Solicitation 47PF0020R0026 Amendment 002.pdf
PDF 391 KB Posted
- Attached to
- Bean Backfill CMc - Award Federal contract opportunity
- Solicitation number
- 47PF0020R0026
About this file
This is an amendment to a master schedule for the Bean Backfill project. The schedule provides details on procurement of a construction manager as constructor (CMc) to support construction activities. Key details include that CMc procurement will take place from January 2020 through August 2022, with construction mobilization beginning in August 2022. Construction is scheduled to start in October 2022 and be completed by May 2024 for the Customs and Border Protection and Marine Corps tenants. Closeout and occupancy activities, including tenant moves, will then occur through August 2024 to fully complete the project. The General Services Administration Region 5 is the contracting agency managing this federal construction project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Beta SAM Public Notice of Award.pdf | ||
| Solicitation 47PF0020R0026 Amendment 005.pdf | ||
| Solicitation 47PF0020R0026 Amendment 004.pdf | ||
| Solicitation 47PF0020R0026 Amendment 001.pdf | ||
| MGEJB Backfill_CMc SOW_2020 May 28.pdf | ||
| Bean Backfill CMc - RFP Package with Prospectus 06042020.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
1 5
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
Activity ID Activity Name Original
Duration
Remaining
Duration
Schedule %
Complete
Start Finish
BEAN BACKFILL BEAN BACKFILL: CBP & USMC Master ScheduleBEAN BACKFILL BEAN BACKFILL: CBP & USMC Master Schedule 2239 1078 0% 05-Jan-16 A 05-Aug-24
BEAN BACKFILL.1 MGEJ BEAN Center Backfill: Master ScheduleBEAN BACKFILL.1 MGEJ BEAN Center Backfill: Master Schedule 2239 1078 0% 05-Jan-16 A 05-Aug-24
BEAN BACKFILL.1.1 Project Initiation ActivitiesBEAN BACKFILL.1.1 Project Initiation Activities 2032 361 0% 05-Jan-16 A 19-Oct-23
BEAN BACKFILL.1.1.1 CILP Appropriation & FundingBEAN BACKFILL.1.1.1 CILP Appropriation & Funding 950 0 0% 05-Jan-16 A 01-Oct-19 A
Funding-010 Develop CILP Documents 95 0 100% 05-Jan-16 A 16-May-16 A
Funding-020 ***CUSTOMER REQUEST (1) 1 0 100% 05-Jan-16 A 05-Jan-16 A
Funding-030 ***PROJECT INITIATED (28) 0 0 100% 16-May-16 A 16-May-16 A
Funding-040 ***DEFINE PROJECT FUNDING REQUIREMENT (62) 1 0 100% 17-May-16 A 17-May-16 A
Funding-050 Develop & Issue Draft OA's for CBP 70 0 100% 29-Aug-17 A 04-Dec-17 A
Funding-060 INITIAL SCOPE & REQUIREMENTS FINALIZED WITH CUSTOMER: 1 0 100% 12-Sep-17 A 12-Sep-17 A
Funding-070 ***CONGRESSIONAL APPROPRIATION (OMNIBUS) (61) 1 0 100% 23-Mar-18 A 23-Mar-18 A
Funding-080 PROJECT AUTHORIZATION (02) (Approval to proceed but not award) 1 0 100% 15-Jun-16 A 15-Jun-16 A
Funding-090 ***SIGNED DRAFT OA's RECEIVED: Tenant A (08) 1 0 100% 02-Jan-19 A 02-Jan-19 A
Funding-100 ***INITIAL CUSTOMER AGREEMENT/DRAFT OA: Tenant A (04) 1 0 100% 15-Jan-19 A 15-Jan-19 A
Funding-110 Funding Released by GSA 1 0 100% 11-Apr-19 A 11-Apr-19 A
Funding-120 Develop & Issue Draft OA for USMC 30 0 100% 01-Aug-19 A 11-Sep-19 A
Funding-130 Occupancy Committment Received from USMC: Start POR 1 0 100% 01-Oct-19 A 01-Oct-19 A
BEAN BACKFILL.1.1.2 RWA'sBEAN BACKFILL.1.1.2 RWA's 361 361 0% 01-Jun-22 19-Oct-23
BEAN BACKFILL.1.1.2.1 CBP RWA's ProcesessingBEAN BACKFILL.1.1.2.1 CBP RWA's Procesessing 327 327 0% 01-Jun-22 01-Sep-23
RWA-CBP-005 CBP Agency Funds in Place 5 5 0% 01-Jun-22* 07-Jun-22
RWA-CBP-010 CBP FY22 RWA Certified 0 0 0% 14-Jun-22* 14-Jun-22
RWA-CBP-020 Process CBP FY22 RWA 34 34 0% 14-Jun-22 29-Jul-22
RWA-CBP-030 CBP FY22 RWA Accepted by GSA 0 0 0% 01-Aug-22 01-Aug-22
RWA-CBP-040 CBP Move Services RWA Certified 1 1 0% 20-Oct-22* 20-Oct-22
RWA-CBP-050 Process CBP FY23 RWA 35 35 0% 05-Jul-23* 22-Aug-23
RWA-CBP-060 CBP FY23 RWA Accepted 0 0 0% 01-Sep-23* 01-Sep-23
BEAN BACKFILL.1.1.2.2 USMC RWA ProcessessingBEAN BACKFILL.1.1.2.2 USMC RWA Processessing 361 361 0% 01-Jun-22 19-Oct-23
RWA-USMC-005 USMC Agency Funds in Place 5 5 0% 01-Jun-22* 07-Jun-22
RWA-USMC-010 USMC Construction RWA Certified 0 0 0% 14-Jun-22* 14-Jun-22
RWA-USMC-020 Process USMC Construction RWA 34 34 0% 14-Jun-22 29-Jul-22
RWA-USMC-030 USMC Construction RWA Accepted by GSA 0 0 0% 01-Aug-22 01-Aug-22
RWA-USMC-040 Process FY24 USMC Move-Services RWA 34 34 0% 01-Sep-23* 18-Oct-23
RWA-USMC-050 USMC FY24 Move Services RWA Certified 0 0 0% 19-Oct-23* 19-Oct-23
RWA-USMC-060 USMC FY24 Move-Services RWA Accepted 0 0 0% 19-Oct-23 19-Oct-23
BEAN BACKFILL.1.2 Planning PhaseBEAN BACKFILL.1.2 Planning Phase 1469 308 0% 06-Jun-16 A 23-Aug-21
BEAN BACKFILL.1.2.1 Program Development Study: CBPBEAN BACKFILL.1.2.1 Program Development Study: CBP 323 0 0% 06-Jun-16 A 28-Aug-17 A
PLAN-010 Prepare PDS SOW 43 0 100% 06-Jun-16 A 03-Aug-16 A
PLAN-020 Procure & Award PDS 9 0 100% 04-Aug-16 A 16-Aug-16 A
PLAN-030 PRE-DESIGN AWARD (17) 1 0 100% 16-Aug-16 A 16-Aug-16 A
PLAN-040 Prepare, submit, review 35% PDS 90 0 100% 17-Aug-16 A 20-Dec-16 A
PLAN-050 Prepare, submit, review 50% PDS 74 0 100% 21-Dec-16 A 03-Apr-17 A
PLAN-060 Prepare, submit, review 90% PDS 62 0 100% 04-Apr-17 A 28-Jun-17 A
PLAN-070 Prepare, submit, review 100% PDS 43 0 100% 29-Jun-17 A 28-Aug-17 A
PLAN-080 PRE-DESIGN COMPLETE: Tenants A (18) 1 0 100% 28-Aug-17 A 28-Aug-17 A
BEAN BACKFILL.1.2.2 Project DesignBEAN BACKFILL.1.2.2 Project Design 1469 308 0% 03-Jan-18 A 23-Aug-21
BEAN BACKFILL.1.2.2.1 Design for CBP & Concept Phase Design Standards for USMCBEAN BACKFILL.1.2.2.1 Design for CBP & Concept Phase Design Standards for USMC 1469 308 0% 03-Jan-18 A 23-Aug-21
BEAN BACKFILL.1.2.2.1.1 D.E.A/E ProcurementBEAN BACKFILL.1.2.2.1.1 D.E.A/E Procurement 800 0 0% 03-Jan-18 A 10-May-19 A
AE-PRPCURE-010 Write & approve A/E Acquisition Plan 14 0 100% 03-Jan-18 A 22-Jan-18 A
AE-PRPCURE-020 DESIGN ACQUISITION PLAN FINALIZED (05) 1 0 100% 23-Jan-18 A 23-Jan-18 A
AE-PRPCURE-030 Write Stage 1 Synopsis for FBO posting 13 0 100% 06-Feb-18 A 22-Feb-18 A
AE-PRPCURE-040 DE Synopsis Review & Approval by Central Office 10 0 100% 09-Feb-18 A 22-Feb-18 A
AE-PRPCURE-050 OCA Finalize A/E Selection Board & Industry Peer Selection 121 0 100% 23-Feb-18 A 10-Aug-18 A
AE-PRPCURE-060 Prepare detailed IGCE for A/E Contract 156 0 100% 30-Apr-18 A 03-Dec-18 A
AE-PRPCURE-070 Write full A/E SOW 89 0 100% 15-May-18 A 14-Sep-18 A
AE-PRPCURE-080 DESIGN PR SUBMITTED (43) (Funding Memo Received from Central Office) 1 0 100% 15-Jun-18 A 15-Jun-18 A
AE-PRPCURE-090 CONTRACTING ACCEPTS DESIGN PR (44) (Funding Memo) 1 0 100% 15-Jun-18 A 15-Jun-18 A
AE-PRPCURE-100 DESIGN RFP PUBLISHED in FBO (Stage 1)(06) 1 0 100% 25-Jun-18 A 25-Jun-18 A
AE-PRPCURE-110 FBO Posting period from Stage I Synopsis 49 0 100% 26-Jun-18 A 31-Aug-18 A
AE-PRPCURE-120 DESIGN RFP PROPOSALS RECEIVED (Stage 1)(30) 1 0 100% 31-Jul-18 A 31-Jul-18 A
AE-PRPCURE-130 SSEB Review/deliberate/shortlist Stage 1 Proposals 3 0 100% 13-Aug-18 A 15-Aug-18 A
AE-PRPCURE-140 DESIGN FIRMS SHORTLISTED (31) 1 0 100% 28-Aug-18 A 28-Aug-18 A
AE-PRPCURE-150 Stage II Announcement.Solicitation Period & Networking session 25 0 100% 29-Aug-18 A 02-Oct-18 A
AE-PRPCURE-160 Stage II Proposals received 1 0 100% 02-Oct-18 A 02-Oct-18 A
AE-PRPCURE-170 SSEB Stage 2 Evaluate/Interview/Rank/Select A/E 16 0 100% 02-Oct-18 A 23-Oct-18 A
AE-PRPCURE-180 Prepare A/E Evaluation Board Report 19 0 100% 23-Oct-18 A 16-Nov-18 A
AE-PRPCURE-190 Regional Commissioner review & approval 2 0 100% 19-Nov-18 A 20-Nov-18 A
AE-PRPCURE-200 FIRM SELECTED/ISSUE RFP FOR A/E PRICING PROPOSAL (32) 1 0 100% 20-Nov-18 A 20-Nov-18 A
AE-PRPCURE-210 A/E prepare pricing proposal 22 0 100% 21-Nov-18 A 20-Dec-18 A
AE-PRPCURE-220 FBO Announcement of A/E Selection 10 0 100% 21-Nov-18 A 04-Dec-18 A
AE-PRPCURE-230 A/E pricing proposal received by GSA 1 0 100% 21-Dec-18 A 21-Dec-18 A
AE-PRPCURE-240 Government Shutdown 16 0 100% 07-Jan-19 A 28-Jan-19 A
AE-PRPCURE-250 Review Pricing Proposal then conduct several rounds of Negotiations 50 0 100% 28-Jan-19 A 05-Apr-19 A
AE-PRPCURE-260 IG Audit 26 0 100% 30-Jan-19 A 06-Mar-19 A
AE-PRPCURE-270 AMD completes file & award documents 15 0 100% 08-Apr-19 A 26-Apr-19 A
AE-PRPCURE-280 Process A/E Award allowance request 11 0 100% 23-Apr-19 A 07-May-19 A
AE-PRPCURE-290 PR routed for A/E award 4 0 100% 07-May-19 A 10-May-19 A
AE-PRPCURE-300 A/E CONTRACT AWARDED (19) 1 0 100% 10-May-19 A 10-May-19 A
AE-PRPCURE-310 CONTRACTING ACCEPTS DESIGN PR 1 0 100% 10-May-19 A 10-May-19 A
BEAN BACKFILL.1.2.2.1.2 Design Execution : CBPBEAN BACKFILL.1.2.2.1.2 Design Execution : CBP 591 308 0% 10-May-19 A 23-Aug-21
BEAN BACKFILL.1.2.2.1.2.1 Design Contract MobilizationBEAN BACKFILL.1.2.2.1.2.1 Design Contract Mobilization 208 0 0% 10-May-19 A 03-Mar-20 A
DESIGN MOD-010 A/E Executes Subcontracts 166 0 100% 10-May-19 A 03-Mar-20 A
DESIGN MOD-020 A/E Team key Security Clearances 27 0 100% 17-May-19 A 24-Jun-19 A
DESIGN MOD-030 Pre-design site analysis & Critaria review 24 0 100% 05-Jul-19 A 07-Aug-19 A
DESIGN MOD-040 A/E CONTRACT FULL NTP (21) 1 0 100% 19-Jul-19 A 19-Jul-19 A
BEAN BACKFILL.1.2.2.1.2.3 D.E. Concept PhaseBEAN BACKFILL.1.2.2.1.2.3 D.E. Concept Phase 242 0 0% 16-Aug-19 A 12-Jun-20 A
DE CONCEPT-010 Develop (3) preliminary concepts 61 0 100% 16-Aug-19 A 08-Nov-19 A
DE CONCEPT-020 CMa preliminary concepts cost estimating 16 0 100% 25-Oct-19 A 15-Nov-19 A
DE CONCEPT-030 CBP & GSA Review & comment for Preliminary concept designs 21 0 100% 15-Nov-19 A 13-Dec-19 A
DE CONCEPT-040 Conduct OCA Informal Review of Preliminary Concepts 1 0 100% 18-Dec-19 A 18-Dec-19 A
DE CONCEPT-050 Finalize concepts for peer review 21 0 100% 19-Dec-19 A 29-Jan-20 A
DE CONCEPT-060 1st Peer Review: final concept Selection follow-up 8 0 100% 30-Jan-20 A 06-Feb-20 A
DE CONCEPT-070 ***D.E. PEER REVIEW #1(48) 1 0 100% 30-Jan-20 A 30-Jan-20 A
DE CONCEPT-080 Develop final concept (Draft Final Concept) 31 0 100% 31-Jan-20 A 10-Mar-20 A
DE CONCEPT-090 Final Concept CMa cost estimating 11 0 100% 25-Feb-20 A 10-Mar-20 A
DE CONCEPT-100 CBP & GSA Review & Cost Reconciliation before Peer Review 2 16 0 100% 11-Mar-20 A 13-Mar-20 A
DE CONCEPT-110 Final Concept Peer Review follow-up (Final Concept) 6 0 100% 17-Mar-20 A 01-Apr-20 A
DE CONCEPT-120 ***D.E. PEER REVIEW #2(49) 1 0 100% 16-Mar-20 A 16-Mar-20 A
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
2020 2021
03-Mar-20 A, BEAN BACKFILL.1.2.2.1.2.1 Design Contract Mobilization
12-Jun-20 A, BEAN BACKFILL.1.2.2.1.2.3 D.E. Concept Phase
CBP & GSA Review & Cost Reconciliation before Peer Review 2
Final Concept Peer Review follow-up (Final Concept)
BEAN BACKFILL: CBP USMC Master Schedule Classic Schedule Layout 17-Jun-20 16:29
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Remaining
Duration
Schedule %
Complete
Start Finish
DE CONCEPT-130 Finalize concept submission requirements 21 0 100% 02-Apr-20 A 11-Jun-20 A
DE CONCEPT-140 Concept Design Revisions & clarification following comm. presentation 0 0 0% 12-Jun-20 A 12-Jun-20 A
DE CONCEPT-150 Commissioner's Presentation 1 0 0% 12-Jun-20 A 12-Jun-20 A
DE CONCEPT-160 P-120 Desgin Schedule Contingency: Concept Phase 0 0 0% 12-Jun-20 A 12-Jun-20 A
DE CONCEPT-170 ***CONCEPT DESIGN APPROVAL COMPLETE (22) 0 0 0% 12-Jun-20 A 12-Jun-20 A
BEAN BACKFILL.1.2.2.1.2.4 Design Development: CBP & USMCBEAN BACKFILL.1.2.2.1.2.4 Design Development: CBP & USMC 182 182 0% 15-Jun-20 A 25-Feb-21
DE DVLP-010 Prepare 35% DD submission 60 60 0% 15-Jun-20 A 08-Sep-20
DE DVLP-020 35% Design Development Submission 0 0 0% 08-Sep-20 08-Sep-20
DE DVLP-030 35% DD IDR/comments/Reconciliation/Corrections 25 25 0% 08-Sep-20 12-Oct-20
DE DVLP-040 35% DD Cost Estimating (CMa) 15 15 0% 08-Sep-20 28-Sep-20
DE DVLP-050 Prepare 50% Design Development Submission 25 25 0% 18-Dec-20 21-Jan-21
DE DVLP-060 50% Design Development Submission 0 0 0% 22-Jan-21 22-Jan-21
DE DVLP-070 50% DD IDR/comments/Reconciliation 25 25 0% 22-Jan-21 25-Feb-21
DE DVLP-080 50% DD Cost Estimating 15 15 0% 22-Jan-21 11-Feb-21
DE DVLP-090 P-120 Design Schedule Contingency: DD Phase 0 0 0% 12-Feb-21 12-Feb-21
DE DVLP-100 ***REQUIREMENTS FINALIZED (03) 0 0 0% 12-Feb-21 12-Feb-21
BEAN BACKFILL.1.2.2.1.2.5 Construction DocumentsBEAN BACKFILL.1.2.2.1.2.5 Construction Documents 125 125 0% 01-Mar-21 23-Aug-21
DE CD-010 Prepare 75% Construction Documents 25 25 0% 01-Mar-21 02-Apr-21
DE CD-020 75% CD Cost Estimating (CMa & CMc) 15 15 0% 05-Apr-21 23-Apr-21
DE CD-030 Submit 75% CD's 0 0 0% 05-Apr-21 05-Apr-21
DE CD-040 75% CD IDR/comments/Reconciliation 20 20 0% 05-Apr-21 30-Apr-21
DE CD-050 Prepare 90% Construction Documents 25 25 0% 03-May-21 04-Jun-21
DE CD-060 ***90% CONSTRUCTION DOCUMENTS SUBMISSION (52) 0 0 0% 07-Jun-21 07-Jun-21
DE CD-070 90% CD IDR/comments/Reconciliation 20 20 0% 07-Jun-21 02-Jul-21
DE CD-080 90% CD Cost Estimating (A/E & CMc) 15 15 0% 07-Jun-21 25-Jun-21
DE CD-090 Prepare 100% Construction Documents 15 15 0% 05-Jul-21 23-Jul-21
DE CD-100 100% CD IDR/Final Changes/Reconciliation 20 20 0% 26-Jul-21 20-Aug-21
DE CD-110 Submit 100% CD's 0 0 0% 26-Jul-21 26-Jul-21
DE CD-120 100% CD Cost Estimating (A/E & CMc) 10 10 0% 26-Jul-21 06-Aug-21
DE CD-130 P-120 Design Schedule Contingency: CD Phase 0 0 0% 23-Aug-21 23-Aug-21
DE CD-140 ***DESIGN COMPLETE 0 0 0% 23-Aug-21 23-Aug-21
BEAN BACKFILL.1.2.2.1.3 Create Building Design StandardBEAN BACKFILL.1.2.2.1.3 Create Building Design Standard 199 142 0% 16-Aug-19 A 01-Jan-21
DS-010 Develop Enhanced/ Concept Phase BDS for USMC (Tenant areas focus) 122 52 46.72% 16-Aug-19 A 27-Aug-20
DS-020 Concept Design Phase Tenant Space BDS Completed 0 0 0% 28-Aug-20 28-Aug-20
DS-030 Finish BDS for Bean Center (Common areas focus) 90 90 0% 28-Aug-20 31-Dec-20
DS-040 BDS Completed 0 0 0% 01-Jan-21 01-Jan-21
BEAN BACKFILL.1.2.2.3 USMC Contract ModificationBEAN BACKFILL.1.2.2.3 USMC Contract Modification 18 18 0% 31-Jul-20 25-Aug-20
BEAN BACKFILL.1.2.2.3.1 USMC Contract ModificationBEAN BACKFILL.1.2.2.3.1 USMC Contract Modification 18 18 0% 31-Jul-20 25-Aug-20
PROCURE-USMC-010 Allowance Request for USMC Design Options 12 12 0% 31-Jul-20* 17-Aug-20
PROCURE-USMC-020 Prepare & exercise modification for USMC Design Options 15 15 0% 03-Aug-20 24-Aug-20
PROCURE-USMC-030 PR routed & approved for USMC Design Options 6 6 0% 18-Aug-20 25-Aug-20
BEAN BACKFILL.1.2.2.2 Design Execution for USMCBEAN BACKFILL.1.2.2.2 Design Execution for USMC 190 133 0% 27-Jan-20 A 18-Dec-20
BEAN BACKFILL.1.2.2.2.5 Program Development for USMCBEAN BACKFILL.1.2.2.2.5 Program Development for USMC 110 32 0% 27-Jan-20 A 30-Jul-20
PD-USMC-010 Allowance request for POR Option 10 0 100% 27-Jan-20 A 10-Feb-20 A
PD-USMC-020 Prepare and exacute modification for POR 10 0 100% 11-Feb-20 A 28-Feb-20 A
PD-USMC-030 Prepare USMC POR & Space Requirements Report 100 32 47% 11-Mar-20 A 30-Jul-20
PD-USMC-040 Obtain final POR approvals from USMC, NAVFAC, GSA 30 30 0% 17-Jun-20 28-Jul-20
PD-USMC-050 USMC POR Completed 1 1 0% 29-Jul-20 29-Jul-20
BEAN BACKFILL.1.2.2.2.1 Concept Design: USMCBEAN BACKFILL.1.2.2.2.1 Concept Design: USMC 85 85 0% 24-Aug-20 18-Dec-20
CONCEPT-USMC-010 Fit USMC Program into USMC Footprint 40 40 0% 24-Aug-20 16-Oct-20
CONCEPT-USMC-020 USMC & GSA Reviews & Approvals for USMC Concept Design 15 15 0% 19-Oct-20 06-Nov-20
CONCEPT-USMC-030 Finalize USMC Concept Design 16 16 0% 06-Nov-20 27-Nov-20
CONCEPT-USMC-040 Final Review & approvals for SMC Concept Design 16 16 0% 27-Nov-20 18-Dec-20
CONCEPT-USMC-050 P-120 Design Schedule Contingency: USMC Concepts 0 0 0% 18-Dec-20 18-Dec-20
CONCEPT-USMC-060 Finish Concept Design: USMC 0 0 0% 18-Dec-20 18-Dec-20
BEAN BACKFILL.1.2.3 CMa Procurement (Includes CXa)BEAN BACKFILL.1.2.3 CMa Procurement (Includes CXa) 218 0 0% 15-Feb-18 A 16-May-19 A
CMa-PROCURE-010 Prepare CMa SOW, RFP 175 0 32.57% 15-Feb-18 A 17-Oct-18 A
CMa-PROCURE-020 Write & approve CMa Acquisition Plan 17 0 100% 15-Feb-18 A 09-Mar-18 A
CMa-PROCURE-030 Initiate & Route PR for CMa FSS Soliciation (FNA) 8 0 0% 02-Oct-18 A 11-Oct-18 A
CMa-PROCURE-040 Solicit CMa Procurement (FSS procurement) 34 0 0% 30-Oct-18 A 14-Dec-18 A
CMa-PROCURE-050 CMa proposals received 1 0 0% 14-Dec-18 A 14-Dec-18 A
CMa-PROCURE-060 Government Shutdown 16 0 100% 07-Jan-19 A 28-Jan-19 A
CMa-PROCURE-070 Evaluate & Negotiate CMa proposals 20 0 100% 22-Jan-19 A 18-Feb-19 A
CMa-PROCURE-080 AMD prepares CMs contract file & award documents 50 0 74% 19-Feb-19 A 29-Apr-19 A
CMa-PROCURE-090 Process CMa award allowance request 16 0 100% 17-Apr-19 A 08-May-19 A
CMa-PROCURE-100 PR routed & approved for CMa award 7 0 0% 08-May-19 A 16-May-19 A
CMa-PROCURE-110 CMa CONTRACT AWARD (24) 1 0 0% 16-May-19 A 16-May-19 A
CMa-PROCURE-120 CXa AWARD (25) 1 0 0% 16-May-19 A 16-May-19 A
BEAN BACKFILL.1.2.5 CUSTOMER CONCURRENCE-FINAL SCOPE/SCHDL/COST Tenant A: (42)BEAN BACKFILL.1.2.5 CUSTOMER CONCURRENCE-FINAL SCOPE/SCHDL/COST Tenant A: (42) 1 1 0% 30-Jul-20 30-Jul-20
FS-010 CUSTOMER CONCURRENCE-FINAL SCOPE/SCHDL/COST Tenant A: (42) 1 1 0% 30-Jul-20 30-Jul-20
BEAN BACKFILL.1.6 Execution PhaseBEAN BACKFILL.1.6 Execution Phase 1070 1013 0% 01-Jun-17 A 06-May-24
BEAN BACKFILL.1.6.1 Art in Architecture ProcurementBEAN BACKFILL.1.6.1 Art in Architecture Procurement 160 0 0% 01-Jun-17 A 24-Jun-19 A
AAP-010 Initiate AiA contract planning & outreach to 2012 artist 57 0 100% 01-Jun-17 A 18-Aug-17 A
AAP-020 Prepare AiA SOW, RFP & IGCE 62 0 67.74% 20-Dec-17 A 15-Mar-18 A
AAP-030 Write & approve AiA Sole Source Justification 15 0 100% 10-Jan-18 A 30-Jan-18 A
AAP-040 AIA CUSTOMER MEETING 1 (53) 1 0 100% 30-Jan-18 A 30-Jan-18 A
AAP-050 AIA CUSTOMER MEETING 2 (54) 1 0 100% 30-Jan-18 A 30-Jan-18 A
AAP-060 AIA CUSTOMER MEETING 4 (56) 1 0 100% 30-Jan-18 A 30-Jan-18 A
AAP-070 AIA CUSTOMER MEETING 5 (57) 1 0 100% 30-Jan-18 A 30-Jan-18 A
AAP-080 Finalize & Approve AiA OFOC 18 0 100% 15-Jun-18 A 10-Jul-18 A
AAP-090 GSA prepares AiA contract SOW and proposal pricing 45 0 53.33% 11-Jul-18 A 11-Sep-18 A
AAP-100 Issue AiA RFP/ proposed contract for artist review 1 0 0% 11-Sep-18 A 11-Sep-18 A
AAP-110 Artist engagement Contract negotiations 25 0 0% 12-Sep-18 A 16-Oct-18 A
AAP-120 AiA Proposed contract agreement 1 0 0% 01-Nov-18 A 01-Nov-18 A
AAP-130 Finalize AiA contract file & award documents 21 0 0% 01-Apr-19 A 29-Apr-19 A
AAP-140 Process AiA Allowance Request 11 0 0% 23-Apr-19 A 07-May-19 A
AAP-150 Route AiA PR for approval 5 0 0% 07-May-19 A 13-May-19 A
AAP-160 AiA CONTRACT AWARD (26) 1 0 0% 13-May-19 A 13-May-19 A
AAP-170 AiA Clearances & Mobilization 31 0 0% 13-May-19 A 24-Jun-19 A
AAP-180 FBO Posting of AiA Selection 15 0 0% 14-May-19 A 03-Jun-19 A
BEAN BACKFILL.1.6.2 CMc ProcurementBEAN BACKFILL.1.6.2 CMc Procurement 626 569 0% 28-Jan-20 A 23-Aug-22
BEAN BACKFILL.1.6.3 Construction PhaseBEAN BACKFILL.1.6.3 Construction Phase 444 444 0% 23-Aug-22 06-May-24
BEAN BACKFILL.1.6.3.1 Construction MobilizatonBEAN BACKFILL.1.6.3.1 Construction Mobilizaton 50 50 0% 23-Aug-22 31-Oct-22
CM-010 CMc execute subcontracts & remaining subcontractor clearances 30 30 0% 23-Aug-22 03-Oct-22
CM-020 Preconstruction Submittals 40 40 0% 06-Sep-22 31-Oct-22
CM-040 ***ISSUE ON SITE NTP (11) 0 0 0% 04-Oct-22 04-Oct-22
BEAN BACKFILL.1.6.3.2 ConstructIon (CBP & USMC)BEAN BACKFILL.1.6.3.2 ConstructIon (CBP & USMC) 414 414 0% 04-Oct-22 06-May-24
C-CBP-010 Construction / Build-Out for CBP & USMC 344 344 0% 04-Oct-22 26-Jan-24
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
2020 2021
Finalize concept submission requirements
Concept Design Revisions & clarification following comm. presentation
Commissioner's Presentation
P-120 Desgin Schedule Contingency: Concept Phase
***CONCEPT DESIGN APPROVAL COMPLETE (22)
25-Feb-21, BEAN BACKFILL.1.2.2.1.2.4 Design Development: CBP & USMC
Prepare 35% DD submission
35% Design Development Submission
35% DD IDR/comments/Reconciliation/Corrections
35% DD Cost Estimating (CMa)
Prepare 50% Design Development Submission
50% Design Development Submission
50% DD IDR/comments/Reconciliation
50% DD Cost Estimating
P-120 Design Schedule Contingency: DD Phase
***REQUIREMENTS FINALIZED (03)
Prepare 75% Construction Documents
75% CD Cost Estimating (CMa & CMc)
Submit 75% CD's
75% CD IDR/comments/Reconciliation
Prepare 90% Construction Documents
***90% CONSTRUCTION DOCUMENTS SUBMISSION (52)
90% CD IDR/comments/Reconciliation
90% CD Cost Estimating (A/E & CMc)
01-Jan-21, BEAN BACKFILL.1.2.2.1.3 Create Building Design Standard
Develop Enhanced/ Concept Phase BDS for USMC (Tenant areas focus)
Concept Design Phase Tenant Space BDS Completed
Finish BDS for Bean Center (Common areas focus)
BDS Completed
25-Aug-20, BEAN BACKFILL.1.2.2.3 USMC Contract Modification
25-Aug-20, BEAN BACKFILL.1.2.2.3.1 USMC Contract Modification
Allowance Request for USMC Design Options
Prepare & exercise modification for USMC Design Options
PR routed & approved for USMC Design Options
18-Dec-20, BEAN BACKFILL.1.2.2.2 Design Execution for USMC
30-Jul-20, BEAN BACKFILL.1.2.2.2.5 Program Development for USMC
Prepare USMC POR & Space Requirements Report
Obtain final POR approvals from USMC, NAVFAC, GSA
USMC POR Completed
18-Dec-20, BEAN BACKFILL.1.2.2.2.1 Concept Design: USMC
Fit USMC Program into USMC Footprint
USMC & GSA Reviews & Approvals for USMC Concept Design
Finalize USMC Concept Design
Final Review & approvals for SMC Concept Design
P-120 Design Schedule Contingency: USMC Concepts
Finish Concept Design: USMC
30-Jul-20, BEAN BACKFILL.1.2.5 CUSTOMER CONCURRENCE-FINAL SCOPE/SCHDL/COST Tenant A: (42)
CUSTOMER CONCURRENCE-FINAL SCOPE/SCHDL/COST Tenant A: (42)
BEAN BACKFILL: CBP USMC Master Schedule Classic Schedule Layout 17-Jun-20 16:29
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 2 of 3 TASK filter: All Activities
Remaining
Duration
Schedule %
Complete
Start Finish
C-CBP-020 CONSTRUCTION PEER REVIEW 15% 0 0 0% 07-Feb-23 07-Feb-23
C-CBP-030 CONSTRUCTION PEER REVIEW 65% 0 0 0% 14-Aug-23 14-Aug-23
C-CBP-040 CONSTRUCTION PEER REVIEW 95% 0 0 0% 06-Nov-23 06-Nov-23
C-CBP-050 P-120 Schedule Contingency: Construction 30 30 0% 29-Jan-24 08-Mar-24
C-CBP-060 ***PREOCCUPANCY TENENT ACCESS - Tenant A (12) 0 0 0% 11-Mar-24 11-Mar-24
C-CBP-070 Punchlist & Commission 40 40 0% 11-Mar-24 03-May-24
C-CBP-080 Construction Complete 0 0 0% 06-May-24 06-May-24
BEAN BACKFILL.1.6.3.4 ALL CONSTRUCTION SUBSTANTIALLY COMPLETEBEAN BACKFILL.1.6.3.4 ALL CONSTRUCTION SUBSTANTIALLY COMPLETE 0 0 0% 06-May-24 06-May-24
SC-010 ***ALL CONSTRUCTION SUBSTANTIALLY COMPLETE (13) 0 0 0% 06-May-24 06-May-24
BEAN BACKFILL.1.4 Close Out & Occupancy PhaseBEAN BACKFILL.1.4 Close Out & Occupancy Phase 1078 1078 0% 17-Jun-20 05-Aug-24
CO-OPH-010 Prepare & execute USMC Move Services BPA Order 40 40 0% 19-Oct-23 13-Dec-23
CO-OPH-020 MOVE-IN: USMC 60 60 0% 17-Jun-20 08-Sep-20
CO-OPH-030 Prepare & execute CBP Move Services BPA Order 40 40 0% 01-Sep-23 26-Oct-23
CO-OPH-040 MOVE-IN: CBP 60 60 0% 11-Mar-24 31-May-24
CO-OPH-050 Close-Out Contracts and RWA's 65 65 0% 06-May-24 02-Aug-24
CO-OPH-060 ***CONSTRUCTION COMPLETE (20) 0 0 0% 06-May-24 06-May-24
CO-OPH-070 ***RENT START/ finalize all OA's (14) 0 0 0% 03-Jun-24 03-Jun-24
CO-OPH-080 ***TENANT OCCUPANCY (15) 0 0 0% 03-Jun-24 03-Jun-24
CO-OPH-090 ***PROJECT COMPLETE (27) 0 0 0% 05-Aug-24 05-Aug-24
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
2020 2021
MOVE-IN: USMC
BEAN BACKFILL: CBP USMC Master Schedule Classic Schedule Layout 17-Jun-20 16:29
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone summary
Page 3 of 3 TASK filter: All Activities
| Amendment 002 - SF30 |
| MGEJB Backfill Master Schedule Update 2020 June 17 |