Nakamura Elevator Project Development Study - Redacted

View the file

Other files

File Type Posted
A002_Amendment_Documents.zip ZIP file
0_-_SF30_EQ10PCB2180024_A002.pdf PDF
0_-_SF30_EQ10PCB2180024_A001.pdf PDF
EQ10PCB2180024_A001_Documents.zip ZIP file
EQ10PCB-2-18-0024_Solicitation_Package.zip ZIP file
NCH_Elev_IndustryOutreachSourcesSought.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT DEVELOPMENT & FEASIBILITY STUDY

ELEVATOR UPGRADE & MODERNIZATION

WILLIAM KENZO NAKAMURA UNITED STATES COURTHOUSE

(WA0035ZZ)

1010 5TH AVENUE, SEATTLE, WA

SUBMITTAL 4:

FINAL PDS REPORT

January 26, 2018

Prepared for:

Prepared by:

GSA NCH ELEVATOR PDS FINAL PDS REPORT (Submittal 4) 01262018

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT

COPYING, DISSEMINATION, OR DISTRIBUTION OF THIS DOCUMENT TO

UNAUTHORIZED RECIPIENTS IS PROHIBITED

Do not remove this notice Properly destroy or return documents when no longer needed

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT FOR OFFICIAL USE ONLY

Do not remove this notice Properly destroy or return documents when no longer needed Page 2 of 4

TABLE OF CONTENTS

PROJECT TEAM ………………………………………………………………………………… 3

EXECUTIVE SUMMARY ………………………………………………………………………... 4

MODERNIZATION SURVEY REPORT (16 pgs) ………………………………….………

MODERNIZATION SURVEY MANUAL (59 pgs) ……………………………….……….……………... 21

MODERNIZATION FINAL COST ESTIMATE (18 pgs) ……………………………….……. 80

Do not remove this notice Properly destroy or return documents when no longer needed Page 3 of 4

GSA PROJECT TEAM

Contracting Officer (CO) Project Manager (COR) Contract Specialist (CS) Dawn M. Ashton Erik Steimle Kimberly M. Johnston dawn.ashton@gsa.gov erik.steimle@gsa.gov kimberlym.johnson@gsa.gov

(253) 306-1711 (206) 220-4917 (253) 931-7337

AECOM/URS and LERCH BATES PROJECT TEAM Project Manager Paul C Weber paul.c.weber@aecom.com

(503) 539-9442

Elevator Technical Lead Elevator Field Lead Cory Hunter Carl Cary cory.hunter@lerchbates.com carl.cary@lerchbates.com

(503) 440-7229 (425) 205-2205

Do not remove this notice Properly destroy or return documents when no longer needed Page 4 of 4

EXECUTIVE SUMMARY

AECOM Technical Services (AECOM/URS) and it’s Consultant LERCH BATES herein presents Submittal 4 FINAL PDS which provides the fully developed preferred option as approved by GSA to completely modernize the four passenger elevator's equipment and controls. This has been vetted to address feasibility details and logic, fully satisfy the GSA SOW and to integrate all GSA SME re-view comments. The Project Survey Report and Project Manual / Specifications are provided for GSA to include as key documents in the DB RFP procurement package. A final coordination of the following sections with the GSA procurement package is recommended to mitigate discrepancies:

Section 00100 Instructions to Contractor (Examination, Existing Maintenance Contract)

Section 00200 Contractor Qualifications (General Requirements, Project Staffing)

Section 00800 Conditions (General and Supplemental Conditions, Special Conditions – Compliance, Labor Laws, Delays and L.D., Payment)

Section 01010 Work - 01040 Procedures (SOW, Codes, Duties, Responsibilities, Requirements)

Section 01300 Submittals (Requirements, Milestones/Phases, Receipt and Review Durations)

Section 01800 Maintenance (Interim and Warranty - start interim maintenance at Design NTP (66 weeks) or at Construction NTP (52 weeks) and warranty maintenance period initiates only after all four elevators are final inspected by GSA AHJ and accepted, automatic extension to 12 mo.

warranty period due to repeat issues)

Section 01900 Related Work (Fire Alarm, HVAC, and Elec./ Lighting Upgrades, Standby Power)

Section 142200 ALL (Coordination with RFP, SOW, FAR, Approved Contractors, Components, Installers, Warranty, Concur Sealed Design Submittals required and Early Order (Long Lead Items) developed to 100% at 75% submittal is acceptable)

Addition inclusion to the Submittal 4 FINAL PDS are a preliminary CPM and Uniformat Level 3 Cost Estimate to serve as guidance for GSA’s establishing the anticipated project duration and cost.

This Submission 4 completes our SOW which was comprised of four Submittals, as follows:

· Submittal 1: Needs assessment, executive summary

· Submittal 2: Construction and feasibility concept options which provide constructability path for use by DB project team, preliminary cost estimates, preliminary construction schedule, hazardous materials report(s)

· Submittal 3: Draft Final report including preferred option (as described above) construction feasibility details and logic, performance specifications, updated cost estimates and preliminary CPM schedule

· Submittal 4: Final conformed report

2050 BE AVE RCRE EK ROA D • SU IT E 101-317 • OREGON C IT Y, OREGON 97045

T 503-440-7229 • www.lerchbates.com

NAKAMURA COURTHOUSE

SEATTLE, WASHINGTON

ELEVATOR MODERNIZATION SURVEY – SUBMITTAL 4

JANUARY 26, 2018

Prepared For:

Paul Weber Construction Manager

AECOM

AECOM /URS

Project Number 60554876

Prepared By:

Cory Hunter, CEI Consultant

Carl Cary Consultant

LERCH BATES Project Number 0100014395

All documents furnished by Lerch Bates Inc. (Lerch Bates) are instruments of service and shall remain the sole property of Lerch Bates. Lerch Bates shall retain all common law, statutory and other reserved rights, including the copyright thereto. They are to be used only for this project and are not to be modified, distributed or used for any other project, in whole or in part, except with the written authorization of Lerch Bates. Lerch Bates accepts no liability for any unauthorized use or modification of these documents.

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT

COPYING, DISSEMINATION, OR DISTRIBUTION OF THIS DOCUMENT

TO UNAUTHORIZED RECIPIENTS IS PROHIBITED

Do not remove this notice Properly destroy or return documents when no longer needed

ELEVATOR MODERNIZATION SUBMITTAL 4

Nakamura Courthouse, Seattle, Washington Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

TABLE OF CONTENTS

SECTION 1 EXECUTIVE SUMMARY AND RECOMMENDATIONS

A. GENERAL

B. MODERNIZATION OBJECTIVES

C. CONCLUSION

D. RECOMMENDATIONS

SECTION 2 EXISTING EQUIPMENT REVIEW

A. GENERAL

B. DISCUSSION

C. CONCEPTS AND FEASIBILITY

D. OPINION OF PROBABLE COSTS

SECTION 3 CODE RELATED ITEMS

A. GENERAL

B. CONCLUSIONS

SECTION 4 MODERNIZATION PLANS

A. GENERAL

B. MODERNIZATION SCOPE

C. RECOMMENDATIONS

APPENDIX A SUPPORTING PHOTOGRAPHS

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

SECTION 1

EXECUTIVE SUMMARY AND RECOMMENDATIONS

A. GENERAL

Lerch Bates Inc. was commissioned to review the elevator equipment for the Nakamura Courthouse in Seattle, Washington in consideration of a potential modernization. The existing elevator equipment condition was evaluated for Elevators 1-4, to determine proper component replacement as well as reuse.

Elevator 5 was recently installed in the parking garage and not included in the required scope of work.

Existing building conditions in the elevator machine room, hoistway, and pit were also reviewed for Code compliance, which becomes incumbent with a modernization project.

B. MODERNIZATION OBJECTIVES

In our judgment, a comprehensive elevator modernization at Nakamura Courthouse should consider the following objectives:

1. Replace aged components to ensure 20+ years of service without allocating and additional funds for upgrade or modernization work.

2. Recondition retained equipment to ensure reliable operation.

3. Improve overall system reliability and performance by providing efficient microprocessor logic for elevator dispatch.

4. Improved stopping accuracy and ride quality.

5. Improved door operation.

6. Compliance with current Fire Recall Requirements.

7. Upgrade existing building conditions to comply with current national and City of Seattle elevator safety code and building code requirements.

8. Improved aesthetics for building tenants.

C. CONCLUSION

In our judgement, existing elevator equipment for cars 1-4 is in average condition for this vintage of equipment. The four elevators were engineered and installed in 1940 and partially modernized by ThyssenKrupp in 2009. The modernization in 2009 replaced the motor controls operational controls of the elevators, car door equipment, fixtures and hoistway wiring. The DC gearless hoist machines have not been replaced since their installation and are now approximately 77 years old. Changes in equipment design and technology have made the existing dispatching system and motor control obsolete. The DC gearless hoist machines are no longer supported, if the equipment fails the contractor will be required to have custom motor work done and the elevator will be out of service for a significant amount of time.

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

Existing controls are original thyssenkrupp Elevator engineered in 2009. Parts are not available for the Tac50 product. Thyssenkrupp no longer supports the original 16-bit Tac50 controller and a 32-bit replacement upgrade is required to these controllers to allow them to be supported.

Fujitec America is the existing elevator maintenance contractor. Fujitec has provided information to the GSA that the floor leveling primarily on cars 3 and 4 is erratic and can often leave a trip hazard to the public. We were not able to witness the leveling issues while onsite. In review of the callback records over 2017, Fujitec has been responding to callbacks and entrapments with the elevators not responding.

Several callbacks are related to security card readers, a majority of the calls are due to a non-responsive system.

The harmonic door operation equipment was upgraded in 2009 during the last modernization. This is a high quality, heavy duty door operating device. Advances in door technology have resulted in improved passenger safety with new linear closed loop operation.

Existing signal fixtures are a combination of modernized and obsolete equipment. Planning for replacement should also include new LED hall and car fixtures as well as replacement of the multi-light hall position indicators at the Lobby level.

The elevator cab interiors are in good condition. The planning process will include review of available options for improving the elevator aesthetics to the building tenants, and is the choice of the owner.

Appointments can include new interior side and rear wall panels as well as new stainless-steel finishes at the front of the cab.

Finally, a modernization of the elevator equipment will require upgrades to existing building for Code compliance within limitations of existing structure to ensure city acceptability of the new installations. A summary of Code deviations noted during our site survey is included for review and discussion in Section 3.

D. RECOMMENDATIONS

We recommend planning proceed for the replacement of the existing TAC50 control systems with new microprocessor based controls, new AC gearless hoist machines, new AC variable voltage variable frequency (ACV³F) drives and new LED car and hall fixtures. Various existing mechanical and structural components can be reconditioned and reused.

We recommend that the specifications include an alternate for Owner's consideration to upgrade the existing cab interiors and ceilings with new front stainless steel, and side and rear wall finishes. This recommendation is based on the concept that the building tenants will not be visually aware of the Owner's investment in the property unless the major aesthetics are upgraded.

We recommend that the building work be included in the elevator contracts for a turnkey project.

The modernization project duration will be approximately 64 months, depending on project scope and manufacturing. Contractor selection should be based upon a fair tendering process with final award based upon initial cost, five-year cost of ownership, mutually acceptable contract terms and conditions, and contractor's track record in the local Seattle market.

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

SECTION 2

EXISTING EQUIPMENT REVIEW

A. GENERAL

During our survey, existing passenger elevator components were checked to determine overall condition and suitability for continued use. In addition, machine room, hoistway, and pit spaces were reviewed for compliance with current codes. This section reviews the results of our equipment survey.

B. DISCUSSION

The four DC gearless traction passenger elevator systems(s) at the Nakamura Courthouse were manufactured and installed by Otis in 1940. The most recent modernization was in 2009 by thyssenkrupp Elevator which replaced many of the original components. All recommendations and design considerations discussed are based on providing the building and owner with a minimum of 20 years of reliable service.

Passenger elevators 1, 2 and 3; have a rated capacity of 3,000 lbs. and travel at a speed of 600f.p.m.

Elevators 1-3 serve 10 landings (Floors 1-10). Judge’s elevator 4 serves 11 landings (Floors B,1-10).

Existing car interior does comply with the Americans with Disabilities Act. Entrances are 3’-10” wide x 7’- 0” high, power operated, two-speed, side opening doors.

C. CONCEPTS AND FEASIBILITY

The following provides details on the existing component condition and recommendations for replacement or reuse:

1. Controls

The existing thyssenkrupp passenger elevator control system is representative of a then state-of-the-art, microprocessor based control; however, it is now obsolete. These controllers utilize an early Tac50 16-bit processor, which have been replaced by the 32-bit system. Thyssenkrupp no longer supports these controllers, and an expensive software upgrade is required to retrofit the system simply to maintain the existing equipment.

Significant changes in design have made substantial improvements in operation and reliability via AC microprocessor based systems. In addition, new drive systems are available from various manufacturers who can potentially reduce energy consumption.

2. Hoist Machine and Deflector Sheave

The existing Otis gearless hoist machines are approaching 80 years of service, and are not suitable for re-use. This design was robust at the time it was designed, however; the machines are operating significantly beyond their original design life. New AC hoist machines should be installed which will improve reliability, reduce energy consumption and provide a minimum of 20 years of reliable operation. New hoist machines will include an integral dual-brake system, which meet the requirements of the code for unintended car motion. The modernization in 2009 did not address unintended car motion and ascending car overspeed protection which is required by code.

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

The existing governor tail sheave provides sufficient tension on the governor rope and can be reused.

3. Car Frame and Safety

The existing car frame is simply structural steel and should be reused. The roller guides are of similar design to today’s installations; replacement will not result in noticeable ride quality improvements. Existing safety mechanism is a flexible guide clamp type safety and is suitable for reuse.

4. Platform

The existing platform is suitable for reuse.

5. Counterweight

The existing counterweight roller guides are suitable for reuse.

6. Hoist Ropes

The existing traction steel hoist ropes will be replaced with the new AC hoist machines.

New traction steel cables or coated belts will be provided.

7. Car and Hoistway Door Equipment

The existing hoistway door panels and entrance frames are in good condition and can be reused. Consideration may be given to changing out the existing car doors if the cab interiors are upgraded.

The existing passenger elevator hoistway door sills are in good condition and will be cleaned and securely tightened and retained. Consideration may be given to changing out the existing car sills if the cab interiors are upgraded.

8. Cab Enclosure

The elevator cab interiors are wood side walls and brushed stainless steel fronts. The fronts do show some wear. Options under the modernization include:

a. Reuse as is.

b. Refinishing of the stainless-steel fronts.

c. Replacement of the side wall panels.

d. Replacement of the entire cab with new interior finishes.

We recommend further consideration of such options by ownership with bid documents including an alternate price for upgrade.

9. Car and Hall Station Fixtures

The car control stations and the hall pushbutton stations should be replaced with new long-lasting LED registration buttons. The current buttons comply with the requirements of the Americans with Disabilities Act (ADA) for access by physically challenged. The hall

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018 buttons were mounted at 42" above finish floor; this will enable reuse of the existing fixture boxes and eliminate any hall cutting and patching.

10. Guide Rail Supports

Existing passenger elevator car and counterweight guide rail fishplates were reinforced to meet seismic requirements during the 2009 project, and are in generally good condition and are suitable for reuse under any modernization program where speed and capacity are not changed. They will be cleaned with all fastenings tightened.

11. Traveling Cables and Hoistway Wiring

Existing traveling cables and hoistway wiring will be replaced as a result of the new controls and fixtures. New traveling cables should be provided with minimum 10% spare conductors and should include a minimum of four (4) sets of twisted shielded pairs of communication wires to facilitate installation of new car controls and to provide sufficient spares to accommodate future devices if desired.

12. Buffers and Pit Equipment

Existing passenger elevator car and counterweight buffers are in fair condition and will be reconditioned for reuse.

13. Fire Command Panel

The existing Fire Command Panel located in the Fire Command Center requires replacement. The panel does not have floor indicators that match the existing floor nomenclature. We recommend replacement with a new panel with LED illumination.

14. Security Control Panel

A new security panel will be provided in the security office. The panel can be configured to have the required security elevator control of the building. Specifications developed will provide adequate interfacing between new open market security systems and elevator controls. The type of security system, function, location of readers or keypads and methods of access control shall be designed by the owner.

D. OPINION OF PROBABLE COSTS

Our opinion of probable cost, including related building work, .

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

SECTION 3

CODE RELATED ITEMS

A. GENERAL

By ASME A17.1 Elevator Code the initiation of an elevator modernization requires upgrade to related building components. Such items can include the electrical supply, structure fire ratings, and life safety components. Listed below are building deviations from current codes; some items can be “grandfathered” by local code authority (AHJ), other items require installation of an additional feature or device.

ASME RULE

NO.

REQUIREMENT COMMENT

U.B.C. 101.A MACHINE ROOM DOOR TO BE FIRE RATED

2.7.9.2 VENTILATION OF MACHINE ROOM SPACE RECOMMEND HVAC AND

THERMOSTAT TO BE INSTALLED

2.8.1 NO FOREIGN EQUIPMENT IN MACHINE ROOM PASS THROUGH CONDUIT

THROUGH MACHINE ROOM.

REQUIRES CONSIDERATION OF

OWNER

2.9 ASCENDING CAR OVERSPEED AND UNINTENDED

CAR MOVEMENT PROTECTION

INSTALL NEW AC MACHINES

WITH DUAL BRAKE

1206.1H INSTALL TESTED FIRE EXTINGUISHER CLASS ABC

B. CONCLUSIONS

The building will require minimal modifications for code compliance. It is our recommendation that the specifications narrate that the required changes and the scope of work be included in the elevator modernization contract. We suggest the documents include approved sub-contractors for use by the elevator contractor. This contracting method requires the elevator contractor to coordinate any necessary sub-contractors and minimizes potential unknown cost overruns to the owner. The contractor mark-up on such work is typically worth the coordination efforts.

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

SECTION 4

MODERNIZATION PLANS

A. GENERAL

The modernization project should be based on equipment changes to achieve the objectives set forth in Section 1 of this report. The scope of work should balance today’s cost constraints with improvements that represent a comprehensive, long-term (minimum 20 years) solution. The current market climate and competitive bidding process may enable ownership to possibly realize more than could have been previously realized.

B. MODERNIZATION SCOPE

Planning will include development of a specification Section 14220 which will outline a detailed scope of work following the summary below.

ELEVATORS 1, 2 AND 3 4

DESCRIPTION

MANUFACTURER OTIS/TKE OTIS/TKE

DOOR TYPE AND SIZE 3’-10” WIDE X 7’-0” HIGH 3’-10” WIDE X 7’-0” HIGH

FLOORS

SERVED/TRAVEL FLOORS 1-10 FLOORS B, 1-10

MAJOR COMPONENTS

MACHINE TYPE DC GEARLESS DC GEARLESS

POWER CONVERSION SCR SCR

OPERATIONAL

CONTROL MICROPROCESSOR MICROPROCESSOR

DOOR OPERATION TWO SPEED, SIDE OPENING TWO SPEED, SIDE OPENING

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

R = RETAIN

N = NEW

A = ALTER

NA = NOT

APPLICABLE

OPINION OF PROBABLE COST LABOR

AND MATERIAL.

ITEMS RETAINED ARE

REBUILT/REFURBISHED, CLEANED

AND PAINTED

SPEED: R

CAPACITY: R

CONTROLS: N

ENCODER: N INCLUDED WITH CONTROLLER

HOIST MACHINE: N

HOIST ROPES/MEANS: N

MOTOR CONTROL: N INCLUDED WITH CONTROLLER

GOVERNOR: R

GOVERNOR ROPE: R

HOISTWAY EQUIPMENT

(BUFFERS AND PIT EQUIPMENT):

R

CAR SLING: R

ROLLER GUIDES: R

PLATFORM: R

SAFETY PLANK: R

COUNTERWEIGHT: R

CAR DOOR OPERATOR: N

CAR DOOR EQUIPMENT: N

RAILS/SUPPORTS: R

HOISTWAY DOOR EQUIPMENT: R

HOISTWAY ENTRANCE FRAMES: R

HOISTWAY DOOR PANELS: R

HOISTWAY DOOR SILLS: R

HOISTWAY WIRING TRAVELING CABLES: N

SIGNALS: N

CAR OPERATING PANELS: N

HALL PUSHBUTTONS: N

HALL LANTERNS: A

CAR POSITION INDICATORS: N

CAB INTERIOR FINISHES: BASE BID

RETAIN,

ALTERNATE BID

FOR

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

R = RETAIN

N = NEW

A = ALTER

NA = NOT

APPLICABLE

OPINION OF PROBABLE COST LABOR

AND MATERIAL.

ITEMS RETAINED ARE

REBUILT/REFURBISHED, CLEANED

AND PAINTED

REPLACEMENT

ELEVATOR REFURBISHMENT COST:

MACHINE ROOM: R & A

MACHINE ROOM LIGHTING: R

MACHINE ROOM OUTLETS: R

MACHINE ROOM ACCESS: R

MACHINE DISCONNECT SWITCH: R

COOLING/HEATING MACHINE ROOM: N

PIT LIGHTING: R

PIT OUTLETS: R

HOISTWAY VENTING: R

SECURITY SYSTEM UPGRADES: N TBD

TOTAL

As most new microprocessor based car and motor controls are “proprietary” in nature, the specifications should include the requirements to provide the necessary diagnostic service tools and technical manuals to provide maximum flexibility in contracting for future maintenance. As an alternative, non-proprietary controls by a third-party manufacturer could be specified, however, they will result in an increased initial installation cost of approximately 10%.

In addition to Section 14220, Lerch Bates will provide general Terms and Conditions specification sections. A partial list of those documents include: Instructions to Bidders, Quotation Form, Summary of Work, Alternates, Project Procedures, Submittals, Related Work, and Interim and Long-Term Elevator Maintenance. The bidding community is familiar with the Lerch Bates documents and the tendering process.

C. RECOMMENDATIONS

We recommend implementation of modernization scope outlined above to provide comprehensive modernization of the existing elevators. We recommend that Lerch Bates prepare our standard contracting package for ownership review. Final documents should include any scope and contractual modifications required by ownership.

In order to secure the most competitive prices, bid documents will include a Five-Year Maintenance specification for pricing by all bidders.

We recommend inviting the six (6) major elevator companies, KONE, Fujitec, Mitsubishi, Otis Elevator, Schindler Elevator, and ThyssenKrupp, as well as a limited number of local independent companies to

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018 tender for the project. Consideration of award should be based upon the initial modernization investment as well as the five-year cost of ownership.

Planning should include consideration of long lead times for fabrication of equipment and installation.

Approximate time periods for the project are as follows.

PREPARATION OF BID SPECIFICATION/OWNER REVIEWS 3 WEEKS

CONTRACT/BID REVIEW AND AWARD OF CONTRACT 3-4 WEEKS

SHOP DRAWING APPROVAL 6 WEEKS

EQUIPMENT FABRICATION 8 WEEKS

EQUIPMENT DELIVERY 2 WEEKS

INSTALLATION 10 WEEKS/ELEVATOR

FINAL ADJUSTING AND TESTING 2 WEEKS

TOTAL ELAPSED TIME FOR PROJECT 64-65 WEEKS

Durations can vary by manufacturer. The bid documents will include solicitation of each contractor’s time frames. Installation may be completed one car at a time or the schedule may be compressed to remove two cars at a time for modernization depending on the owners’ requirements.

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

APPENDIX A

SUPPORTING PHOTOGRAPHS

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

1. Cartop handrails are installed and will be retained. 2. GAL MOVFR were installed in 2009 and can be retained or replaced with a new linear door operator.

3. Seismic fishplates have been installed and will be retained.

4. Car guides are high quality and can be retained. The hoistway will require screening by the elevator contractor since one elevator will be modernized at a time and the other elevator will be left running.

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

5. Machine room is naturally ventilated, HVAC and a thermostat should be installed to maintain 65-95 degrees Fahrenheit. Windows that can be opened are not allowed by current code. They will be modified as part of the modernization.

6. Disconnects were installed in 2009 and meet current code requirements.

7. Shunt trip operation for the disconnects is installed and will be retained.

8. Independent car light circuits are installed. New 15-amp circuit breakers will be installed as part of the modernization.

Lerch Bates Project No. 0100014395 © 2018 Lerch Bates Inc.

January 25, 2018

9. 16-bit Tac50 controllers are no longer support. 32-bit upgrade is required.

10. Existing DC gearless machines are approximately 77 years old, machines will be replaced with new AC gearless machines.

11. Replace car operating station signal fixtures with LED type.

12. Replace hall signal fixtures with LED type.

LERCH BATES INC. TRACTION ELEVATOR MODERNIZATION

Elevator Consulting Group

TABLE OF CONTENTS

INFORMATION AND INSTRUCTIONS

00100 INSTRUCTIONS TO CONTRACTOR .....................................................................00100-1

FORMS

00200 CONTRACTOR QUALIFICATIONS ........................................................................00200-1

CONDITIONS TO THE CONTRACT

00800 SUPPLEMENTAL CONDITIONS ............................................................................00800-1

SPECIFICATIONS

01010 SUMMARY OF WORK ............................................................................................01010-1 01030 ALTERNATES .........................................................................................................01030-1 01040 PROJECT PROCEDURES......................................................................................01040-1 01300 SUBMITTALS ..........................................................................................................01300-1 01600 MATERIAL AND HANDLING...................................................................................01600-1 01700 FINAL CONTRACT COMPLIANCE REVIEW..........................................................01700-1 01800 MAINTENANCE.......................................................................................................01800-1 01900 RELATED WORK ....................................................................................................01900-1 142200 MODERNIZATION...................................................................................................14220-1

LERCH BATES INC. TRACTION MODERNIZATION

Elevator Consulting Group INSTRUCTIONS TO CONTRACTOR

SECTION 00100

TABLE OF CONTENTS

PART 1 - GENERAL

1.1 EXAMINATION

1.2 EXISTING MAINTENANCE CONTRACT

Nakamura Courthouse, Seattle, Washington LB Project No.0100014395 ©2018 Lerch Bates Inc.

January 25, 2018 00100 - 1

SECTION 00100

INSTRUCTIONS TO CONTRACTOR

PART 1 - GENERAL

1.1 EXAMINATION

A. In order to discover and resolve conflicts or lack of definition which might create problems, Contractor must review Contract Documents, existing site conditions, and existing equipment specified to be retained for compatibility with its product prior to submitting quotation. Site review shall include, but not be limited to adequacy of access, retained equipment, elevator hoistways, pits, machine rooms, overhead clearances, electrical power characteristics, structural supports, etc. Investigation and structural calculations required to determine compliance of existing elevator components including machine support beams, with ASME A17.1, Rule 8.7.2.15.2, are responsibility of Contractor. Compliance with all provisions of Contract Documents is assumed and required in absence of written exception. If written exception is acceptable to Contractor and Consultant, an Addendum to the specifications will be issued and authorized. Purchaser will not pay for change to building structure, structural supports, mechanical, electrical or other systems required to accommodate Contractor’s equipment if not identified before Contract award and authorized as stipulated above.

B. Submission of quotation is considered evidence that Contractor has visited and is conversant with the site facilities, site conditions, requirements of the Contract Documents, pertinent state and local codes, state of labor and material markets, and has made due allowance in his quotation for all contingencies. Should Contractor’s investigation of site conditions or local codes or rules reveal requirements contrary to Contract Documents, or if Contractor finds any discrepancies or omissions from Contract Documents, or if Contractor is in doubt as to their meaning, they shall contact the Consultant for clarification at least five working days prior to quotation due date.

C. No oral explanation will be made, and no oral instructions will be given before quotation due date. Contractor shall act promptly and allow sufficient time for a reply to reach him before submission of his quotation. Any required interpretation or supplemental instructions will be issued in the form of an addendum to the specifications and forwarded to all pre-qualified Contractors.

D. Provide everything necessary for and incidental to the satisfactory completion of work required by Contract Documents. All required preparations and hoisting and movement of new equipment, reused equipment, or removal of existing equipment shall be the responsibility of Contractor.

E. Any conflicts or discrepancies between the Lerch Bates specifications and the RFP or SOW published by the GSA, the GSA documents shall govern.

1.2 EXISTING MAINTENANCE CONTRACT

A. Purchaser shall affect cancellation of existing Maintenance Contract.

B. If Contractor currently providing equipment maintenance under contract with Purchaser is included on the list of invited Contractors for this Contract, Contractor acknowledges and agrees that said contract shall be immediately null and void upon award of this Contract to Contractor or alternate invited Contractor. Further, if present Maintenance Contractor is not the successful firm in regard to this Contract, Maintenance Contractor agrees to deliver existing as modified

Nakamura Courthouse, Seattle, Washington LB Project No.0100014395 ©2018 Lerch Bates Inc.

January 25, 2018 00100 - 2 control wiring diagrams to Purchaser and immediately remove its equipment and materials from the premises with the Purchaser or Purchasers’ representative present. Purchaser shall withhold final maintenance payment due until Maintenance Contractor is in compliance with this requirement.

END OF SECTION

Elevator Consulting Group CONTRACTOR QUALIFICATION FORM

SECTION 00200

TABLE OF CONTENTS

PART 1 - GENERAL

1.1 GENERAL REQUIREMENTS

1.2 BONDING

1.3 PROJECT STAFFING

LB Project No.0100014395 ©2018 Lerch Bates Inc.

January 25, 2018 00200 - 1

SECTION 00200

CONTRACTOR QUALIFICATION FORM

PART 1 - GENERAL

1.1 GENERAL REQUIREMENTS

A. Contractors invited to submit a quotation for modernization of four traction elevator(s) at the Nakamura Courthouse, Seattle, Washington, shall complete this Qualification Form with tender documents.

B. Minimum Qualifications

1. Minimum 6 years as licensed elevator contractor in local market

2. $8,000,000 minimum annual revenue for last 6 years

3. Six (6) maintenance routes

4. Four (4) dedicated modernization crews plus dedicated Mod Superintendent

5. One (1) Local Business Manager and one (1) Field Superintendent

1.2 BONDING

A. Provide a list with a minimum of 10 similar projects completed by your firm in the last 6 years in close proximity to building location. List current projects in progress, including start dates and estimated completion dates. Include the following information on each representative project:

1. Building name

2. Building address

3. Name of principal contact

4. Phone number of principal contact

5. Date completed

6. Scheduled and actual final project completion dates

7. Cost of project

8. Provide current number of new installation and modernization projects in progress and estimated completion dates

B. Provide general information as follows:

1. Number of years your firm has existed:

2. Number of years your firm has operated in locale of this building:

3. Number of field employees currently employed by your firm in general locale of this building:

a. Construction/Modernization Mechanics:

b. Construction/Modernization Supervisors:

c. Maintenance Mechanics:

d. Maintenance Supervisors:

4. Number of Maintenance Routes:

5. Average number of elevator/escalator units maintained by individual Maintenance

Mechanic:

6. Average number of hours per month to be expended performing routine site preventive maintenance at the project site upon completion of modernization work:

7. Name of the Union of which your Maintenance Mechanics are members:

8. Name of manufacturer, including system/component designation for the following:

a. Group supervisory and motor control:

b. Door operator:

c. Signal fixtures:

d. Car enclosure, new/refurbish:

e. Hoist machine:

©2018 Lerch Bates Inc.

January 25, 2018 00200 - 2

1.3 PROJECT STAFFING

A. Attach a commentary to this form summarizing how your firm would propose to staff and complete this project. Also attach a resume of proposed project managers, superintendents, and site mechanic in charge.

Elevator Consulting Group SUPPLEMENTAL CONDITIONS

SECTION 00800

TABLE OF CONTENTS

PART 1 - GENERAL

1.1 DEFINITION OF TERMS

1.2 CONSULTANT’S STATUS

1.3 CONTRACT

1.4 MEASUREMENTS AND DRAWINGS

1.5 CODES AND ORDINANCES

1.6 CONTRACTOR’S INSURANCE

1.7 PURCHASER INSURANCE

1.8 TAXES, OLD AGE PENSIONS AND UNEMPLOYMENT INSURANCE

1.9 LABOR LAWS

1.10 PATENTS

1.11 ASSIGNMENTS

1.12 ADVERTISING

1.13 PROTECTION OF WORK AND PROPERTY

1.14 ACCIDENT REPORTS

1.15 STORAGE OF MATERIALS

1.16 REMOVAL OF EQUIPMENT AND RUBBISH

1.17 MATERIALS AND WORKMANSHIP

1.18 SUPERVISION

1.19 ROUTINE BUSINESS

1.20 CHANGES AND EXTRA WORK

1.21 PAYMENTS

1.22 PAYMENT WITHHELD

1.23 LIENS AND AFFIDAVITS

1.24 CLAIMS FOR EXTRA COST

1.25 DELAYS AND EXTENSION OF TIME

1.26 PERMITS

PART 2 - SPECIAL CONDITIONS

2.1 PROGRESS OF WORK

Nakamura Courthouse, Seattle, Washington LB Project No.0100014395 ©2018 Lerch Bates Inc

January 25, 2018 00800 - 1

SECTION 00800

SUPPLEMENTAL CONDITIONS

PART 1 - GENERAL

1.1 DEFINITION OF TERMS

A. Term ELEVATOR CONSULTANT or CONSULTANT as used herein refers to the owner’s representative/CMa CONSULTANT.

B. PURCHASER as used herein refers to GSA.

C. The term CONTRACT or CONTRACT DOCUMENTS as used herein consists of the Agreement, Conditions of Contract, Specifications, Addenda, Drawings if included, and Alternates if accepted.

D. CONTRACTOR or ELEVATOR CONTRACTOR as used herein refers to any persons, partners, firm, or corporation having a contract with Purchaser to furnish labor and materials for the execution of work required.

E. CONTRACT AWARD as used herein refers to Purchaser’s verbal or written award for work required.

F. SUBCONTRACTOR as used herein refers to any persons, partners, firm, or corporation having a contract with Contractor to furnish labor and materials for the execution of work required.

G. As used in these Contract Documents “provide” shall be understood to mean “furnish and install.”

H. As used in these Contract Documents “retain or reuse existing” shall be understood to mean restore existing components or parts to like-new condition and meet current code requirements.

Retain or reusing specified equipment in like-new condition is the minimum requirement.

Replacement with new component equal to or exceeding components specified as retain or reuse is acceptable, if approved in writing by GSA.

I. Words in the singular shall include the plural whenever applicable or context so indicates.

J. All technical terms in these Contract Documents have their definition given in latest edition of American National Standard Safety Code for Elevators, Dumbwaiters, Escalators, and Moving Walks ASME A17.1. and A17.2.

1.2 CONSULTANT’S STATUS

A. Consultant shall act as Purchaser’s and/or Building Management’s representative on all matters pertaining to required work. Consultant shall interpret Contract Documents, analyze Contractor’s quotations, review Contractor suggested alternates, review all submittals of Contractor, approve billings, review technical details and construction procedure, perform work progress reviews and review and test completed work for compliance with Contract Documents prior to acceptance of work by Purchaser.

B. Field Review Scheduling: Schedule progress and final work reviews with Consultant. Reply promptly, in writing, to corrective work indicated on Consultant’s progress and/or final review reports, indicating status and schedule for completion. Consultant anticipates scheduled site

Nakamura Courthouse, Seattle, Washington LB Project No.0100014395 ©2018 Lerch Bates Inc

January 25, 2018 00800 - 2 review appointments will be met. Contractor’s price will be reduced to reimburse Consultant at its normal billing rates for appointments not kept or for additional follow up reviews required due to Contractor’s gross non-compliance with previous review requirements.

1.3 CONTRACT

A. Contract includes all engineering, labor, tools and material required to complete the work in every respect. Contractor is cautioned to familiarize itself with existing site conditions and to include all incidental work that might occur or be required during the work. After Contract has been awarded, verbally or in writing, no extra charges will be allowed for any labor or material necessary to complete required work whether exactly described in these specifications herein or not, as long as such work, labor, and material are required to accomplish desired effect and results.

B. Any discrepancies or ambiguities found in Contract Document or drawings shall be reported to the Consultant prior to Contractor’s quotation submittal.

1.4 MEASUREMENTS AND DRAWINGS

A. Drawings or measurements included with Contract Documents are for convenience of Contractor. Complete responsibility for detailed dimensions lies with Contractor. Contractor shall verify all dimensions with the actual on-site conditions. Where work of Contractor is to join another trade, Contractor’s shop drawings shall show actual dimensions and method of joining work of those trades.

1.5 CODES AND ORDINANCES

A. All work covered by these Contract Documents is to be done in full accord with national code, state and local codes, ordinances, and elevator safety orders as are in effect at time of Contract award. All requirements of local Building Department and fire jurisdiction are to be fulfilled by Contractor and its Subcontractors. Also see Section 01040, Article 1.01.

1.6 CONTRACTOR’S INSURANCE

A. Contractor shall take out and maintain during the life of this Contract Worker’s Compensation Insurance with statutory limits set by the State of Washington laws for protection of its employees.

B. Contractor shall carry a comprehensive general liability policy including completed operations blanket contractual broad form property damage, and Purchaser’s and Contractor’s protective liability in a casualty or liability insurance company acceptable to Purchaser. Insurance policy shall fully protect Contractor, its Subcontractors, Purchaser, and Consultant from all loss and liability. Refer to GSA Terms and Conditions provided.

C. Prior to commencing work, Contractor shall secure required insurance, at its sole cost, and submit certificate of confirmation naming indemnified parties as additional insured. Said policies, including an endorsement which states that such insurance will not be cancelled or materially changed unless Purchaser is given thirty (30) days notice, in writing, of the intention of said insurer to cancel or change any such policy. In the event Property is owned by a joint venture or other multi-party entity, all joint venture partners or parties with an equity interest in the ownership shall be named as additional insureds. Contractor’s insurance shall be primary to any applicable loss. With Purchaser’s prior approval, an Owners & Contractors Protective Liability

Nakamura Courthouse, Seattle, Washington LB Project No.0100014395 ©2018 Lerch Bates Inc

January 25, 2018 00800 - 3

(OCPL) Policy may be substituted for commercial general liability coverage. Please refer to the attached appendix that states the project specific insurance requirements.

D. Contractor shall file with Purchaser a certificate of insurance from its insurance company, stating that such insurance is being carried and that Purchaser will be notified at least 10 days prior to any cancellation of said insurance.

1.7 PURCHASER INSURANCE

A. Purchaser’s insurance policy covers work and equipment in place in building and approved and accepted by Consultant and Purchaser. All material and equipment stored on site and not actually installed is not included in Purchaser’s policy and such material and equipment shall be covered under Contractor’s Property Damage Insurance.

1.8 TAXES, OLD AGE PENSIONS AND UNEMPLOYMENT INSURANCE

A. Contractor’s quotations for required work, materials and equipment shall include all local, state, and federal occupational and sales taxes, luxury taxes, excise taxes, federal and state old age pensions, unemployment insurance contributions, and any other similar taxes and contributions in effect at time of award of Contract, verbally or in writing. Contractor shall be liable for aforementioned taxes whether or not specifically included in his quotation or in final Contract Document. In event additional sales or use taxes are imposed after award of Contract, such sales or use taxes are to be paid, in addition to original Contract amount, by Purchaser to Contractor, who in turn is to pay them to proper authorities. Reciprocally, if any of above mentioned taxes or contributions in effect at time of award of Contract should be revoked before consummation of Contract, Contractor shall rebate Purchaser amount of taxes included in original quotation and Contract. Where required by law, amount of the tax is to be specifically stated in Contractor’s quotation; however, failing to do so will not relieve Contractor from responsibility for assumption of these taxes.

1.9 LABOR LAWS

A. Contractor and its Subcontractors performing work under this Contract shall comply with applicable provisions of all federal, state, and local labor laws.

1.10 PATENTS

A. Contractor shall save and hold harmless Purchaser and its officers, agents, servants, employees, and Consultant from liability of any nature or kind on account of any patented or unpatented invention, process, article, or appliance manufactured or used in performance of Contract, including its use by Purchaser including all cost and expenses for defending any suits unless otherwise specifically stipulated in Contract Documents.

B. Licenses which may be required for completion of required work are to be obtained and paid for by the Contractor.

1.11 ASSIGNMENTS

A. Neither party to this Contract shall assign Contract or sublet it as a whole without written consent of other party, nor shall Contractor assign any payment due him or to become due to him hereunder without previous written consent of Purchaser.

Nakamura Courthouse, Seattle, Washington LB Project No.0100014395 ©2018 Lerch Bates Inc

January 25, 2018 00800 - 4

1.12 ADVERTISING

A. Advertising privileges will be retained by Purchaser. It is the duty of Contractor to keep premises free from posters, signs, decorations, etc., unless specifically approved by Purchaser.

1.13 PROTECTION OF WORK AND PROPERTY

A. Contractor shall continuously maintain adequate protection of all its work from damage and shall protect Purchaser property from injury or loss arising out of this Contract. Contractor shall make good any such damages, injury, or loss, except such as may be directly caused by agents, subcontractors, or employees of the Purchaser. Contractor shall provide all barricades required to protect open hoistways or shafts per OSHA regulations. Contractor shall provide and install hoistway screening. Design of barricades in public areas shall be approved by Purchaser prior to fabrication and installation.

B. If Contract includes work which would be disruptive during normal business operations, or would be dangerous to building occupants, said work shall be performed during hours as building management dictates. Examples of such work include, without limitation, saw cutting of concrete, jack hammering, welding, metal cutting, pouring concrete, erecting steel or hoisting equipment over occupied portions of the building, or performing tests requiring all elevators in a group. Painting and/or detectable odors impacting tenants shall be done after hours. Contractor shall perform such work during off-hours and shall include all costs in its quotation. The following times and scheduling requirements are part of the project: Off hours are considered 6:00 p.m. to 6:00 a.m. Monday through Friday and all-day Saturday and Sunday. These services as well as the items listed in this paragraph shall be performed off hours: All pre-testing, final testing and life safety testing.

C. Contractor shall install a suitable protective covering on all finished floors whether marble, wood, carpet or other, in areas where work is being performed. No material handling equipment shall be permitted on or over finished floors unless said floors have been protected in a manner approved by building management.

D. Portable fire extinguishers shall be provided throughout Contractor’s area of work and shall be placed so as to be accessible at all times. Extinguishers shall be multi-purpose dry chemical type, provided on a basis of one 2A-20BC rated unit for each 3,000 square feet of floor area.

Extinguishers will remain property of Contractor.

E. Contractor shall at all times maintain work areas so all portions are accessible to fire department personnel and apparatus. Fire hydrants and fire department connections to building sprinkler systems must be kept free from obstruction at all times.

F. Contractor shall strictly supervise any welding, metal cutting or other operations employing open flame work. All welding and cutting equipment shall be safely arranged and all combustibles in vicinity of any work being performed shall either be removed or protected by a noncombustible cover. Welding or cutting shall be attended by an assistant or fire watchman who is equipped with at least one 2A-20BC rated multi-purpose dry chemical fire extinguisher. Fire watchman will maintain strict surveillance during entire welding or cutting operation and extinguish flying sparks or burning slag. After welding or cutting operation fire watchman shall thoroughly search entire area for remnants of smoldering materials before he is released from his duty. Any welding or other operation employing open flame in any portion of building shall be scheduled with and receive approval of Purchaser. Hot work permits shall be scheduled and approved with Owner.

Nakamura Courthouse, Seattle, Washington LB Project No.0100014395 ©2018 Lerch Bates Inc

January 25, 2018 00800 - 5

G. Contractor shall keep noise level below 80 dBA level during normal building hours. When it is necessary to produce noise above this level, Contractor shall advise building management of such needs and times will be scheduled as directed. The Contractor shall anticipate and schedule excessive noise generating procedures and include allowance for same in its quotation and schedule. Anything above 80 dBA shall be conducted in previously listed off hours.

1.14 ACCIDENT REPORTS

A. In the event of accidents of any kind, Contractor shall furnish Purchaser with copies of all accident reports. Reports shall be sent without delay and at same time that they are forwarded to any other parties.

1.15 STORAGE OF MATERIALS

A. Contractor shall confine storage of materials on job site to limits approved by Purchaser and shall not unnecessarily encumber premises or overload any portion of building with materials to a greater extent than structure design load.

1.16 REMOVAL OF EQUIPMENT AND RUBBISH

A. Contractor shall remove and properly dispose of all rubbish as fast as it accumulates including all existing parts and components not retained, keeping building and premises clean during progress of work and leave premises at completion in a condition acceptable to the Purchaser.

Store parts and components identified by Consultant as useful for maintenance of units not being modernized as directed by Purchaser. All other parts and components not retained shall become property of Contractor. Dumpster shall be located in the loading dock area.

1.17 MATERIALS AND WORKMANSHIP

A. All materials and equipment furnished shall be new and best quality. Installation shall be accurate, workmanlike, and subject to approval of…