10 P.M. Monday)

• Independence Day (noon on July 3 thru 10 P.M. on July 5)

• Labor Day weekend (noon on Friday thru 10 P.M. Monday)

• Thanksgiving Holiday (noon on Wednesday thru 10 P.M. Sunday)

• Christmas Holiday (noon on December 23 thru 10 P.M. December 26)

Holiday restrictions for Independence Day, Thanksgiving Holiday, and the Christmas Holiday may be extended for the “week of” due to the nature of work being performed and the work location at the discretion of the Engineer for safety of the traveling public.

Roadway closures during the following key dates and/or special events are prohibited.

Event Restrictions – No Lane Closures that restricts or interferes with traffic will be allowed for the regional events set forth below. This affects IH30 and IH35E. TxDOT has the right to lengthen, shorten, or otherwise modify these restrictions as actual traffic conditions may warrant. TxDOT also has the right to modify the list of major events as they are added, renamed, rescheduled, or as warranted.

• State Fair of Texas (no lane closures after 6 A.M. on Fridays through 9 P.M. on Sundays;

no full closures for any direction of any facility from opening day through the closing day).

• The University of Texas vs. University of Oklahoma football game (no lane closures beginning 4 hr. prior to the event and ending 3 hr. following event completion).

• The First Responder Bowl (no lane closures beginning 3 hr. prior to the event and ending

2 hr. following the event completion).

• Dallas Mavericks Home Games (no lane closure beginning 2 hr. prior to the event and ending ½ hr. following event commencement with no full lane closures considered until 2

hr. following event completion).

• Dallas Stars Home Games (no lane closure beginning 2 hr. prior to the event and ending ½

hr. following event commencement with no full lane closures considered until 2 hr.

following event completion).

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3E

• Texas Rangers Home Games (no lane closure beginning 2 hr. prior to the event and ending

½ hr. following event commencement with no full lane closures considered until 2 hr.

following event completion).

• Dallas Cowboys Home Games (no lane closure beginning 2 hr. prior to the event and ending ½ hr. following event commencement with no full lane closures considered until 2

hr. following event completion).

• Major Events at the American Airline Center, Globe Life Park in Arlington, AT&T

Stadium with expected attendance exceeding 15,000 (no lane closures beginning 2 hr. prior to event and ending ½ hr. following event commencement with no full closures considered until 2 hr. following event completion).

• Major Downtown Dallas Events (restrictions will be considered on a case-by-case basis).

This category could include, but is not limited to, parades for sports championships, major political events, major Art District Events, and large athletic events such as marathons.

Roadway closures during the following key dates and/or special events are prohibited.

• The University of Texas vs. University of Oklahoma football game (no lane closures beginning 4 hr. prior to the event and ending 3 hr. following event completion).

• Texas Motor Speedway – NASCAR Series Races – April and November

• Texas Motor Speedway – INDY Series Races – June and September

The Contractor will plan work such that no work is ongoing, and all lanes of traffic are available for the NASCAR series races at the Texas Motor Speedway starting the Thursday of race week through Sunday. These races are run usually in early April and Mid-November. The Contractor will not be allowed to have any lane closures on the day of the INDY car races, one of which is usually scheduled during the beginning of June and the other is usually scheduled during Mid-

September. Scheduled events at Texas Motor Speedway may be reviewed at their website:

http://www.texasmotorspeedway.com. All incomplete work activities will need to be shaped up prior to the race events as to pose no hazard to traffic. The above is applicable to each year the work is ongoing.

Item 8 – Prosecution and Progress:

Contract days will be charged in accordance with Section 8.3.1.5, “Calendar Day.”

Working days will be charged in accordance with Section 8.3.3.2.1, “Nighttime Work Only.”

Perform work Sunday through Thursday between 9 P.M. and 5 A.M., unless otherwise approved.

http://www.texasmotorspeedway.com/

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3F

The Lane Closure Assessment Fee is shown on the following table. The fee applies to the

Contractor for closures or obstructions that overlap into restricted hour traffic for each hour or portion thereof, regardless of the duration of the lane closure or obstruction.

Table 3

Lane Closure Assessment Fee Table

Roadway Amount Per Lane

Per Hour

SH 183, SH 114,

SL 12, IH 30, IH 35

$6,250

Item 9 – Measurement and Payment:

Payment for police officer hours will be paid under “Force Account – Law Enforcement

Personnel” and will not exceed the duration of the lane closure. Time will begin when set up operations commence and end when the closure is removed. TxDOT Form 318 will be utilized.

Item 132 – Embankment:

Compact embankment in accordance with Section 132.3.4.1., “Ordinary Compaction”.

Excavated material from the project site becomes property of the contractor and to be removed from the project.

Perform Tex-106-E (Plasticity Index) by an approved laboratory on excavated soils from sources outside right of way when used in roadways embankment. Provide the test results at no expense to the department.

Do not use shaley clays in embankment unless approved in writing.

Use embankment material Type C2 described in Table 1 “Soil Constants Requirements” as shown in the proposed typical sections.

Item 344 – Superpave Mixtures:

Engineer will determine length of overlay in the field. Unless otherwise approved, depth will be 2 in.

Use aggregate that meets the Surface Aggregate Classification (SAC) requirement of Class A for mill and overlay work orders.

Asphalt edges will be beveled to eliminate pavement drop offs.

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3G

An approved anti-stripping agent will be required.

Unless otherwise approved, dumping of the asphalt mixture in a windrow and then placing the mixture in the finishing machine will not be permitted.

Storing the completed mix on the ground will not be permitted at the mixing plant or the job site.

Any mix that comes in contact with the earth or other objectionable foreign matter will be rejected.

Item 351 – Flexible Pavement Structure Repair:

Existing asphalt to be removed will be sawed full depth along neat lines where portions are to be left in place temporarily or permanently.

Do not expose any location that cannot receive the final pavement surface in any one day.

Coarse aggregates to be used in the surface course will have a minimum surface aggregate classification of “B.”

Tack must be placed between each lift of hot mix.

Furnish MS-2 or SS-1 Emulsified Asphalt in accordance with Item 300, “Asphalt, Oils and

Emulsions,” for tack coat.

Provide surface course Superpave SP-C PG 70-22.

The surface of the pavement after compaction will be smooth and true to the established line, grade, and cross section. When tested with a 10-ft. straight edge placed parallel to the centerline of the roadway or tested by other equivalent means, the maximum deviation will not exceed 1/8

in. within 10 ft., unless otherwise approved by the Engineer.

Item 354 – Planing and Texturing Pavement:

During the planing operation, maintain the existing centerline stripe for overnight traffic operations unless full width planing is accomplished in one day. Plane all vertical longitudinal faces with a

3:1 slope to meet Edge Condition I as shown on sheet “Treatment for Various Edge Conditions.”

Maintain the surface of planed surfaces prior to HMAC operations.

The planing operation will be followed closely by the hot-mix asphalt (HMA) overlay operation.

Vacuum loose fines immediately after the milling operation and prior to overlaying with HMA. If inclement weather or other unexpected factors do not allow planed areas to be overlaid as described

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3H above, warning signs per current standard sheet for “Signing for Uneven Lanes” will be maintained until the hot-mix asphalt overlay operation is completed.

If unstable material is observed after initial milling, plane additional material to a depth that will support traffic.

Use a minimum 30 ft. ski on the planing machine.

Item 500 – Mobilization:

One mobilization callout will be paid for each work order. Locations within a work order will generally be limited to one roadway and one direction.

Item 502 – Barricades, Signs, and Traffic Handling:

Close no more than one lane at a time, unless otherwise approved. Provide proposed lane closure information to the Engineer by 1 P.M. on the day prior to the proposed closures. Furnish information for Monday closures or closures following a national or state holiday on the last office workday prior to the closures. Do not close lanes if the above reporting requirements have not been met.

Maximum length of lane closure will be 2 miles.

Traffic Control Plans with a lane closure causing backups of 10 minutes or greater in duration will be modified by the Engineer.

Utilize the managed lanes automated barrier gates to close the corridor for work orders within the reversible managed lanes at IH35E and IH-30. Coordinate these closures with the Managed Lanes

Operations and Maintenance Contractor. All work and expenses related to coordination with the

Managed Lanes Operations and Maintenance Contractor are subsidiary to this Item.

Item 503 – Portable Changeable Message Sign:

Provide Portable Changeable Message Signs (PCMS) units as approved.

Item 505 – Truck Mounted Attenuator (TMA):

The total number of truck mounted attenuators (TMAs) or trailer attenuators (TAs) required when utilizing the traffic control standards are shown in the tables below.

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3I

TCP 5 Series Scenario Required

TMA/TA

(5-1)-18 A B 1

TCP 6 Series Scenario Required

TMA/TA

(6-1)-12 A B 1 2

(6-2)-12 / (6-3)-12 All 1

(6-4)-12 A B 1 2

(6-5)-12 A B 1 2

(6-6)-12 / (6-7)-12 All 1 Per Lane

(6-8)-14 All 1

Shadow vehicles equipped for truck mounted attenuators (TMA) for mobile and stationary operations must be available for use at any time as determined by the Engineer.

The Contractor will be responsible for determining if one or more of these operations will be ongoing at the same time to determine the total number of TMAs/TAs needed for the project for those times per plan requirements. Additional TMAs/TAs used that are not specified in the plans in which the Contractor expects compensation will require prior approval from the Engineer.

Item 585 – Ride Quality for Pavement Surfaces:

Provide a 10-ft. straightedge at all times. Measure and evaluate ride quality of repairs as directed by using Surface Test Type A. Correct surface areas as required.

Item 666 – Retroreflectorized Pavement Markings:

The minimum production rate for long line striping is equal to the Material Placement

Requirements.

Placement of markings in proper alignment will be strictly enforced. Irregular lines placed on both sides of the existing markings will not be accepted.

A gravity flow applicator will be used to funnel the beads onto the stripe. Truck speed will be slow enough to ensure that the beads drop onto the stripe and do not roll in the paint film.

All stripes will be applied in 1 coat.

Layout work will be required where markings have been obliterated, sealed, or overlaid.

Project Number: RMC - A00218279 Control: 6493-19-001

County: Dallas Highway: SH0183

General Notes Sheet 3J

All equipment will be capable of maintaining a continuous work schedule to the satisfactory completion of the project. Equipment used for the contract will be equipped with footage counters capable of measuring the linear footage placed. Counters must be calibrated prior to the beginning of striping operations.

Item 672 – Raised Pavement Markers:

The maximum deviation rate in alignment is 1 in. per 200 ft. of roadway. The maximum deviation is to not exceed 2 in. or be abrupt.

Removal of old existing adhesive material, bituminous or epoxy is required on concrete surfaces.

Bituminous adhesive will not be allowed on concrete pavement.

Only place Raised Pavement Markers where they are missing, broken, or non-reflective unless otherwise directed.

Control : 6493-19-001 Project : RMC - A00218279

DALLAS

SH 183Highway :

County :

TEXAS DEPARTMENT OF TRANSPORTATION

GOVERNING SPECIFICATIONS AND SPECIAL PROVISIONS

ALL SPECIFICATIONS AND SPECIAL PROVISIONS APPLICABLE TO THIS PROJECT ARE

IDENTIFIED AS FOLLOWS:

SPECIAL PROVISIONS :

SPECIAL PROVISIONS WILL GOVERN AND TAKE PRECEDENCE OVER

THE SPECIFICATIONS ENUMERATED HEREON WHEREVER IN

CONFLICT THEREWITH.

STANDARD SPECIFICATIONS:

SUPERPAVE MIXTURES(300) (301) (320) (504) (520) (585) ITEM 344

FLEXIBLE PAVEMENT STRUCTURE REPAIR(104) (132) (204) (247) (260) (275)

(276) (292) (310) (316) (330) (334) (341) (344)

ITEM 351

PLANING AND TEXTURING PAVEMENTITEM 354

MOBILIZATIONITEM 500

PORTABLE CHANGEABLE MESSAGE SIGNITEM 503

TRUCK-MOUNTED ATTENUATOR (TMA) AND TRAILER ATTENUATOR (TA)ITEM 505

WORK ZONE PAVEMENT MARKINGS(666) (668) (672) (677) ITEM 662

RETROREFLECTORIZED PAVEMENT MARKINGS(316) (502) (662) (667) (677)

(678)

ITEM 666

RAISED PAVEMENT MARKERS(677) (678) ITEM 672

ITEMS 1-9 INCL., GENERAL REQUIREMENTS AND COVENANTS

ADOPTED BY THE TEXAS DEPARTMENT OF TRANSPORTATION

SEPTEMBER 1, 2024.

STANDARD SPECIFICATIONS ARE INCORPORATED INTO THE

CONTRACT BY REFERENCE.

"NONDISCRIMINATION" (000---001) SPECIAL PROVISION

"CERTIFICATE OF INTERESTED PARTIES (FORM 1295)" (000---017) SPECIAL PROVISION

"NOTICE OF CONTRACTOR PERFORMANCE EVALUATIONS" (000---

125)

SPECIAL PROVISION

"SCHEDULE OF LIQUIDATED DAMAGES" (000---224) SPECIAL PROVISION

(002---004) SPECIAL PROVISION TO ITEM 002

(003---006) SPECIAL PROVISION TO ITEM 003

(004---003) SPECIAL PROVISION TO ITEM 004

(007---001) SPECIAL PROVISION TO ITEM 007

(008---001) SPECIAL PROVISION TO ITEM 008

(009---002) SPECIAL PROVISION TO ITEM 009

(247---001) SPECIAL PROVISION TO ITEM 247

(260---001) SPECIAL PROVISION TO ITEM 260

(275---001) SPECIAL PROVISION TO ITEM 275

(292---001) SPECIAL PROVISION TO ITEM 292

(300---003) SPECIAL PROVISION TO ITEM 300

(666---002) SPECIAL PROVISION TO ITEM 666

(672---001) SPECIAL PROVISION TO ITEM 672

1-2

GENERAL :

THE ABOVE-LISTED SPECIFICATIONS ITEMS ARE THOSE UNDER WHICH

PAYMENT IS TO BE MADE. THESE, TOGETHER WITH SUCH OTHER PERTINENT

ITEMS, IF ANY, AS MAY BE REFERRED TO IN THE ABOVE-LISTED

SPECIFICATION ITEMS, AND INCLUDING THE SPECIAL PROVISIONS LISTED

ABOVE, CONSTITUTE THE COMPLETE SPECIFICATIONS FOR THIS PROJECT.

SPECIAL SPECIFICATIONS :

2-2

CHILD SUPPORT STATEMENT

Under section 231.006, Family Code, the vendor or applicant certifies that the individual or business entity named in this contract, bid, or application is not ineligible to receive the specified grant, loan, or payment and acknowledges that this contract may be terminated and payment may be withheld if this certification is inaccurate.

CONFLICT OF INTEREST CERTIFICATION

Pursuant to Texas Government Code Section 2261.252(b), the Department is prohibited from entering into contracts in which Department officers and employees have a financial interest.

By signing the Contract, the Contractor certifies that it is not prohibited from entering into a Contract with the Department as a result of a financial interest as defined under Texas Government Code Section 2261.252(b), and that it will exercise reasonable care and diligence to prevent any actions or conditions that could result in a conflict of interest with the Department.

The Contractor also certifies that none of the following individuals, nor any of their family members within the second degree of affinity or consanguinity, owns 1% or more interest or has a financial interest as defined under Texas Government Code Section 2261.252(b) in the Contractor:

Any member of the Texas Transportation Commission; and The Department’s Executive Director, General Counsel, Chief of Procurement and Field Support

Operations, Director of Procurement, and Director of Contract Services.

Violation of this certification may result in action by the Department.

E-VERIFY CERTIFICATION

Pursuant to Texas Transportation Code §223.051, all TxDOT contracts for construction, maintenance, or improvement of a highway must include a provision requiring Contractors and subcontractors to use the U.S. Department of Homeland Security’s E-Verify system to determine employment eligibility. By signing the contract, the Contractor certifies that prior to the award of the Contract:

the Contractor has registered with and will, to the extent permitted by law, utilize the United States Department of Homeland Security’s E-Verify system during the term of the Contract to determine the eligibility of all persons hired to perform duties within Texas during the term of the agreement; and the Contractor will require that all subcontractors also register with and, to the extent permitted by law, utilize the United States Department of Homeland Security’s E-Verify system during the term of the subcontract to determine the eligibility of all persons hired to perform duties within Texas during the term of the agreement.

Violation of this requirement constitutes a material breach of the Contract, subjects a subcontractor to removal from the Contract, and subjects the Contractor or subcontractors to possible sanctions in accordance with Title 43, Texas Administrative Code, Chapter 10, Subchapter F, “Sanctions and Suspension for Ethical Violations by Entities Doing Business with the Department.”

_BPSDocName 1-1

Certification Regarding Disclosure of Public Information Pursuant to Subchapter J, Chapter 552, Texas Government Code, contractors executing a contract with a governmental body that results in the expenditure of at least $1 million in public funds must:

1) preserve all contracting information* as provided by the records retention requirements applicable to Texas Department of Transportation (TxDOT) for the duration of the contract,

2) on request of TxDOT, promptly provide any contracting information related to the contract that is in the custody or possession of the entity, and

3) on completion of the contract, either:

A. provide, at no cost to TxDOT, all contracting information related to the contract that is in the custody or possession of the entity, or B. preserve the contracting information related to the contract as provided by the records retention requirements applicable to TxDOT

The requirements of Subchapter J, Chapter 552, Government Code, may apply to this contract, and the contractor or vendor agrees that the contract can be terminated if the contractor or vendor knowingly or intentionally fails to comply with a requirement of that subchapter.

By entering into Contract, the Contractor agrees to:

• provide, or make available, to TxDOT and any authorized governmental investigating or auditing agency all records, including electronic and payment records related to the contract, for the same period provided by the records retention schedule applicable to TxDOT, and

• ensure that all subcontracts include a clause requiring the same.

* As defined in Government Code §552.003, “Contracting information” means the following information maintained by a governmental body or sent between a governmental body and a vendor, contractor, potential vendor, or potential contractor:

1) information in a voucher or contract relating to the receipt or expenditure of public funds by a governmental body;

2) solicitation or bid documents relating to a contract with a governmental body;

3) communications sent between a governmental body and a vendor, contractor, potential vendor, or potential contractor during the solicitation, evaluation, or negotiation of a contract;

4) documents, including bid tabulations, showing the criteria by which a governmental body evaluates each vendor, contractor, potential vendor, or potential contractor responding to a solicitation and, if applicable, an explanation of why the vendor or contractor was selected; and

5) communications and other information sent between a governmental body and a vendor or contractor related to the performance of a final contract with the governmental body or work performed on behalf of the governmental body.

CERTIFICATION TO NOT BOYCOTT ISRAEL

Pursuant to Texas Government Code §2271.002, the Department must include a provision requiring a written verification affirming that the Contractor does not boycott Israel, as defined in Government Code §808.001, and will not boycott Israel during the term of the contract. This provision applies to a contract that:

1) is with a Contractor that is not a sole proprietorship,

2) is with a Contractor with 10 or more full-time employees, and

3) has a value of $100,000 or more.

By signing the contract, the Contractor certifies that it does not boycott Israel and will not boycott Israel during the term of this contract. “Boycott” means refusing to deal with, terminating business activities with, or otherwise taking any action that is intended to penalize, inflict economic harm on, or limit commercial relations specifically with Israel, or with a person or entity doing business in Israel or in an Israeli-controlled territory, but does not include an action made for ordinary business purposes.

CERTIFICATION TO NOT BOYCOTT ENERGY COMPANIES

Pursuant to Texas Government Code §2274.002, the Department must include a provision requiring a written verification affirming that the Contractor does not boycott energy companies, as defined in Government Code §809.001, and will not boycott energy companies during the term of the contract. This provision applies to a contract that:

1) is with a Contractor that is not a sole proprietorship,

2) is with a Contractor with 10 or more full-time employees, and

3) has a value of $100,000 or more.

By signing the contract, the Contractor certifies that it does not boycott energy companies and will not boycott energy companies during the term of this contract. “Boycott” means taking any action that is intended to penalize, inflict economic harm on, or limit commercial relations with a company because the company: (1) engages in the exploration, production, utilization, transportation, sale, or manufacturing of fossil fuel-based energy and does not commit or pledge to meet environmental standards beyond applicable federal and state law; or (2) does business with a company described by (1).

CERTIFICATION TO NOT DISCRIMINATE AGAINST

FIREARM ENTITIES OR FIREARM TRADE ASSOCIATIONS

Pursuant to Texas Government Code §2274.002, the Department must include a provision requiring a written verification affirming that the Contractor:

1) does not have a practice, policy, guidance, or directive that discriminates against a firearm entity or firearm trade association, as defined in Government Code §2274.001, and

2) will not discriminate against a firearm entity or firearm trade association during the term of the contract.

This provision applies to a contract that:

1) is with a Contractor that is not a sole proprietorship,

2) is with a Contractor with 10 or more full-time employees, and

3) has a value of $100,000 or more.

By signing the contract, the Contractor certifies that it does not discriminate against a firearm entity or firearm trade association as described and will not do so during the term of this contract. "Discriminate against a firearm entity or firearm trade association" means, with respect to the entity or association, to:

(1) refuse to engage in the trade of any goods or services with the entity or association based solely on its status as a firearm entity or firearm trade association; (2) refrain from continuing an existing business relationship with the entity or association based solely on its status as a firearm entity or firearm trade association; or (3) terminate an existing business relationship with the entity or association based solely on its status as a firearm entity or firearm trade association. "Discriminate against a firearm entity or firearm trade association" does not include: (1) the established policies of a merchant, retail seller, or platform that restrict or prohibit the listing or selling of ammunition, firearms, or firearm accessories; (2) a company’s refusal to engage in the trade of any goods or services, decision to refrain from continuing an existing business relationship, or decision to terminate an existing business relationship to comply with federal, state, or local law, policy, or regulations or a directive by a regulatory agency, or for any traditional business reason that is specific to the customer or potential customer and not based solely on an entity ’s or association’s status as a firearm entity or firearm trade association.

FOREIGN ADVERSARIES REQUIREMENTS

Pursuant to Executive Order No. GA-48 relating to the hardening of state government, TxDOT must require any company that submits a bid or proposal with respect to a contract for goods or services to the Department to certify that the company, and, if applicable, any of its holding companies or subsidiaries, is not:

A. Listed in Section 889 of the 2019 National Defense Authorization Act (NDAA); or

B. Listed in section 1260H of the 2021 NDAA; or

C. Owned by the government of a country on the U.S. Department of Commerce foreign adversaries list under 15 C.F.R. 791.4; or

D. Controlled by any governing or regulatory body located in a country on the U.S. Department of Commerce’s foreign adversaries list under 15 C.F.R. 791.4.

By signing this proposal, the Contractor certifies that neither it nor any affiliated entities are:

• Listed in Section 889 of the 2019 NDAA;

• Listed in Section 1260H of the 2021 NDAA;

• Owned by the government of a country listed under 15 C.F.R. 791.4; or

• Controlled by any governing or regulatory body located in a country listed under 15 C.F.R.

791.4

Prohibited Activities by Contractors and Vendors

Pursuant to Texas Government Code 2261.302, a state agency contractor, subcontractor, or vendor responding to a contract solicitation may not directly or indirectly:

(1.) engage in surveillance targeting:

(a.) a member of the state legislature or a person employed to support the state legislature in any capacity, (b.) a family member of a person described in subsection (a), (c.) a state agency employee, or (d.) an individual making a complaint or raising concerns regarding state agency operations or contracting;

(2.) engage in an act of intimidation, coercion, extortion, undue influence, or other similar conduct intended to influence, silence, or retaliate against a person described in subsection (1) above, or;

(3.) use private or confidential information to manipulate or influence a state contracting decision or proceeding.

By signing this proposal, the bidder certifies that it will not engage in surveillance targeting or an act of intimidation, coercion, extortion, undue influence, or other similar conduct intended to influence, silence, or retaliate against a member of the state legislature, a person employed to support the state legislature in any capacity, a family member of an aforementioned person, a state agency employee, or an individual making a complaint or raising concerns regarding state agency operations or contracting.

Furthermore, the bidder certifies that it will not use private or confidential information to manipulate or influence a state contracting decision or proceeding.

2024 Specifications 000-001

1 06-23 Statewide

Special Provision to Item 000

Nondiscrimination

1. DESCRIPTION

All recipients of federal financial assistance are required to comply with various nondiscrimination laws, including Title VI of the Civil Rights Act of 1964, as amended (Title VI). Title VI forbids discrimination against anyone in the United States on the grounds of race, color, or national origin by any agency receiving federal funds.

The Texas Department of Transportation, as a recipient of federal financial assistance, and under Title VI and related statutes, ensures that no person will on the grounds of race, religion (where the primary objective of the financial assistance is to provide employment in accordance with 42 USC 2000d-3), color, national origin, sex, age, or disability be excluded from participation in, be denied the benefits of, or otherwise be subjected to discrimination under any Department programs or activities.

2. DEFINITION OF TERMS

Where the term “Contractor” appears in the following six nondiscrimination clauses, the term “Contractor” is understood to include all parties to Contracts or agreements with the Department.

3. NONDISCRIMINATION PROVISIONS

During the performance of this Contract, the Contractor agrees as follows.

3.1. Compliance with Regulations. The Contractor must comply with the Regulations pertinent to nondiscrimination in federally assisted programs of the United States Department of Transportation 49 CFR 21, as they may be amended from time to time, (hereinafter referred to as the Regulations), which are herein incorporated by reference and made a part of this Contract.

3.2. Nondiscrimination. The Contractor, regarding the work performed during the Contract, must not discriminate on the grounds of race, color, or national origin in the selection and retention of subcontractors, including procurements of materials and leases of equipment. The Contractor must not participate either directly or indirectly in the discrimination prohibited by Section 21.5 of the Regulations, including employment practices when the Contract covers a program set forth in Appendix B of the Regulations.

3.3. Solicitations for Subcontracts, Including Procurements of Materials and Equipment. In all solicitations either by competitive bidding or negotiation made by the Contractor for work to be performed under a subcontract, including procurements of materials or leases of equipment, the Contractor must notify each potential subcontractor or supplier of the Contractor’s obligations under this Contract and the Regulations relative to nondiscrimination on the grounds of race, color, or national origin.

3.4. Information and Reports. The Contractor must provide all information and reports required by the Regulations or directives issued pursuant thereto, and must permit access to its books, records, accounts, other sources of information, and facilities as may be determined by the Recipient or the Department to be pertinent to ascertain compliance with such Regulations, orders, and instructions. Where any information required of a Contractor is in the exclusive possession of another who fails or refuses to furnish this information, the Contractor must so certify to the Recipient, or the Department as appropriate, and must set forth what efforts it has made to obtain the information.

3.5. Sanctions for…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .