Q_and_A_Part_3_-_Flint_Saginaw_O&M.pdf

PDF 110 KB Posted

Attached to
Operations and Maintenance, Flint and Saginaw Federal contract opportunity
Solicitation number
47PF0018R0040
Issued by
General Services Administration Public Buildings Service Region 5

About this file

Question-and-Answer document, Part 3

View the file

Other files for this federal contract opportunity

Other files attached to Operations and Maintenance, Flint and Saginaw, newest first.
File Type Posted
Solicitation_Amendment_0003.pdf PDF
47PF0018R0040__Amendment0002.pdf PDF
Q_and_A_Part_2_-_Flint_Saginaw_O&M.pdf PDF
Sign_In_2.pdf PDF
Sign_In_3.pdf PDF
Sign_In_1.pdf PDF
Deka-Unigy_High_Rate_Series_HR3500.pdf PDF
Q_and_A_-_published_to_FBO.pdf PDF
PreproposalMinutes.pdf PDF
Amendment_47PF0018R0040_0001.pdf PDF
Solicitation_47PF0018R0040.pdf PDF
Attachment_1_Cost_Wksht.xls XLS spreadsheet
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions-And-Answers, Part 3 Solicitation 47PF0018R0040

Operation and Maintenance at the United States Federal Building in Flint, MI and the Social Security Administration facility in Saginaw, MI

The following questions were submitted to the Contract Specialist on May 16, 2018:

Q56: 1. Regarding Switchgear tests. The J.5.Building Information Sheets for Saginaw and Flint indicate Switchgear testing is not applicable (N/A). Please confirm this is true for the duration of the contract as we do not see this covered in the solicitation.

A56: Thank you for your question. Amendment 0003 makes corrections to Section J.5 - Building Information Sheets. These tests are applicable for the Flint location. Please refer to that Amendment. Please also note that the Building Information Sheet contains the anniversary dates of tests, but that the work requirements for the incoming contract are found in Section C of the Solicitation. Contractors are responsible for ensuring that they are compliant with Section C as well as all applicable codes and regulations pertaining to building maintenance, including electrical work.

Q57: Regarding Past Performance References which are requested as part of the document submission when forwarding the proposal. H.1.2 GSAR 552.237-70 suggests a narrative statement with experience would be acceptable as opposed to the samples on page 229. It refers to individuals now or recently engaged in the performance of building services A56: Section H.1.2 is not an Evaluation Factor for this particular award and is not a substitute for Past Performance. Past Performance is an Evaluation Factor, per Section M.4 of the Solicitation. Past Performance references, submitted on Attachment A, are still a requirement for this procurement. Offerors without 3 relevant past performance examples shall be rated “Neutral,” per Section M.4 of the Solicitation. Please refer to the Solicitation Sections L and M for a description of the submission and evaluation requirements.