This document outlines a statement of work for construction manager as constructor services for a renovation project at the Major General Emmett J. Bean Federal Center in Indianapolis, Indiana. The General Services Administration seeks design and construction services to renovate approximately 200,000 square feet of office space for occupancy by the U.S. Customs and Border Protection and U.S. Marine Corps. Key requirements include attending regular design and construction meetings, conducting constructability and cost reviews, developing a project schedule and sequencing plan, coordinating hazardous materials abatement, and assisting with commissioning and project closeout. The construction manager will also help pursue LEED certification and support an art in architecture installation. The design phase services are priced as a firm-fixed-price contract, and construction phase services will be executed under a guaranteed maximum price option upon 75% design document completion.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Beta SAM Public Notice of Award.pdf | ||
| Solicitation 47PF0020R0026 Amendment 005.pdf | ||
| Solicitation 47PF0020R0026 Amendment 002.pdf | ||
| Solicitation 47PF0020R0026 Amendment 001.pdf | ||
| MGEJB Backfill_CMc SOW_2020 May 28.pdf | ||
| Bean Backfill CMc - RFP Package with Prospectus 06042020.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
GSA Great Lakes Region
Solicitation 47PF0020R0026 Amendment 004 RFI List
1. Are the current drawings for the existing configuration of areas impacted by this project available for review? These documents would enable us to analyze the scope and extent of the interior demolition for this project.
a. Additional drawings are not available at this time.
2. Will the existing modular office furniture/fixtures be removed by the owner or another contract?
a. The tenant will remove the existing modular office furniture from areas of construction. This will not be required by the CMc.
3. Will the new furniture, fixtures, and equipment referenced on the room data sheets and shown on the documents be furnished and installed by the CMs Contractor?
a. Modular systems furniture, office furniture, conference room furniture and loose furniture will be provided by a separate furniture contractor. The CMc will be responsible for built-in items such as pantry cabinets and millwork.
4. Will the CMc Contractor hold the abatement scope/contract?
a. Yes the CMc contractor will be responsible for the hazardous abatement as required.
5. "FAR 52.230-1 Accounting Standards Notices and Certifications Is this contract exempt from the cost accounting standards board as specified in 48CFR 9903.201-1 as a:
(1) Sealed bid
(2) Negotiated contract not in exec of (TINA)
(15) Firm Fixed Price"
a. Exemption is dependent upon the business size of the offeror in the case of this procurement. The listed exemptions do not apply as this is not a sealed bid, is in excess of TINA, and not a traditional firm fixed price contract.
6. If not exempt is form CASD-1 to be used?
a. See page 14 of the RFP regarding submission requirements.
7. Should form CASD-1 be submitted with this proposal?
a. See page 14 of the RFP regarding submission requirements.
8. Should form CASD-1 be submitted to the contracting officer separately from the proposal?
a. See page 14 of the RFP regarding submission requirements.
9. Should form CASD-1 be submitted to the cognizant federal auditor? If so, please provide contact information.
a. See page 14 of the RFP regarding submission requirements.
10. Please confirm the CMa contractor will be responsible for all environmental services (ie haz mat testing, abatement) as outlined in Appendix B. The Total Evaluated Price sheet indicates it is part of that total but no hazardous material report was provided.
a. The CMa will only be responsible for a 3rd Party Environmental Consultant, which will provide oversite, of all abatement activities including air monitoring and/or testing. The CMc shall be responsible for acquiring an abatement contractor who will be performing that actual abatement/hazardous material mitigation work/services.
11. Appendix B 3.7.3 notes that FFE is being procured through the Owner’s Representative (not the CMc). There are items in the architectural narrative that could be part of the GMP or FFE. What items are included in FFE contract and what is in the CMc GMP?
a. Phone booths, lockers, cushions, modular furniture, workstations and loose items will be procured under a separate furniture contract. Appliances will be provided by a separate contract and the CMc should not include these costs. The CMc will provide and install built-in components such as millwork in the break room locations.
12. Will the Owner be providing builders risk insurance for the project?
a. No.
13. There are provisions in the RFP to convert the contract from a GMP to a Firm Fixed Price. Is it the GSA’s intent to exercise this option?
a. Yes, the Government intends to convert the GMP.
14. GN06 indicates level 5 finish in specialty areas. What area should the assumption be for the basis of the bid?
a. DELETE General Note GN 06. Level 5 finish is not required.
15. Please clarify locations for the ‘Skyfold’ partitions
a. Skyfold partitions are indicated on the drawings in the following rooms: 108 D-1, 108 D-2, 106 S-1, 106 S-2, 106 T, 108 X-1, 108 X-2, 109 X-1, 109 X-2.
16. CBP Workplace Standards indicate sound baffles on return grilles and acoustic dampers as options, in which locations should these be assumed?
a. Provide sound trap return air boots at all return air grilles in enclosed rooms.
17. CBP Workplace Standards indicate options for AV Screens, marker boards and acoustical wall panels in offices, project rooms, etc. For the basis of this pricing, what rooms should be assumed to have these products? Please provide size and product desired as well.
a. AV screens are by CBP vendor. Provide marker boards as indicated on drawings by note C.01.
Provide acoustical wall panels as indicated on drawings by note C.07.
18. Is there a location the CMc can occupy on the interior of the building for a field office?
a. There is no location within the building. CMc shall provide their own trailers which can be placed on-site as their field office during the course of the project.
19. How many individual docks at the loading dock will the CMc be able to occupy during construction for material loading/unloading? Will there be separate exterior laydown area for our use?
a. GSA can likely designate a single loading dock for project use.
There is laydown area in the grass on the northeast corner of the building (directly north of the guard shack). In addition, there are gravel areas within the fencing and directly south of the fencing on the east side of the building that may be available for use.
20. Will badging be required for each individual working on site? Is there a cost?
a. Per Appendix D (HSPD-12 Handbook), Chapter 2, page 14: Requirements for GSA contractors differ according to whether their employment is expected to be long-term or temporary:
(a.) Long-term contractors are those employed for more than 6 months (require a PIV vard/badge).
(b.) Temporary contractors are those employed for 6 months or less (do not require a badge, but must be escorted at all times by an individual holding a PIV card/badge).
Please review the handbook further to determine which of your employees will require either clearance type. Additionally, review Chapter 4 of the handbook.
GSA allows individuals to be escorted for a maximum of 15 cumulative dates in a 6 month period.
Also refer to Section 2.D. Personnel Security Requirements of the SOW which outlines the security clearance management process.
The Government is responsible for all costs associated with security clearances. The CMc is responsible for the cost to replace PIV cards/badges that are lost/stolen in the amount of $36 per PIV card/badge.
21. Will we need an escort within the building to get us into any of the areas we are doing work in?
a. No. With the exception of Temporary (Short-term) and Escorted type individuals per the HSPD-12
Security Clearance requirements. (See question regarding badging above).
22. What are the penalty terms for the bid guarantee?
a. Per FAR 52.228-1, failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
23. Will any of the existing equipment in the MDF rooms used for removed telecommunication and security infrastructure, racks, patch panels, data switches, UPS, etc. remain and be reused for new work?
a. Abandoned MDF rooms will have all equipment removed by the previous tenant.
24. Will the owner be providing any of the Audio/Video equipment required to be installed?
a. A/V equipment will be furnished and installed by the tenant.
25. Does the owner wish to retain any items removed from demolition?
a. The CMc shall turn over salvaged materials as indicated on the drawings.
26. There is 124,326 sf of renovation required for CBP part of the project. Per sheets A101 and A102 there is an additional 103,938 sf of work designated as "Future Work". These total 228,264 sf. All through the RFP there is mention of approximately 200,000 sf of work. Does the quantity of 103,938 sf for Future work agree with your quantities?
a. Total intended project area is 200,000 square feet.
27. What scopes of work are we to include in the areas designated as Future Work (USMC, USDA,
et. Al.)?
a. The scope of work for the future work areas (USMC) is the same concept design applied to the additional square footage. Costs for the CBP areas should be extrapolated or projected to the cross-hatched (future work) areas. Similar office layouts, workstation groupings, meeting spaces, etc. will be utilized in these areas.
28. Are we to include removal of existing furniture? If yes, who gets possession?
a. Existing furniture shall be removed by others, prior to construction commencement of this project.
29. Locker / File Legend on sheets A101, A102 list quantities to be provided and installed for 2 tier lockers and 3,5 high file cabinets. Are GC's to include this scope of work in our project budget?
a. No. At this stage of design the intent is for lockers to be included in the furniture package.
30. General Note GN.15 - Include demountable wall systems (Steelcase) for Huddle and Office
Blocks, also price as shown on plans stick built. Are we correct to assume the stick built option is the base budget and the demountable partitions options is an alternate?
a. Provide stick built partitions as base budget. Disregard all language on drawings referring to additional pricing or alternates.
31. General Note GN.17 - Please provide a typical size for the allowance for Strong Rooms
a. Strong Room requirements apply to the following rooms: 114b Z-2, 116b Z-1, 115 Z, 115 Y-4, 115
Y-3, 115 Y-2, 115 Y-1, 107 Y, 105 L, 117 E-1 , 103 C-3, 103 CC-3, 105 M-1, 218 C, 204 Ja, 204 Vb, and 204 G-2.
32. General Note GN.20 - Include additional price line item for interior storefront at perimeter offices within the OCC Suite (Northwest Area). Price as full height glazing with privacy film and shade.
Also price as shown on elevations with clerestory windows. Are we correct to assume the clerestory window option is base budget and the full height storefront option is an alternate?
a. Provide clerestory transom windows at perimeter offices in OCC Suite as indicated on sheet A420 in base budget. Disregard all language on drawings referring to additional pricing or alternates.
33. General Note GN.21 - Include additional pricing line item for shade (see General Note 11 For Spec) at Large Hearing Room in OCC Suite (Northwest Area) Are we correct to assume that this option is an alternate? Should we price manual or operable shades?
a. Provide manual shades at interior glazing in Large Hearing Room 106C as base budget. Disregard all language on drawings referring to additional pricing or alternates.
34. General Note GN.11 - Include additional line item for shades, shades at all exterior glazing within the CBP space to be priced as SWF Contract, Crosshatch A500, 5% Openness, manual shades or equal. Are we correct to assume that this option should be priced as an alternate?
a. Provide manual shades at all exterior windows in CBP Space as base budget. Disregard all language on drawings referring to additional pricing or alternates.
35. General Note GN.23 - Phone Booths are shown and are to be priced as furniture, MFR: Framery O and Q (59 Phone Booths Pods Total). Should GC's include this furniture in our project budget?
Should GC's include ALL office furniture shown on the design documents?
a. Phone booths, lockers, cushions, modular furniture, workstations and loose items will be procured under a separate furniture contract. Appliances will be provided by the tenant and the CMc should not include these costs. The CMc will provide and install built-in components such as millwork in the break room locations.
36. Flooring Finishes Note F.03 Sealed Concrete - Please provide some direction for type of material and floor preparation methods required.
a. Design intent is to expose existing concrete slab, patch/fill from demolition, remove paint/stains, clean and coat with clear floor sealer.
37. Equipment / Accessories Plan Note E.01 - Typical equipment - reference CBP workplace standards - exact specs and quantities TBD. Please provide additional information for materials and quantities to be included in our budget
a. Refer to pages 18-47 of the Final Concept Design Architectural Narrative (pages 42-71 of the combined narrative document) for CBP workplace standards and equipment requirements.
38. Equipment / Accessories Plan Note E.03 - Pull out drawers at Trash / Recycling - include bins and applied graphics. Please provide additional information for materials and quantities to be included in our budget
a. Refer to pages 18-47 of the Final Concept Design Architectural Narrative (pages 42-71 of the combined narrative document) for CBP workplace standards and equipment requirements.
39. Is an environmental assessment report available? We need to understand the extent of hazardous material abatement that may be required.
a. Yes. Please see Amendment #002 for environmental related scope/services required.
40. Can we limit the bid guarantee to 5% or 10% of the bid price? Is this acceptable?
a. No, it remains 20%.
41. There are several alternates listed on the drawings and in the design narratives. Where do you want us to show these prices?
a. Disregard all language on drawing referring to additional pricing or alternates.
42. We assume this project is exempt from Indiana Sales tax. Is this correct?
a. It is the responsibility of the contractor working with the Indiana Department of Revenue to determine whether or not work performed under the contract qualifies for a tax exemption.
43. GN20 asks for an additional pricing item for interior storefront with in the OCC suite. Would it be possible to show the limits of this work? Does this occur at the perimeter offices on just A401A, A401B? Our interpretation of perimeter offices are those offices on the exterior walls. Please clarify
a. Provide clerestory transom windows at perimeter offices in OCC Suite as indicated on sheet A420 in base budget. Disregard all language on drawings referring to additional pricing or alternates.
44. General Note 23 asks for 59 phone booths. We need to know how many Framery Type O (1-person) and how many Framery Type Q (2-4 persons) units are needed.
a. Phone booths, lockers, cushions, modular furniture, workstations and loose items will be procured under a separate furniture contract. Appliances will be provided by the tenant and the CMc should not include these costs. The CMc will provide and install built-in components such as millwork in the break room locations.
45. General Note 22, is there a specification for the color changing lights?
a. Provide color changing lights in 8 conference rooms. See link included for basis of design lighting product data: http://www.lumenwerx.com/wp-content/files/VIA5-RGBW-RECESSED-SPEC.pdf
46. What is the composition of the existing exterior walls? We assume new drywall will be required on exterior walls for placement of new power and data devices. Is this correct?
a. Existing exterior wall finish is gypsum wallboard. Contractor option to repair or replace.
47. Are the existing window sills scheduled to remain or are they being replaced?
a. Existing window sills are to remain.
48. There are rooms labeled as High-Density. We assume this references high-density storage. Are we to include high density storage units? Are we to include any concrete slab work required for the rails?
a. Provide high density storage system as base budget. System will be surface mounted and anchored to concrete slab without recess. Final selection of the movable storage system TBD.
49. Elevation 6/A420 has a mark C.08 that is not listed on the notes. Please clarify
a. Reference note C.01 instead.
50. The RFP mentions an Excel file "Bean Federal Center Lease Backfill Final Concept Estimate.xlsm" is included but we could not find. Please furnish.
a. We cannot provide this document as it is for internal government use only.
51. Is our proposal to include furniture? If so, specifications are needed.
a. Phone booths, lockers, cushions, modular furniture, workstations and loose items will be procured under a separate furniture contract. Appliances will be provided by the tenant and the CMc should not include these costs. The CMc will provide and install built-in components such as millwork in the break room locations.
52. The narrative indicates that there will be specifications for seismic requirements for equipment & supports for the fire suppression, plumbing, and electrical systems. Are seismic restraints required for these systems on this project? Are seismic certificates required for any equipment, and if so, which equipment…?
a. Seismic protection is required for fire protection and the emergency electrical systems. New fire protection or electrical equipment serving the emergency electrical system are required to be provided with a seismic certificate.
53. Please provide quantities of Hazmat materials to be abated.
a. Existing finished flooring scheduled to be removed may be installed over asbestos containing resilient tile and mastic systems or over encapsulate coating. Abatement of ACM down to original concrete floor slab will be required. CMc to assume 30% of the flooring contains ACM. Lead-based paint or encapsulated LBP is unknown at this time. CMc to assume 0% at this time. Water infiltration inside exterior wall beneath windows throughout the building has been documented and mold may be present but is unknown at this time. CMc to assume no mold at this time. Refer to environmental appendix for information relating to hazardous materials.
54. Please provide approved security vendor(s) for IDS, VSS, PACS and Audio Recording Systems?
a. Specific security vendor(s) have not been identified at this time. CMc to work with the design team and the tenant(s) to complete the design and installation of these systems per the tenant’s requirements.
55. Please confirm what Equipment and furnishings are CFCI. Please address phone booths, break room appliances, lockers, cushions, modular furniture, workstations, etc.
http://www.lumenwerx.com/wp-content/files/VIA5-RGBW-RECESSED-SPEC.pdf
a. Phone booths, lockers, cushions, modular furniture, workstations and loose items will be procured under a separate furniture contract. Appliances will be provided by the tenant and the CMc should not include these costs. The CMc will provide and install built-in components such as millwork in the break room locations.
56. Please confirm that the items shown on the furniture data sheets are OFOI.
a. The items shown on the furniture data sheets will be provided and installed by a separate furniture contractor.
57. Please provide existing HVAC controls manufacturer.
a. The existing temperature control system was provided by Precision Controls of Indianapolis.
58. Please provide a design narrative, program requirements, concept wall layout, etc. for USMC spaces if available.
a. USMC program of requirements is being developed at this time. It is not currently available. The concept architectural design characteristics of the CBP space and as indicated by the architectural narratives will apply to USMC space.
59. The RFP indicates the total project square footage will be approximately 200,000 SF. The drawings currently indicate just over 100,000 SF of space allocated for the USMC spaces. Please confirm the total project is approximately 230,000 SF for both CBP and USMC spaces.
a. Total intended project area is 200,000 square feet.
60. Please clarify further Strong Room requirements per GN. 17 (dimensions, etc) to establish allowance.
a. See response to line item 31.
61. Please provide the finish C.08 shown on the elevation.
a. See response to line item 49.
62. Please confirm pre-action fire suppression is required for LAN rooms.
a. IT Rooms will not be provided with a pre-action system per the requirements of the P100, refer to
7.11.2 of the P100.
63. "The Design Narratives Table of Contents indicates:
The following excel file is included with this submission:
• Bean Federal Center Lease Backfill Final Concept Estimate.xlsm Will this be provided or should this be stricken from the Table of Contents?"
a. We cannot provide this document as it is for internal government use only
64. Please confirm removal of existing furnishings will not be required.
a. See response to line item 2.
65. Please confirm partition height around Private Offices and Project Rooms (base bid) extend only to the ceiling height and not to the structure above. If the alternate for Demountable partitions is accepted please confirm the height of the demountable partitions.
a. Provide stick-built partitions extending to structure above as base budget. Disregard all language on drawings referring to additional pricing or alternates
66. Please confirm workstations on page 23 of the room data sheets are not included in the demountable partitions scope of work and shall be part of the furniture package by others.
a. Phone booths, lockers, cushions, modular furniture, workstations and loose items will be procured under a separate furniture contract. Appliances will be provided by the tenant and the CMc should not include these costs. The CMc will provide and install built-in components such as millwork in the break room locations.
67. Based on the schedule, all design is complete by August 2021, but we are not able to release contracts until August 2022. I do not see any activities on the schedule to address what happens during this 12 month period. Can you please provide your expectations and/or the work that will take place during this 12 month gap so we can be sure to address it in our RFP
a. The start of construction depends upon release of space that is currently occupied by other federal agencies which are not associated with this project. Vacated space required for this project's construction was previously planned for release to GSA on 9/30/2021. The space release date has recently changed. The anticipated date of space release for construction under this project is now as late as 9/30/2022. GSA is using this date for planning purposes. If space is released earlier than 9/30/2022, GSA's intent is to award the CMc construction option earlier and begin construction as soon as possible.
* Drawing Scope Note 02.4119.13 is amended as follows: "Remove all existing finished flooring systems including carpet and underlying levelers, encapsulates, original resilient tile, mastics, adhesives, etc.
Prepare exposed concrete for new specified finished flooring system.
* GN 10 is amended as follows: "All existing columns to be prepared for specified finish, primed and painted".
* General Note GN 07 reads, "All areas exposed to structure shall be painted general white, UNO".
ADD Note L to General Notes on Reflected Ceiling Plans A-111 and A-112. Note L to read, "All exposed structure to be painted general white UNO"
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020
General Services Administration Public Buildings Service
Construction Manager as Constructor (CMc) Statement of Work (SoW)
PROJECT IDENTIFICATION
Project Name: Bean Federal Center Lease Backfill Project
Project Number: PIN-1703-IN18
Region: Region 5, Great Lakes Region.
Building Name: Major General Emmett J. Bean Federal Center
Building Address: 8899 East 56th Street, Indianapolis, Indiana 46249
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020
TABLE OF CONTENTS
I. PROJECT DESCRIPTION 4
A. Base Contract (Design Stage) Services 4 B. Option (Construction) Services 5
II. GENERAL REQUIREMENTS 6
A. Project Duration and Schedule Milestone 6 B. Reference Materials 6
1. Standards and Criteria Documents 6 C. Project Team and Communications 8
1. Identification of the CMc Team 9
2. Project Delivery Team 10
3. Architect/Engineering Firm (A/E) 10
4. Construction Manager as Agent (CMa) 10
5. Commissioning Agent (CxA) 11
6. Communications Plan 11
D. Personnel Security Requirements 11 E. Project Management 12
1. Electronic Project Management (ePM) 12
a) Definition 12
b) Project Collaboration and Documentation 12
c) Equipment 12
d) Training 13
e) Support 13
f) Personnel Requirements 13
g) Data Ownership 13
F. Base Services (Design Stage) Progress Payments 13 G. Travel 14 H. Project Delivery Requirements 14
1. Construction Excellence 14
2. Art in Architecture Program (AiA) 15
III. SCOPE OF SERVICES 16
A. Scope Base (Design Stage) Services 16
1. Design Stage in General 16
2. Collaboration with the A/E 16
3. Meetings 16
a) Project Initiation Meeting 17
b) Progress Meetings and Presentations 17
c) Design Submission Reviews 17
d) Risk Management Workshops 18
e) Building Information Modeling (BIM) 18
f) Systems Selections Analysis Meetings and Mockups 18
g) Value Management 18
h) Partnering 18
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020
4. Deliverables 19
a) Required Deliverables 19
b) Constructability Review 19
c) Cost Estimating, Reconciliation, and Proposed Alternatives
(CERPA) 20
d) Preliminary Project Schedule and Analysis 20
e) Construction Work Sequencing and Phasing Plan 21
f) Early Work Packages 21
g) Modifications to the Risk Registry 21
B. Scope of Option (Construction Stage) Services 21
1. Pre-Construction Conference 21
2. Submittal Schedule 21
3. Project Progress Meetings 22
4. Inspections and Testing 22
5. Hazardous Materials 22
6. Project Documentation 22
7. Clarifications/ Requests for Information / Change Orders 22
8. Payment Requests 23
9. CMc Contingency Allowance 23
10. Construction Excellence Peer Reviews (CE PR) 23
11. Art-in-Architecture (AiA) Installation 23
12. Commissioning 24
13. Turnover Process 24
14. Closeout Documentation 24
15. Material Samples, Attic Stock and Spare Parts 24
16. Preparations for Occupancy 25
17. Project Awards/LEED Certification/Dedication Ceremony 25
18. Contract Closeout 25
IV. APPENDIX A - REFERENCE DOCUMENTS 26
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020
I. PROJECT DESCRIPTION
This Statement of Work (SOW) is for Construction Manager as Constructor (CMc) for the renovation project of approximately 200,000 square feet (sf) at the The Major General Emmett J. Bean Federal Center (Bean Center).
GSA has contracted with a separate architect-engineer (A/E) firm that is responsible for developing complete design and construction documents for this Project. In addition, GSA has contracted with a separate Construction Management Advisor (CMa) firm with Commissioning Agent (CxA) services to provide certain services during the design and construction stages of this Project. A copy of the AE and CMa/CxA statements of work (SOW) are included in Section IV Appendix. GSA has also issued an additional, separate contract to an artist under the Art-in-Architecture program.
The MGEJ Bean Center was named after Major General Emmett J. Bean, a commander of the Army Finance Center in St. Louis, and who coordinated the Center's move to Indianapolis.
The building was once part of Ft. Benjamin Harrison, a former military installation. Ft.
Benjamin Harrison closed in 1995 and ownership of the building was transferred from the Department of Defense (DoD) to GSA in October 1996. This 3-story building of approximately
1.66 million gross square feet is currently being used as a multi-tenant office building. It was modernized and renovated in 2003 to an office space type interior from its previous use as a DoD records storage facility and is eligible for listing on the National Register of Historic Places.
The current MGEJ Bean Center’s primary tenant is consolidating their utilization of space. This will result in approximately 200,000 sf of vacant space which the GSA intends to backfill with new federal agency occupancies currently housed in leased office space in the Indianapolis area. Design services, which will be accomplished through a separate contract, will be necessary for the renovations and alterations of vacant space to meet; the functional requirements of prospective tenants, fulfill policy and regulatory criteria, and provide state of the art workplaces that help define interior design standards for the building. Designed solutions shall be consistent with the latest objectives of GSA, prospective tenants, and best practices in architectural planning and design.
The primary customers for this project are U.S. Customs and Border Protection (CBP) and the U.S. Marine Corps (USMC). The space required by these prospective tenants is primarily general office space including; both open office area and private offices, ancillary and support space such as conference rooms, secure sensitive areas and storage.
A. Base Contract (Design Stage) Services The Design Stage of this project shall include all services taking place prior to or preceding the Construction Stage. This Statement of Work (SOW) primarily focuses and outlines the Design Stage services not otherwise provided for in the Contract Design Documents that the CMc Contractor shall be required to perform. The CMc Contractor is required to complete the Design Stage Services for the firm-fixed-price set forth in the Contract Price Schedule.
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020
As a general matter, the CMc Contractor shall review and become familiar with the scope of services under the A/E’s SOW contract, especially the various standards, guidelines, policies, and documents (also see Section II.B. Reference Materials below) required to develop the design and construction documents. This review and familiarization is vitally important as part of the Pre-Construction Services as the primary tasks of the CMc Contractor during the Design Stage are to provide constructability and cost estimation reviews of the A/E’s submissions (see Section III.A). At its core, the CMc Contractor will help to ensure that the design and construction documents will enable the Government to exercise the Guaranteed Maximum Price (GMP) Option at a price that is at or below the GMP.
B. Option (Construction) Services This Option relates to the Construction Stage Services that will be required by the CMc Contractor. These services, as outlined within this SOW, provide a general and brief description of services the CMc Contractor shall be required to perform during the Construction Stage (see Section III.B). In the event of a discrepancy between Construction Stage services outlined within this SOW and the A/E’s Construction Documents (CDs), the CD shall take precedence.
Prior to the exercise of this Option, the Government and the CMc Contractor shall agree on the Estimated Cost of the Work (“ECW”), which when combined with the Fee and the Construction Contingency Allowance shall not exceed the Guaranteed Maximum Price (GMP). Upon exercise of this Option for Construction Stage services, the CMc Contractor shall be held responsible for completing the construction stage work in its entirety.
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020
II. GENERAL REQUIREMENTS
Requirements in this section shall apply to both the Base and Option services and all project stages. The CMc Contractor shall understand and fully comply with the Principles of Federal Contracting, including contract administration, in accordance with Federal Acquisition Regulation (FAR), the General Services Administration Acquisition Manual (GSAM), and Public Buildings Services acquisition policy.
As a general matter, the Facilities Standards for the Public Buildings Service (P-100) represents the overarching document that governs the CMc Contractor’s performance of work.
In addition, other policies and procedures (such as those listed in Section II.Bl. Reference Materials below) provide detailed procedures and requirements that the CMc Contractor shall follow. The primary purpose of this Statement of Work (SoW) is to set forth services that the CMc Contractor shall provide in addition to the services that will be outlined in final, approved Construction Documents (drawings and specifications), which shall be completed by the separate Architect/Engineering (A/E) firm hired as part of this project.
A. Project Duration and Schedule Milestone The project’s general milestone schedules are identified below, and are not indicative or representative of the entire list of anticipated deliverables, tasks, reviews, meetings, and/or due dates as defined within this SOW. Preliminary full project milestone schedule is included in Section IV, Appendix for CMc Contractor’s reference. The finalized project duration(s) and key milestone dates will be located in the Construction Documents.
The CMc Contractor is directed to review the milestone data and base their proposal per the dates indicated below:
Design Documents (DDs) Complete February 2021
Construction Documents (CDs) Complete August 2021
Construction NTP October 2022
Construction Substantial Completion May 2024
Construction Final Completion August 2024
B. Reference Materials There are two types of Reference Materials. The first type are project-specific planning documents and information listed in Section IV, Appendix. The second type are the Standards and Criteria Documents, which are specifically set forth below.
1. Standards and Criteria Documents All designs developed under this contract must comply to the maximum extent feasible with the following GSA Standards and Guidelines and federal, state and
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020 local codes and laws. The latest edition of these codes and standards in effect at the time the design is started must be used throughout the design and construction stages of this project.
● GSA, PBS P-100, Facilities Standards for the Public Buildings Service
○ http://www.gsa.gov/p100
● GSA National Business Space Assignment Policy
○ https://www.gsa.gov/cdnstatic/NBSAP_Feb_2013.pdf
● GSA Pricing Desk Guide, 4th Edition
○ https://www.gsa.gov/cdnstatic/Pricing_Desk_Guide_4th_Ed__2014.6.5_LP
OE_update_FINAL.pdf
● ePM Requirements
○ http://www.gsa.gov/epm
● General Services Administration Criteria
○ http://www.wbdg.org/ffc/gsa/criteria
● GSA, PBS P-120, Project Estimating Requirements
○ https://www.gsa.gov/cdnstatic/P_120.pdf
● Key Sustainable Products Standards
○ https://www.gsa.gov/cdnstatic/KSP_report_for_071415_%281%29.pdf
● GSA PBS National Environmental Policy Act (NEPA) Desk Guide
○ https://www.gsa.gov/cdnstatic/PBS_NEPA_Deskguide.pdf
● GSA, PBS Asbestos Policy
○ https://www.gsa.gov/directives-library/asbestos-policy-10001-pbs
● GSA, Fire Protection and Life Safety, Design and Construction Responsibilities
○ https://www.gsa.gov/real-estate/environmental-programs/fire-protection-and -life-safety/design-and-construction
● GSA, Design and Construction Overview
○ https://www.gsa.gov/real-estate/design-and-construction-overview
● GSA, Building Information Modeling Guide
○ https://www.gsa.gov/real-estate/design-construction/3d4d-building-informati on-modeling/bim-guides
● GSA, Commissioning Program
○ https://www.gsa.gov/real-estate/design-construction/commissioning/commis sioning-program
● GSA, PBS Building Commissioning Guide
○ https://www.gsa.gov/cdnstatic/BCG_3_30_Final_R2-x221_0Z5RDZ-i34K-p
R.pdf
● GSA, Design Excellence Policies and Procedures
○ https://www.gsa.gov/real-estate/design-construction/design-excellence/desi gn-excellence-program/design-excellence-policies-and-procedures
● GSA, Construction Excellence
○ https://www.gsa.gov/real-estate/design-construction/construction-excellenc e
● GSA, PBS CAD Standards
○ https://www.gsa.gov/cdnstatic/PBS_CAD_Standards.pdf
● GSA Guiding Principles Checklist for New Construction and Major http://www.gsa.gov/p100 https://www.gsa.gov/cdnstatic/NBSAP_Feb_2013.pdf https://www.gsa.gov/cdnstatic/Pricing_Desk_Guide_4th_Ed__2014.6.5_LPOE_update_FINAL.pdf https://www.gsa.gov/cdnstatic/Pricing_Desk_Guide_4th_Ed__2014.6.5_LPOE_update_FINAL.pdf http://www.gsa.gov/epm http://www.wbdg.org/ffc/gsa/criteria https://www.gsa.gov/cdnstatic/KSP_report_for_071415_%281%29.pdf https://www.gsa.gov/cdnstatic/PBS_NEPA_Deskguide.pdf https://www.gsa.gov/directives-library/asbestos-policy-10001-pbs https://www.gsa.gov/real-estate/environmental-programs/fire-protection-and-life-safety/design-and-construction https://www.gsa.gov/real-estate/environmental-programs/fire-protection-and-life-safety/design-and-construction https://www.gsa.gov/real-estate/design-and-construction-overview https://www.gsa.gov/portal/getMediaData?mediaId=227487 https://www.gsa.gov/real-estate/design-construction/3d4d-building-information-modeling/bim-guides https://www.gsa.gov/real-estate/design-construction/3d4d-building-information-modeling/bim-guides https://www.gsa.gov/real-estate/design-construction/commissioning/commissioning-program https://www.gsa.gov/real-estate/design-construction/commissioning/commissioning-program https://www.gsa.gov/cdnstatic/BCG_3_30_Final_R2-x221_0Z5RDZ-i34K-pR.pdf https://www.gsa.gov/cdnstatic/BCG_3_30_Final_R2-x221_0Z5RDZ-i34K-pR.pdf https://www.gsa.gov/real-estate/design-construction/design-excellence/design-excellence-program/design-excellence-policies-and-procedures https://www.gsa.gov/real-estate/design-construction/design-excellence/design-excellence-program/design-excellence-policies-and-procedures https://www.gsa.gov/real-estate/design-construction/construction-excellence https://www.gsa.gov/real-estate/design-construction/construction-excellence https://www.gsa.gov/cdnstatic/PBS_CAD_Standards.pdf
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020
Modernization Projects
○ https://www.gsa.gov/cdnstatic/Design_and_Construction/2016_Guiding_Pri nciples_Checklist_07242018.pdf
● Implementing Value Engineering
○ https://www.gsa.gov/real-estate/design-construction/engineering-and-archit ecture/value-engineering/implementing-value-engineering
● GSA, Information Technology Policy
○ https://www.gsa.gov/policy-regulations/policy/information-technology-policy
● GSA, order 2100.1J GSA Information Technology (IT) Security Policy
○ https://gsa.gov/portal/mediaId/129634/fileName/CIO_21001J_CHGE_1_GS
A_Information_Technology_(IT)_Security_Policy_(Posted_Version_4-28-20 16).action
● IT Security Procedural Guides
○ https://www.gsa.gov/about-us/organization/office-of-the-chief-information-of ficer/chief-information-security-officer-ciso/it-security-procedural-guides
● Office of Mission Assurance (OMA) HPSD-12 Branch
○ https://www.gsa.gov/technology/government-it-initiatives/identity-credentials -and-access-manage/office-of-mission-assurance-oma-hspd12-branch
● Historic Preservation Policy, Tools and Resources
○ https://www.gsa.gov/real-estate/historic-preservation/historic-preservation-p olicy-tools-resources
● Whole Building Design Guide
○ http://www.wbdg.org/ffc/federal-facility-criteria
● GSA, Total Workplace Program
○ https://www.gsa.gov/governmentwide-initiatives/total-workplace
● GSA, PBS NEPA Desk Guide, October 1999
○ https://www.gsa.gov/cdnstatic/PBS_NEPA_Deskguide.pdf
● Architectural Barriers Act Accessibility Standards (ABAAS)
○ https://www.gsa.gov/cdnstatic/ABAAS_FAQ_v2b_R2C15-e_0Z5RDZ-i34K-pR.pdf
● Appendix E Accessibility Standards
○ https://www.gsa.gov/cdnstatic/Accessibility-AppendixE_1-18-11_508c.pdf
● GSA, Spatial Data Management Program
○ https://www.gsa.gov/real-estate/design-construction/spatial-data-managem ent-overview
C. Project Team and Communications The parties to this contract are the Construction Manager as Constructor (CMc or CMc Contractor), and the United States of America, acting by and through the General Services Administration (GSA). GSA may be referred to as “Owner” throughout the contract documents and project. The primary Customers for this project is the U.S.
Customs and Border Protection (CBP) and the U.S. Marine Corps (USMC).
https://www.gsa.gov/real-estate/design-construction/engineering-and-architecture/value-engineering/implementing-value-engineering https://www.gsa.gov/real-estate/design-construction/engineering-and-architecture/value-engineering/implementing-value-engineering https://www.gsa.gov/policy-regulations/policy/information-technology-policy https://gsa.gov/portal/mediaId/129634/fileName/CIO_21001J_CHGE_1_GSA_Information_Technology_(IT)_Security_Policy_(Posted_Version_4-28-2016).action https://gsa.gov/portal/mediaId/129634/fileName/CIO_21001J_CHGE_1_GSA_Information_Technology_(IT)_Security_Policy_(Posted_Version_4-28-2016).action https://gsa.gov/portal/mediaId/129634/fileName/CIO_21001J_CHGE_1_GSA_Information_Technology_(IT)_Security_Policy_(Posted_Version_4-28-2016).action https://www.gsa.gov/about-us/organization/office-of-the-chief-information-officer/chief-information-security-officer-ciso/it-security-procedural-guides https://www.gsa.gov/about-us/organization/office-of-the-chief-information-officer/chief-information-security-officer-ciso/it-security-procedural-guides https://www.gsa.gov/real-estate/historic-preservation/historic-preservation-policy-tools-resources https://www.gsa.gov/real-estate/historic-preservation/historic-preservation-policy-tools-resources http://www.wbdg.org/ffc/federal-facility-criteria https://www.gsa.gov/governmentwide-initiatives/total-workplace https://www.gsa.gov/cdnstatic/PBS_NEPA_Deskguide.pdf https://www.gsa.gov/cdnstatic/ABAAS_FAQ_v2b_R2C15-e_0Z5RDZ-i34K-pR.pdf https://www.gsa.gov/cdnstatic/ABAAS_FAQ_v2b_R2C15-e_0Z5RDZ-i34K-pR.pdf https://www.gsa.gov/cdnstatic/Accessibility-AppendixE_1-18-11_508c.pdf https://www.gsa.gov/real-estate/design-construction/spatial-data-management-overview https://www.gsa.gov/real-estate/design-construction/spatial-data-management-overview
CMc Design & Construction Phase Update, June 30, 2020 MGEJ Bean Federal Center Backfill Prospectus May 28, 2020
The individual authorized to act on the behalf of the GSA in the administration of this contract is the Contracting Officer (CO). The GSA CO may delegate certain of his or her authorities to others who will be known as the Contracting Officer’s Representative (COR) and if so, will notify the CMc, in writing, of the specific authorities delegated to, and limitations placed upon, named authorized representatives. The CMc must not take any direction, or act upon any information, from individuals other than those having the requisite authority as confirmed by the GSA CO’s written notification.
1. Identification of the CMc Team The CMc shall provide sufficient staff and propose a team that can meet the requirements of this SOW and must utilize the personnel named in its accepted offer to perform the services required under this contract. In the event that any of the personnel named in the accepted CMc proposal become unavailable, the CMc Contractor must promptly; submit a complete written resume for a proposed substitution, any other information necessary for the GSA to approve or disapprove, and a detailed explanation of the circumstances necessitating the proposed substitution.
This is the start of the file's text. The full file is on GovTribe.