5__02827_fence_removal_mvo.docx
DOCX document 21 KB Posted
- Attached to
- HANNA DRAW FENCE CONVERSION Federal contract opportunity
- Solicitation number
- 140L6221R0047
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 00_Bid_Schedule.xlsx | XLSX spreadsheet | |
| 2_01009_general_mvo.docx | DOCX document | |
| Sol_140L6221R0047.pdf | ||
| 3__01505__Mobilization_mvo.doc | DOC document | |
| 1_SOW_mvo_KJP.docx | DOCX document | |
| 11_Seminoe_Overview_Map_10k.pdf | ||
| 10_Hanna_Draw_Overview_Map_24k.pdf | ||
| 9_Fence_Conversion_Drawings__Updated.pdf | ||
| 8__Work_Data_Sheet_2__4_wire_mvo.docx | DOCX document | |
| 7__Work_Data_Sheet_1_3_wire_mvo.docx | DOCX document | |
| 6_Material_Specifications_mvo.doc | DOC document | |
| 4_02824_Wire_Fence_and_Gates_mvo.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 02827
FENCE REMOVAL
PART 1: GENERAL
1.1 SUMMARY
A. Section Includes:
1. Removing fences: Woven wire fence with barbed wire (leave existing metal posts for re-use).
B. Requirements: Access roads shall not be constructed along fence lines or to the jobsite unless written approval is granted by the Contracting Officer. Cross-country travel with wheeled or tracked vehicles shall be only to and along fence lines.
PART 2: PRODUCTS
2.1 MATERIALS
A. Requirements: Furnish labor and materials required to remove existing barbed wire/woven wire fence, and gates.
PART 3: EXECUTION
3.1 REMOVAL
A. Removal of Fence: Remove existing fence as directed by the contractors authorized representative on the project. All materials removed from the fence shall become property of the contractor, except for any steel posts removed. Steel posts removed can be piled on site for use/disposal by the Government. Disposal of debris shall be according to Section 01009 – General Information and Requirements.
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: Fence removal will be measured and paid for by the linear foot removed as measured along the ground surface next to the fence prior to removal, including distance across gate openings, end, stress, and corner panels and drainage crossings.
4.2 BASIS OF PAYMENT
A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Pay Item Pay Unit
02827(1) Fence Removal Linear Foot
END OF SECTION 02827
Hanna Draw Fence Conversion 2021 FENCE REMOVAL
02827 -