6-01-PondSprings-BidForm.xlsx

XLSX spreadsheet 692 KB Posted

Attached to
26IFB26 Pond Springs Road Area Drainage Improvements
Solicitation number
26IFB26
Issued by
Williamson County, Texas

About this file

This is a bid form for the Pond Springs Road Area Drainage Improvements project in Williamson County, Texas. The project encompasses construction of a new storm sewer and water line, along with associated pavement finishing and striping work. The bid form itemizes 76 line items across multiple work categories, including mobilization, traffic handling, erosion control, pipe installation (ranging from 2-inch copper to 18-inch RCP), concrete structures (junction boxes, manholes, curb inlets), pavement removal and resurfacing, concrete curb and sidewalk work, and extensive pavement markings and striping. Quantities vary significantly across items, ranging from single units for specialized items such as junction boxes and gate valves to large-scale linear footage requirements, such as 11,052 linear feet for work zone pavement mark removal and 5,115 linear feet for reflectorized thermoplastic pavement markings in yellow. The form includes five force account line items for estimated bonuses or penalties and contingency work, with one item (999-WC01 Soil Retention Blankets) pre-calculated at $25,000.00.

The bid form requires contractors to provide unit costs for each line item, with the total bid amount currently showing $25,000.00, representing only the pre-calculated force account item. All costs for compliance with the Request for Bids, specifications, and contract provisions must be included in the unit prices provided, with no separate compensation offered unless expressly stated. The form designates specific roles for project personnel, including Maria Castanon and James Chamberlin as engineers responsible for inserting bid quantities and specifications, and Christen Eschberger as the contractor responsible for inserting unit costs and the total bid amount. The bid form structure allows for flexible quantity adjustments by engineering personnel prior to final submission, indicating this may be a preliminary or template version pending finalization of actual project quantities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Form

PROJECT:POND SPRINGS DRAINAGE AREA IMPROVEMENTS
Maria Castanon: Engineer to Insert Project NameBIDDER:
Christen Eschberger: Contractor to Insert Bidder NameFull compensation for compliance with each and every provision of the Request for Bids, the Bid, the Specifications, and the Contract will be considered as included in the unit prices for the work set forth below, and no separate payment will be made for compliance with each and every provision of the Request for Bids, the Bid, the Specifications, and the Contract, unless separate payment is expressly provided for therein.
BIDTECHDESCRIPTIONBIDUNITUNIT COSTAMOUNT BID
ITEMSPEC1QUANTITYMEASURE
10467-7099SET (TY I) (S= 5 FT) (HW= 4 FT) (3:1) (C)2

James Chamberlin: Engineer to insert Bid Quantity

EA$ - 0
20496-7004REMOV STR (SET)2

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostEA$ - 0
30496-7007REMOV STR (PIPE)122

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostLF$ - 0
40500-7001MOBILIZATION1

James Chamberlin: Engineer to insert Bid Quantity James Chamberlin: Contractor to Insert Unit Cost

LS$ - 0
50502-7001BARRICADES, SIGNS AND TRAFFIC HANDLING7

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostMO$ - 0
60503-7002PORTABLE CHANGEABLE MESSAGE SIGN2

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit Cost EA James Chamberlin: Contractor to Insert Unit Cost

$ - 0
70506 7023CONSTRUCTION EXITS (INSTALL) (TY 4)187SY$ - 0
80512-7009PORT CTB (FUR & INST)(LOW PROF)(TY 1)2032

James Chamberlin: Engineer to insert Bid Quantity

LF$ - 0
90512-7010PORT CTB (FUR & INST)(LOW PROF)(TY 2)160

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostLF$ - 0
100512-7033PORT CTB (MOVE)(LOW PROF)(TY 1)621

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostLF$ - 0
110512-7034PORT CTB (MOVE)(LOW PROF)(TY 2)220

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit Cost

LF$ - 0
120512-7057PORT CTB (REMOVE)(LOW PROF)(TY 1)2032

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostLF$ - 0
130512-7058PORT CTB (REMOVE)(LOW PROF)(TY 2)160

James Chamberlin: Engineer to insert Bid Quantity James Chamberlin: Contractor to Insert Unit Cost

LF$ - 0
140662-7064WK ZN PAV MRK REMOV (W)4"(SLD)11052

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit Cost

LF$ - 0
150662-7070WK ZN PAV MRK REMOV (W)8"(DOT)860

James Chamberlin: Engineer to insert Bid Quantity James Chamberlin: Contractor to Insert Unit Cost LF James Chamberlin: Contractor to Insert Unit Cost

$ - 0
160662-7072WK ZN PAV MRK REMOV (W)8"(SLD)115LF$ - 0
170662-7095WK ZN PAV MRK REMOV (Y)4"(BRK)2949
James Chamberlin: Engineer to insert Bid QuantityLF$ - 0
180662-7097WK ZN PAV MRK REMOV (Y)4"(SLD)8807

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostLF$ - 0
19COA 101S-BPreparing Right-of-Way17

Maria Castanon: Engineer to Insert Bid Quantity

James Chamberlin: Contractor to Insert Unit Cost

STA$ - 0PREPARING ROW
20COA 104S-ARemove P.C. Concrete Curb11

James Chamberlin: Engineer to insert Bid Quantity

Christen Eschberger: Contractor to Insert Unit CostLF$ - 0
21COA 104S-BRemove P.C. Concrete Curb248

Maria Castanon: Engineer to Insert Bid Quantity

Christen Eschberger: Contractor to Insert Unit CostSF$ - 0PREPARING ROW
22COA 104S-CRemove P.C. Concrete Sidewalks and Driveways74

Maria Castanon: Engineer to Insert Bid Quantity

Christen Eschberger: Contractor to Insert Unit CostSY$ - 0PREPARING ROW
23COA 312S-ASeal Coat, (AC-15P, HFRS-2P OR CRS-2P)2311

Maria Castanon: Engineer to Insert Bid Quantity

Christen Eschberger: Contractor to Insert Unit CostGAL$ - 0PREPARING ROW
24COA 312S-BSeal Coat, (TY-D GR-5)50

James Chamberlin: Engineer to insert Bid Quantity

Christen Eschberger: Contractor to Insert Unit CostCY$ - 0
25COA 315S-ASurface Milling7217

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostSY$ - 0
26COA 340S-AHot Mix Asphaltic Concrete Pavement, TY-D PG70-22830

James Chamberlin: Engineer to insert Bid Quantity James Chamberlin: Contractor to Insert Unit Cost

TON
James Chamberlin: Contractor to Insert Unit Cost$ - 0
27COA 401S-BCommon Structural Excavation1592CY$ - 0
28COA 402-AControlled Low Strength Material421CY$ - 0
29COA 430S-AP.C. Concrete Curb and Gutter (Excavation)337
James Chamberlin: Engineer to insert Bid QuantityLF$ - 0
30COA 432SR-4Reconstruct Concrete sidewalks to 4 inch thickness, including removal of exisitng sidewalk69

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit Cost

SF$ - 0
31COA 433S-CType II P.C. Concrete Driveway1781

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit Cost

SF
James Chamberlin: Contractor to Insert Unit Cost$ - 0
32COA 506-J8x8Junction Box, 8 Ft. x 8 Ft.5EA$ - 0
33COA 506-J16x8Junction Box, 16 Ft. x 8 Ft.1EA$ - 0
34COA 506-M4Standard Pre-cast Manhole w/Pre-cast Base, 4' Dia.3EA$ - 0
35COA 508S-I10SCurb Inlet, Standard, 10ft3EA$ - 0
36COA 509S-1Trench Excavation Safety Protective Systems (all depths)1406LF$ - 0
37COA 510-ASD-18-CLVPipe, 18" dia., RCP-CL V (all depths)294LF$ - 0
38COA 510-AW-2"-WPipe, 2" Dia.Copper Type K, Complete in Place, Including Excavation and Backfill53LF$ - 0
39COA 510-AWRJ-8"-WPipe, 8" Dia. DI CL-350 (Restrained), all depths, Complete in Place, Including Excavation and Backfill96LF$ - 0
40COA 510-AWRJ-12"-WPipe, 12" Dia. DI CL-350 (Restrained), all depths, Complete in Place, Including Excavation and Backfill20LF$ - 0
41COA 510-JW-12"X8"Wet Connections, 12"x8"1
James Chamberlin: Engineer to insert Bid QuantityEA$ - 0
42COA 510-KWDuctile Iron Fittings (C-110 Weight Schedule)0.12

James Chamberlin: Engineer to insert Bid Quantity James Chamberlin: Contractor to Insert Unit Cost

TON$ - 0
43COA 511-A-8"Valves, Gate 8" Dia.1

James Chamberlin: Engineer to insert Bid Quantity James Chamberlin: Contractor to Insert Unit Cost EA James Chamberlin: Contractor to Insert Unit Cost

$ - 0
44COA 559S-5x2Precast Concrete Box Culverts, 5 FT x 2FT42LF$ - 0
45COA 559S-5x3Precast Concrete Box Culverts, 5 FT x 3FT558LF$ - 0
46COA 559S-5x4Precast Concrete Box Culverts, 5 FT x 4FT591LF$ - 0
47COA-602S-ABermuda Block Sodding739SY$ - 0
48COA-639SRock Berm100LF$ - 0
49COA-642SSilt Fence for Erosion Control894LF$ - 0
50COA-648SMulch Sock1298LF$ - 0
51COA 705Remove and Relocate Existing Metal Beam Guard Railing67

James Chamberlin: Engineer to insert Bid Quantity

LF
James Chamberlin: Contractor to Insert Unit Cost$ - 0
52COA 829A-4WType I Bicycle Lane Markings 4 inches in width, W in color4313LF$ - 0
53COA 829S-BType I Bicycle Lane Preferential (directional arrow) Symbol, w in color21EA$ - 0
54COA 829S-CType I Bicycle Lane (Biker Rider) Symbol, W in color12EA$ - 0
55COA 829S-E-4WType II Bicycle Lane Markings 4 inch in width, W in color4313LF$ - 0
56COA 829S-FType II Bicycle Lane Preferential (directional arrow) Symbol, W in color21EA$ - 0
57COA 829S-GType II Bicycle Lane (Biker Rider) Symbol, W in color12EA$ - 0
58COA 863S-3Reflectorized Pavement Markers (Type II-A-A)106EA$ - 0
59COA 863S-5Reflectorized Pavement Markers (Type II-C-R)7EA$ - 0
60COA 871S-A-4WReflectorized Type I Thermoplastic Pavement Markings, 4 inches in width, 90 mils in thickness, W in color531LF$ - 0
61COA 871S-A-4YReflectorized Type I Thermoplastic Pavement Markings, 4 inches in width, 90 mils in thickness, Y in color5115LF$ - 0
62COA 871S-A-8WReflectorized Type I Thermoplastic Pavement Markings, 8 inches in width, 90 mils in thickness, W in color138LF$ - 0
63COA 871S-A-24WReflectorized Type I Thermoplastic Pavement Markings, 24 inches in width, 90 mils in thickness, W in color70LF$ - 0
64COA 871S-DReflectorized Type I Thermoplastic Pavement Chevrons, 90 mils in thickness, w in color142EA$ - 0
65COA 871S-E-4WReflectorized Type II Paint Pavement Markings 4 inches in width, W in color531LF$ - 0
66COA 871S-E-4YReflectorized Type II Paint Pavement Markings 4 inches in width, Y in color5115
James Chamberlin: Engineer to insert Bid QuantityLF$ - 0
67COA 871S-E-8WReflectorized Type II Paint Pavement Markings 8 inches in width, W in color138

James Chamberlin: Engineer to insert Bid Quantity James Chamberlin: Contractor to Insert Unit Cost

LF$ - 0
68COA 871S-E-24WReflectorized Type II Paint Pavement Markings 24 inches in width, W in color70

James Chamberlin: Engineer to insert Bid Quantity

James Chamberlin: Contractor to Insert Unit CostLF$ - 0
69COA 871S-HReflectorized Type II Paint Pavement Chevrons, W in color142

Maria Castanon: Engineer to Insert Bid Quantity

James Chamberlin: Contractor to Insert Unit Cost

EA
Christen Eschberger: Contractor to Insert Unit Cost$ - 0PREPARING ROW
70COA 872S-APrefabricated Pavement Markings (Word), W in color1EA$ - 0
71COA 872S-BTrench Excavation Safety Protection System (All Depths)1EA$ - 0
72COA 874S-A6ELIM EXT PAV MRK & MRKS (6")11000LF$ - 0
73COA SP510-BW-2"x2" DiaWater Service Reconnection, including 2” Corporation Stop, Tap to Main, as well as removal of the existing components1

Maria Castanon: Engineer to Insert Bid Quantity

EA
Christen Eschberger: Contractor to Insert Unit Cost$ - 0PREPARING ROW
74COA SP510-JW-AC-8''x8"AC Pipe Connections, 8" Dia. x 8" Dia.1EA$ - 0
75COA SP510-JW-CI-12''x12"CI Pipe Connections, 12" Dia. x 12" Dia.1EA$ - 0
76SP-A400-W8" DiaRemoving Pipe, 8" Diameter, AC Pipe - For Removal at Storm Crossings, Required Restrained Joints, to Existing Couplings, and Other Areas Specified on Plans; Pipe Removal shall include the cost of trench and pavement repairs, Complete and in place; Removal of valves considered subsidiary to cost of pipe removal92LF$ - 0
NON-BID ITEMS TO BE INCLUDED IN BID AND CONTRACT AMOUNT. DO NOT MAKE CHANGES TO THIS SECTION.
585-WC01FORCE ACCOUNT - ESTIMATED RIDE QUALITY BONUS/PENALTYDOL$ 1.00$ - 0
76999-WC01FORCE ACCOUNT25000DOL$ 1.00$ 25,000.00SOIL RETENTION BLANKETS (CL 1) (TY C)
999-WC02FORCE ACCOUNT - RAILROAD FLAGGERSDOL$ 1.00$ - 0
3076-WC01FORCE ACCOUNT - ESTIMATED PLACEMENT AND PRODUCTION BONUS/PENALTY (TY B)DOL$ 1.00$ - 0
3076-WC02FORCE ACCOUNT - ESTIMATED PLACEMENT AND PRODUCTION BONUS/PENALTY(TY D SURFACE)DOL$ 1.00$ - 0SOIL RETENTION BLANKETS (CL 1) (TY C)
TOTAL AMOUNT OF BID
Dollars and
Christen Eschberger: Contractor to Insert Total Amount of Bid in WordsCents$ 25,000.00

NOTE: THE COURT MAY EITHER REJECT ALL BIDS OR AWARD A CONTRACT TO THE LOWEST AND BEST BID.

Note To User: If Alternate Bid is utilized, include instructions for how to complete the Alternate Bid section.
For example, identify those Items in the Base Bid which are being replaced by the Alternate Items, as applicable.

&"Arial,Bold"BID FORM

WILLIAMSON COUNTY, TEXAS

&9 &X1&XRefer to the Technical Specifications section for a description of the specific reference number. &8Page &P of &N

Sheet1

COA 101S-B
COA 104S-A
COA 104S-B
COA 104S-C
COA 312S-A
COA 312S-B
COA 315S-A
COA 340S-A
COA 430S-A
COA 432SR-4
COA 433S-C
COA 705
0502-7001
0503-7002
0512-7009
0512-7010
0512-7033
0512-7034
0512-7057
0512-7058
0662-7064
0662-7070
0662-7072
0662-7095
0662-7097
COA 874S-A6
0467-7099
0496-6004
0496-6007
COA 401S-B
COA 402-A
COA 506-J8x8
COA 506-J16x8
COA 506-M4
COA 508S-I10S
COA 509S-1
COA 510-ASD-18-CLV
COA 559S-5x2
COA 559S-5x3
COA 559S-5x4
0506 7023
COA-602S-A
COA-639S
COA-642S
COA-648S
COA 829A-4W
COA 829S-B
COA 829S-C
COA 829S-E-4W
COA 829S-F
COA 829S-G
COA 863S-3
COA 863S-5
COA 871S-A-4W
COA 871S-A-4Y
COA 871S-A-8W
COA 871S-A-24W
COA 871S-D
COA 871S-E-4W
COA 871S-E-4Y
COA 871S-E-8W
COA 871S-E-24W
COA 871S-H
COA 872S-A
COA 872S-B
COA 509-A
COA 510-AW-2"-W
COA 510-AWRJ-8"-W
COA 510-AWRJ-12"-W
COA 510-JW-12"X8"
COA 510-KW
COA SP510-BW-2"x2" Dia
COA SP510-JW-AC-8''x8"
COA SP510-JW-CI-12''x12"
COA 511-A-8"
SP-A400-W8" Dia
0500 7001

File details come from the government source that posted it. Updated .