Construction_Statement_of_Work_Incl_Options.pdf
PDF 14 KB Posted
- Attached to
- Vault 3 & 4 Electrical Upgrades Project Federal contract opportunity
- Solicitation number
- 47PM0218N0001
About this file
SOW with Options
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_No_1_SF30_RFI_Responses.pdf | ||
| Site_Visit_Sign_in_Sheet.pdf | ||
| Amendment_No_1_SF30_-_VAULT_3_&_4.pdf | ||
| Attachment_3_CD_Pickup_Instructions_VAULT_3_&_4.pdf | ||
| Registration_Form_for_Site_Visit.docx | DOCX document | |
| SF25-16_Performance_Bond.pdf | ||
| SF_1442_Form_-_47PM0218N0001.pdf | ||
| Vault_3_&_4__Agreement.pdf | ||
| Firms_Past_Performance_Form.pdf | ||
| Solicitation.pdf | ||
| Vault_3_&_4__Offeror_Representations_and_Certifications.pdf | ||
| SOW_-_VAULT_3_&_4.pdf | ||
| Davis_Bacon_Wage_Determination.pdf | ||
| SF25A-16_Payment_Bond.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 4, 2017
Vault 3 & 4 Upgrade Statement of Work
Refer to the Vault 3&4 Electrical Upgrade 100% Construction Documents Dated April 4, 2017.
This a construction project that consists of replacing the Vaults 3 & 4 electrical distribution equipment, located in the Harry S. Truman Building. Perspective bidders shall provide quotes for the base project and three options.
The project will entail numerous outages, which all need to be coordinated in advance with the appropriate State Department point of contact. The Contractor shall adhere to the phasing plan described in the construction documents.
The work should be in accordance with the plans and specifications provided by WRL and the security plans and specifications provided by Diplomatic Security.
Base Project:
• Replace all of the electrical distribution equipment from secondary side of the network transformers. This includes all of the network protectors, switch gear, bus duct, distribution panels with associated conductors, low voltage transformers, lighting, fire alarm and fire protection. The base bid shall include everything except: both options discussed in Paragraph 3.1 "SCHEDULE OF OPTIONS" in specification section 012300
- 2.
• Security plans and specifications provided by Diplomatic Security.
Option 1:
Replace network transformers and feeders already shown in the plans and specifications.
• Replace the network transformers in Vaults 3 & 4.
• Replace medium voltage feeders between Vaults 3 & 4 (Refer to Sheet EP 0B1)
• Replace medium voltage feeders between Vault 3 and Manhole 3 and 3A (Refer to Sheet
EP 0B1)
Option 2:
Medium voltage feeder replacement between the Main Vault and Vault 5. This is referred to as Option No 1 in Paragraph 3.1 in Specification Section 012300-2.