This document is a comprehensive set of Special Provisions for the Florin Road Bicycle and Pedestrian Improvement Project, issued by the County of Sacramento's Department of Transportation. The project involves federally funded infrastructure improvements along Florin Road, with bids scheduled to open on June 27, 2024. The scope of work includes clearing and grubbing, roadway excavation, aggregate base installation, concrete curb and sidewalk construction, drainage pipe and structure work, landscape and irrigation reconstruction, traffic signal modifications, street light installation, pavement grinding, asphalt paving, slurry sealing, traffic striping, and roadside signing. The contract duration is set at 200 working days, with a total project area spanning multiple roadways and intersections in Sacramento County.

The project has a Disadvantaged Business Enterprise (DBE) goal of 21.0% and requires specific federal compliance measures, including Davis-Bacon wage rates and equal employment opportunity provisions. Funding appears to be a combination of federal and local sources, with specific attention to procurement requirements such as Buy America regulations and warm mix asphalt technologies. The contract includes provisions for precise material specifications, quality control testing, and environmental controls, with an estimated project value implied through the detailed technical specifications. The County will use an electronic procurement system for bid submissions, and bidders must provide extensive documentation including DBE commitment forms, good faith efforts documentation, and detailed construction plans.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COUNTY OF SACRAMENTO

COMMUNITY SERVICES AGENCY

DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISIONS

FOR:

FLORIN ROAD

BICYCLE AND PEDESTRIAN IMPROVEMENT

PROJECT

FEDERAL AID PROJECT

HSIPL 5924(235)

CONTRACT NO. 4526

NOTE: THE COUNTY OF SACRAMENTO 2016 STANDARD CONSTRUCTION SPECIFICATIONS, REVISED

MAY 1, 2023 AND THE STATE OF CALIFORNIA DEPARTMENT ON TRANSPORTATION STANDARD

SPECIFICATIONS DATED 2023 ARE HEREBY MADE PART OF THESE SPECIFICATIONS. A COPY OF THE SACRAMENTO STANDARD CONSTRUCTION SPECIFICATIONS MAY BE DOWNLOADED FROM THE COUNTY

WEBSITE AT HTTPS://SACCOUNTYSPECS.SACCOUNTY.GOV

Bids Open: JUNE 27, 2024

DAVID DEFANTI, CONTRACT NO. 4526

Deputy County Executive DATE: OCTOBER 19, 2021

RON E. VICARI, Director Department of Transportation

CONTRACT No. 4526 SPECIAL PROVISIONS

FLORIN ROAD BICYCLE AND PEDESTRIAN IMPROVEMENT PROJECT

THE SPECIAL PROVISIONS CONTAINED HEREIN HAVE BEEN PREPARED BY OR

UNDER THE DIRECTION OF THE FOLLOWING REGISTERED PEOPLE:

ROADWAY & ELECTRICAL:

SIGNED: 5-724

Anthony L. Voo, PE Date

Registered Civil Engineer No. 46313 Exp. December 31,2024

LANDSCAPE:

SIGNED:

Henry Yasui, LS SacDOT Senior Landscape Architect Registered Landscape Architect No. 2746 Exp. November30,2025

APPROVED:

SIGNED:

Spencer E. Ord, PE, TE, QSD SacDOT Senior Civil Engineer Registered Civil Engineer No. 89082 Exp. September30,2A24

Date

Date

*i. ..'*

M;i"iiiM

#lt"t;%

-: PLA2746 :-

*i. ..,* \k;;*-v

6,--T.TIfXe%\.,.:3.;q- 'b".7- Ha caeo82

-lH *i. .j*

\k;ffiiii-q/

5/7/24

EXP DATE: 11/2025

PLA

SIGNED: _________________________ _____________

Spencer E. Ord, PE, TE, QSD Date SacDOT Senior Civil Engineer Registered Civil Engineer No. 89082 Exp. September 30, 2024

5/7/24 i

TABLE OF CONTENTS

SPECIAL PROVISIONS .................................................................................................................................. - 1 - SECTION 1 - TERMS AND DEFINITIONS .................................................................................................. - 1 - 1-1 GENERAL ................................................................................................................................... - 1 -

1-1.01 STATE STANDARD PLANS LIST ...................................................................................................... - 1 -

SECTION 2 - BID REQUIREMENTS AND CONDITIONS ........................................................................ - 3 - 2-1 BID PROPOSAL ......................................................................................................................... - 3 - 2-2 PREPARATION AND SUBMISSION OF BIDS ........................................................................ - 3 -

2-5 CONTRACTORS/SUBCONTRACTORS REQUIRED TO BE LICENSED & REGISTERED - 3 -

2-8 SUBCONTRACTORS ................................................................................................................. - 3 -

2-8.01 BIDDER’S LIST OF SUBCONTRACTORS (DBE AND NON-DBE) ........................................................ - 4 - 2-8.02 FHWA FORM 1273 REQUIRED FEDERAL-AID CONTRACT PROVISIONS ........................................ - 4 -

2-9 ADDENDA .................................................................................................................................. - 4 - 2-11 BID GUARANTEE ..................................................................................................................... - 4 - 2-12 WITHDRAWAL OF BID ............................................................................................................ - 5 - 2-13 PUBLIC OPENING OF BIDS ..................................................................................................... - 5 - 2-16 DISADVANTAGED BUSINESS ENTERPRISES (DBE) ......................................................... - 5 -

2-16.01 DBE GOAL FOR THIS PROJECT ...................................................................................................... - 6 - 2-16.02 DBE SUBMITTAL ADDRESS ........................................................................................................... - 6 - 2-16.03 NONDISCRIMINATION STATEMENT ............................................................................................. - 7 - 2-16.04 CONTRACT ASSURANCE ............................................................................................................... - 7 - 2-16.05 PROMPT PROGRESS PAYMENT .................................................................................................... - 7 - 2-16.07 TERMINATION AND REPLACEMENT OF DBE SUBCONTRACTORS ................................................ - 8 - 2-16.08 COMMITMENT AND UTILIZATION .............................................................................................. - 10 - 2-16.09 GOOD FAITH EFFORTS SUBMITTAL ........................................................................................... - 11 - 2-16.11 COMMERCIALLY USEFUL FUNCTION .......................................................................................... - 12 - 2-16.12 USE OF JOINT CHECKS ................................................................................................................ - 14 -

2-17 FEMALE AND MINORITY GOALS ....................................................................................... - 14 - 2-18 BID RIGGING ........................................................................................................................... - 14 - 2-19 TITLE VI ASSURANCES ......................................................................................................... - 15 - 2-20 SACRAMENTO HOUSING REDEVELOPMENT AGENCY (SHRA) .................................. - 16 - SECTION 3 - AWARD AND EXECUTION OF CONTRACT ................................................................... - 18 - 3-3 AWARD OF CONTRACT ........................................................................................................ - 18 - 3-7 EXECUTION OF THE CONTRACT ........................................................................................ - 18 -

3-7.01 BID ALTERNATIVES ..................................................................................................................... - 18 - 3-9 INSURANCE ............................................................................................................................. - 18 - 3-10 ESCROW BID DOCUMENTS .................................................................................................. - 19 -

3-10.06 EXAMINATION ............................................................................................................................ - 19 -

SECTION 4 - SCOPE OF WORK ................................................................................................................. - 21 - 4-11 LANDS AND RIGHTS-OF-WAY ............................................................................................ - 21 - 4-13 DESCRIPTION OF WORK ....................................................................................................... - 21 - SECTION 5 - CONTROL OF WORK AND MATERIALS ........................................................................ - 22 - 5-5 COOPERATION WITH OTHER ENTITIES ............................................................................ - 22 -ii

5-6 CONTRACTOR’S DISMISSAL OF UNSATISFACTORY EMPLOYEES ............................. - 22 - 5-8 CONTRACTOR’S SUBMITTALS ........................................................................................... - 22 -

5-8.01 SUBMITTAL – RECOVERED ORGANIC WASTE PRODUCTS .......................................................... - 22 - 5-9 SURVEYS ................................................................................................................................. - 23 -

5-9.01 AGENCY-FURNISHED SURVEYS ................................................................................................... - 23 - 5-9.02 SURVEY MONUMENTS – AGENCY FURNISHED SURVEYS ........................................................... - 25 -

5-14 SUBSTITUTIONS ..................................................................................................................... - 25 - 5-16 MATERIALS SAMPLING AND TESTING ............................................................................. - 26 -

5-16.01 CONTROL OF MATERIALS ........................................................................................................... - 26 - 5-21 TEMPORARY SUSPENSION OR DELAY OF WORK .......................................................... - 26 - 5-24 BUY AMERICA ........................................................................................................................ - 27 - 5-25 USE OF UNITED STATES FLAG VESSELS (CARGO PREFERENCE ACT) ...................... - 28 -

5-26 PROHIBITION OF CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE

EQUIPMENT AND SERVICES ....................................................................................................................... - 28 - SECTION 6 - LEGAL RELATIONS AND RESPONSIBILITIES ............................................................. - 30 - 6-1 COMPLIANCE WITH LAWS AND REGULATIONS ............................................................ - 30 -

6-1.02 PREVAILING WAGE ..................................................................................................................... - 30 - 6-1.04 NONDISCRIMINATION ................................................................................................................ - 30 - 6-1.14 LABOR COMPLIANCE POSTERS .................................................................................................. - 30 -

6-10 PERMITS, AND LICENSES, AND CERTIFICATIONS ......................................................... - 31 - 6-10.08 ENCROACHMENT PERMITS ........................................................................................................ - 32 -

6-11 EXISTING UTILITIES.............................................................................................................. - 32 - 6-15 FEDERAL TRAINEE PROGRAM ........................................................................................... - 33 - 6-16 RELATIONS WITH SACRAMENTO AREA SEWER DISTRICT (SASD) ........................... - 35 - 6-17 RELATIONS WITH CALTRANS ............................................................................................ - 37 - SECTION 7 - PROSECUTION OF THE WORK ........................................................................................ - 38 - 7-1 BEGINNING OF WORK .......................................................................................................... - 38 -

7-1.01 ORDER OF WORK ........................................................................................................................ - 38 - 7-6 UNUSUAL SITE CONDITIONS .............................................................................................. - 39 - 7-8 PEAK HOURS, HOURS OF DARKNESS, HOLIDAYS, AND WEEKEND ........................... - 39 -

7-8.01 ALLOWABLE TIMES AND HOURS OF WORK ............................................................................... - 39 - 7-8.02 OFF-PERIOD WORK .................................................................................................................... - 39 -

7-12 DELAYS .................................................................................................................................... - 39 - 7-15 TIME OF COMPLETION ......................................................................................................... - 40 - SECTION 8 - MEASUREMENT AND PAYMENT..................................................................................... - 41 - 8-2 SCOPE OF PAYMENT ............................................................................................................. - 41 -

8-2.02 UNIT PRICE CONTRACT ............................................................................................................... - 41 - 8-5 PROGRESS PAYMENT PROCEDURES ................................................................................. - 41 - 8-10 LIQUIDATED DAMAGES FOR DELAY ................................................................................ - 41 - SECTION 9 - CHANGES AND CLAIMS ..................................................................................................... - 42 - 9-24 SIGNIFICANT CHANGES IN THE CHARACTER OF WORK ............................................. - 42 - SECTION 10 - ENVIRONMENTAL CONTROLS AT WORK SITE ....................................................... - 43 - 10-4 EROSION, SEDIMENT, AND WATER POLLUTION CONTROL ........................................ - 43 -

10-4.04 STORMWATER POLLUTION PREVENTION PLAN (SWPPP) .......................................................... - 43 - 10-4.09 PAYMENT ................................................................................................................................... - 44 -iii

10-4.10 BMP SCHEDULE OF VALUES ....................................................................................................... - 44 - 10-7 CONTAMINATED OR HAZARDOUS MATERIALS ............................................................ - 46 -

10-7.01 AERIALLY DEPOSITED LEAD ........................................................................................................ - 46 - 10-9 SANITARY REGULATIONS ................................................................................................... - 46 - 10-13 PROTECTION OF EXISTING TREES ..................................................................................... - 47 -

10-13.01 ARBORIST SERVICES ................................................................................................................... - 48 -

SECTION 11 - PRECONSTRUCTION PHOTOGRAPHS AND RECORD DRAWINGS ..................... - 50 - 11-2 PRECONSTRUCTION PHOTOGRAPHS ................................................................................ - 50 - 11-4 MEASUREMENT AND PAYMENT ........................................................................................ - 50 - SECTION 12 - SAFETY, PUBLIC CONVENIENCE, AND TRAFFIC CONTROL ............................... - 51 - 12-1 SAFETY .................................................................................................................................... - 51 -

12-1.09.E LEAD COMPLIANCE PLAN ........................................................................................................... - 51 - 12-2 PUBLIC CONVENIENCE AND SAFETY ............................................................................... - 51 -

12-2.02 PEDESTRIAN AND BICYCLIST ACCESS .......................................................................................... - 51 - 12-2.04 ACCESS TO DRIVEWAYS, HOUSES, AND BUILDINGS ................................................................... - 52 -

12-3 PUBLIC SAFETY AND TRAFFIC CONTROL ....................................................................... - 52 - 12-3.04 FURNISHING, INSTALLING, AND MAINTAINING TEMPORARY TRAFFIC CONTROLS ................... - 52 - 12-3.07 CONSTRUCTION SIGNS ............................................................................................................... - 53 - 12-3.14 PORTABLE CHANGEABLE MESSAGE SIGNS ................................................................................. - 54 - 12-3.16 TEMPORARY PAVEMENT DELINEATION ..................................................................................... - 54 -

12-4 TRAFFIC CONTROL PLANS .................................................................................................. - 55 - SECTION 13 - EXISTING FACILITIES ...................................................................................................... - 58 - 13-1 GENERAL ................................................................................................................................. - 58 -

13-1.03 TEMPORARY CONSTRUCTION EASEMENTS ................................................................................ - 58 - 13-2 REMOVING EXISTING FACILITIES ..................................................................................... - 58 -

13-2.04 LANDSCAPING IMPROVEMENTS ................................................................................................ - 58 - 13-2.05 ABANDONED UNDERGROUND FACILITIES ................................................................................. - 59 - 13-2.06 DRAINAGE FACILITIES ................................................................................................................. - 59 - 13-2.09 REMOVAL OF TRAFFIC STRIPES AND PAVEMENT MARKINGS .................................................... - 59 -

13-3 MEASUREMENT AND PAYMENT ........................................................................................ - 59 - 13-4 ADJUST UTILITY BOX/VAULT TO GRADE ........................................................................ - 60 - SECTION 14 - RESTORATION OF SURFACES ....................................................................................... - 61 - 14-3 STREETS AND PARKING LOTS ............................................................................................ - 61 -

14-3.04.A SLURRY SEAL (TYPE 2) ................................................................................................................ - 61 - 14-7 MEASUREMENT AND PAYMENT ........................................................................................ - 63 - SECTION 15 - CLEARING AND GRUBBING ........................................................................................... - 64 - 15-1 GENERAL ................................................................................................................................. - 64 -

15-1.02 TREES, SHRUBS, GROUND COVER, AND LAWNS ........................................................................ - 64 - 15-1.06 MISCELLANEOUS ........................................................................................................................ - 64 -

15-2 PAYMENT ................................................................................................................................ - 65 - SECTION 18 - EARTHWORK ...................................................................................................................... - 66 - 18-2 ROADWAY EXCAVATION .................................................................................................... - 66 - 18-5 UNSUITABLE MATERIAL EXCAVATION .......................................................................... - 66 -iv

18-5.03 STABILIZATION FABRIC ............................................................................................................... - 66 -

SECTION 20 – LANDSCAPING ................................................................................................................... - 70 - 20-1 GENERAL ................................................................................................................................. - 70 -

20-1.01 LANDSCAPING SUBMITTALS ....................................................................................................... - 70 - 20-1.02 COORDINATION .......................................................................................................................... - 70 - 20-1.03 REPAIR AND REPLACE EXISTING LANDSCAPE ............................................................................. - 71 - 20-1.04 ADDITION TO EXISTING LANDSCAPE (5504 & 5601 FLORIN ROAD) ........................................... - 72 - 20-2.02 TOPSOIL ...................................................................................................................................... - 73 - 20-2.05 BARK MULCH .............................................................................................................................. - 74 - 20-4.02 PREPARING PLANTING AREAS .................................................................................................... - 75 - 20-4.04 PLANTING ................................................................................................................................... - 76 - 20-4.04.C TURF SOD ................................................................................................................................... - 77 - 20-4.07 INSPECTION FOR PLANT ESTABLISHMENT PERIOD .................................................................... - 77 - 20-4.08 PLANT ESTABLISHMENT PERIOD ................................................................................................ - 77 - 20-4.09 INSPECTION PRIOR TO FINAL ACCEPTANCE OF LANDSCAPE ...................................................... - 78 - 20-5.01.A EXISTING POINT OF CONNECTION ............................................................................................. - 78 - 20-5.03.C CONTROL WIRE, ELECTRICAL CONDUIT AND PULL BOXES ......................................................... - 78 - 20-5.04.B IRRIGATION SLEEVING ................................................................................................................ - 79 - 20-5.04.D TRENCHING AND BACKFILLING .................................................................................................. - 79 - 20-5.05 PIPE ............................................................................................................................................ - 79 - 20-5.05.A SUBSURFACE DRIPPERLINE ........................................................................................................ - 80 - 20-5.05.B VALVES AND VALVE BOXES ........................................................................................................ - 80 - 20-5.05.C QUICK COUPLING VALVE ............................................................................................................ - 81 - 20-5.05.D BACKFLOW PREVENTERS ............................................................................................................ - 81 - 20-5.05.H SPRINKLERS AND EMITTERS ....................................................................................................... - 81 - 20-5.05.H(1) ROOT ZONE BUBBLER ................................................................................................................. - 82 - 20-5.05.K GATE VALVE ............................................................................................................................... - 82 - 20-5.06 MEASUREMENT AND PAYMENT ................................................................................................ - 82 -

20-6 RECORD DRAWINGS AND CONTROLLER CHARTS ........................................................ - 82 - 20-7.01 INTERLOCKING PAVERS .............................................................................................................. - 83 -

20-8 MEASUREMENT AND PAYMENT ........................................................................................ - 84 - SECTION 22 - BASE MATERIAL ................................................................................................................ - 85 - 22-2 AGGREGATE BASE ................................................................................................................ - 85 - 22-4 MEASUREMENT AND PAYMENT ........................................................................................ - 85 - SECTION 23 - ASPHALT CONCRETE ....................................................................................................... - 86 - 23-1 GENERAL ................................................................................................................................. - 86 -

23-1.02 ABBREVIATIONS ......................................................................................................................... - 86 - 23-1.03 DEFINITIONS ............................................................................................................................... - 86 - 23-1.04 SUBMITTALS ............................................................................................................................... - 87 -

23-2 QUALITY ASSURANCE ......................................................................................................... - 87 - 23-2.01 GENERAL .................................................................................................................................... - 87 - 23-2.02 LABORATORIES ........................................................................................................................... - 87 - 23-2.03 HOT MIX ASPHALT PLANTS ........................................................................................................ - 87 - 23-2.04 TEST METHODS .......................................................................................................................... - 87 - 23-2.05 QUALITY CONTROL ..................................................................................................................... - 87 -v

23-2.05.A GENERAL .................................................................................................................................... - 87 - 23-2.05.B QUALITY CONTROL PLAN ........................................................................................................... - 87 - 23-2.06 DISPUTE RESOLUTION ................................................................................................................ - 88 -

23-3 MATERIALS ............................................................................................................................. - 88 - 23-3.01 AGGREGATES .............................................................................................................................. - 88 - 23-3.01.A GENERAL .................................................................................................................................... - 88 - 23-3.01.B QUALITY ..................................................................................................................................... - 89 - 23-3.01.C GRADATIONS .............................................................................................................................. - 90 - 23-3.02 RECLAIMED ASPHALT PAVEMENT .............................................................................................. - 91 - 23-3.03 ASPHALT BINDER ........................................................................................................................ - 91 - 23-3.04 LIQUID ANTISTRIP ...................................................................................................................... - 91 - 23-3.05 TACK COAT ................................................................................................................................. - 92 -

23-4 MIX DESIGNS .......................................................................................................................... - 92 - 23-4.01 GENERAL .................................................................................................................................... - 92 - 23-4.02 REQUIREMENTS ......................................................................................................................... - 93 - 23-4.02.A GENERAL .................................................................................................................................... - 93 - 23-4.02.B RECLAIMED ASPHALT PAVEMENT .............................................................................................. - 93 - 23-4.02.C TREATMENTS .............................................................................................................................. - 94 - 23-4.02.D WARM MIX ASPHALT TECHNOLOGY .......................................................................................... - 94 - 23-4.03 JOB MIX FORMULAS ................................................................................................................... - 94 - 23-4.03.A GENERAL .................................................................................................................................... - 94 - 23-4.03.B SUBMITTALS ............................................................................................................................... - 94 - 23-4.03.B.1 GENERAL .................................................................................................................................... - 94 - 23-4.03.B.2 LIQUID ANTISTRIP TREATMENT ................................................................................................. - 95 - 23-4.03.B.3 WARM MIX ASPHALT TECHNOLOGY .......................................................................................... - 95 - 23-4.03.C VERIFICATION ............................................................................................................................. - 96 - 23-4.03.D AUTHORIZATION ........................................................................................................................ - 97 - 23-4.03.E RENEWAL ................................................................................................................................... - 97 - 23-4.03.F MODIFICATION ........................................................................................................................... - 98 -

23-5 PRODUCTION .......................................................................................................................... - 99 - 23-5.01 GENERAL .................................................................................................................................... - 99 - 23-5.02 WARM MIX ASPHALT TECHNOLOGY ........................................................................................ - 100 - 23-5.04 QUALITY CONTROL ................................................................................................................... - 101 - 23-5.04.A GENERAL .................................................................................................................................. - 101 - 23-5.04.B AGGREGATE ............................................................................................................................. - 101 - 23-5.04.B.1 GENERAL .................................................................................................................................. - 101 - 23-5.04.B.2 GRADATIONS ............................................................................................................................ - 102 - 23-5.04.C RECLAIMED ASPHALT PAVEMENT ............................................................................................ - 102 - 23-5.04.D LIQUID ANTISTRIP TREATMENT ............................................................................................... - 103 - 23-5.04.E WARM MIX ASPHALT TECHNOLOGY ........................................................................................ - 104 - 23-5.04.F HOT MIX ASPHALT MIXTURES .................................................................................................. - 105 -

23-6 CONSTRUCTION ................................................................................................................... - 105 - 23-6.01 GENERAL .................................................................................................................................. - 105 - 23-6.02 EQUIPMENT ............................................................................................................................. - 105 - 23-6.02.A SPREADING EQUIPMENT .......................................................................................................... - 105 - 23-6.02.B MATERIAL TRANSFER VEHICLE ................................................................................................. - 106 - 23-6.02.C HAULING EQUIPMENT ............................................................................................................. - 106 - 23-6.03 SURFACE PREPARATION ........................................................................................................... - 106 -vi

23-6.04 TACK COAT ............................................................................................................................... - 106 - 23-6.05 PLACEMENT .............................................................................................................................. - 108 - 23-6.05.A GENERAL .................................................................................................................................. - 108 - 23-6.05.B LONGITUDINAL JOINTS ............................................................................................................. - 109 - 23-6.06 COMPACTION ........................................................................................................................... - 109 - 23-6.07 SMOOTHNESS ........................................................................................................................... - 110 - 23-6.08 QUALITY CONTROL ................................................................................................................... - 111 - 23-6.08.A HMA DENSITY ........................................................................................................................... - 111 -

23-9 ACCEPTANCE ....................................................................................................................... - 111 - 23-9.01 GENERAL .................................................................................................................................. - 111 - 23-9.02 HMA DENSITY ........................................................................................................................... - 114 -

23-11 MEASUREMENT AND PAYMENT ...................................................................................... - 116 - 23-12 COMPENSATION ADJUSTMENTS FOR PRICE INDEX FLUCTUATIONS .................... - 116 -

23-12.01 GENERAL .................................................................................................................................. - 116 - 23-12.02 ASPHALT QUANTITIES .............................................................................................................. - 117 - 23-12.03 PAYMENT ADJUSTMENTS ........................................................................................................ - 118 -

SECTION 25 – PORTLAND CEMENT CONCRETE (PCC) PAVEMENT .......................................... - 119 - 25-13 PCC DRIVEWAY CONFORMS ............................................................................................. - 119 - SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT .................................................. - 120 - 26-1 GENERAL ............................................................................................................................... - 120 - 26-3 PAVEMENT PLANING.......................................................................................................... - 120 -

26-3.01 PAVEMENT GRIND (4”) ............................................................................................................ - 120 - 26-3.02 COLD PLANE ASPHALT CONCRETE PAVEMENT ........................................................................ - 121 -

26-6 MEASUREMENT ................................................................................................................... - 121 - 26-7 PAYMENT .............................................................................................................................. - 122 - SECTION 27 - CURB, GUTTER, SIDEWALKS, AND DRAINAGE STRUCTURES .......................... - 123 - 27-3 CONCRETE IN CURBS, GUTTERS, AND SIDEWALKS .................................................... - 123 -

27-3.01 EXPANSION JOINTS, WEAKENED PLANE JOINTS, AND SCORE MARKS ..................................... - 123 - 27-8 CURB RAMPS AND DRIVEWAYS ...................................................................................... - 124 -

27-8.03 DETECTABLE WARNING SURFACE ............................................................................................ - 124 - 27-15 PAYMENT .............................................................................................................................. - 124 - 27-16 PCC CURBS AND CURBS & GUTTER ................................................................................ - 124 - SECTION 30 – CONCRETE STRUCTURES ............................................................................................ - 125 - 30-15 SURFACE FINISH .................................................................................................................. - 125 -

30-15.06 BRIDGE DECK REPAIR AND PREPARATION ............................................................................... - 125 - 30-15.06.A METHACRYLATE SEALER ........................................................................................................... - 125 - 30-15.07 POLYESTER CONCRETE OVERLAY ............................................................................................. - 125 -

30-16 MEASUREMENT AND PAYMENT ...................................................................................... - 125 - SECTION 34 - SIGNS ................................................................................................................................... - 126 - 34-3 ROADSIDE SIGNS ................................................................................................................. - 126 -

34-3.01 PROJECT INFORMATION SIGNS ................................................................................................ - 126 - 34-4 PAYMENT .............................................................................................................................. - 126 - SECTION 38 – STORM DRAIN CONSTRUCTION ................................................................................ - 127 -vii

38-12 MEASUREMENT AND PAYMENT ...................................................................................... - 127 - 39-1 GENERAL ............................................................................................................................... - 128 - 39-2 CONCRETE MANHOLES ...................................................................................................... - 128 -

39-2.01 TEMPORARY REMOVAL MANHOLE OR FLUSHER BRANCH FRAME AND COVER ..................... - 128 - 39-2.01A REMOVE MANHOLE OR FLUSHER BRANCH FRAME AND COVER ............................................. - 128 - 39-2.01B INSTALL MANHOLE OR FLUSHER BRANCH FRAME AND COVER .............................................. - 129 -

39-5 ADJUST STORM DRAIN MANHOLES TO GRADE ........................................................... - 129 - 39-6 RECONSTRUCT STORM DRAIN MANHOLES .................................................................. - 129 - 39-8 MEASUREMENT AND PAYMENT ...................................................................................... - 129 - 39-9 CORE PIPE OPENING INTO DRAIN STRUCTURE ............................................................ - 130 - 40-4 RESET BOLLARD .................................................................................................................. - 131 - 40-4 RECONSTRUCT WOOD FENCE .......................................................................................... - 131 - 40-12 RELOCATE PRIVATE SIGN ................................................................................................. - 131 - SECTION 46 - SURVEY MONUMENTS ................................................................................................... - 133 - 48-2 THERMOPLASTIC TRAFFIC STRIPES AND PAVEMENT MARKINGS ......................... - 134 - 48-3 PAINTED TRAFFIC STRIPES AND PAVEMENT MARKINGS ......................................... - 136 - 48-5 PLACEMENT .......................................................................................................................... - 138 - 48-7 DELINEATORS, PAVEMENT MARKERS, AND OBJECT MARKERS ............................ - 138 - 48-8 CONTRAST STRIPING .......................................................................................................... - 140 - SECTION 49 - SIGNAL, LIGHTING AND ELECTRICAL SYSTEMS ................................................. - 141 - 49-1 GENERAL ............................................................................................................................... - 141 -

49-1.06 MAINTAINING EXISTING AND TEMPORARY ELECTRICAL SYSTEMS .......................................... - 141 - 49-1.10 SIGNAL TURN ON ..................................................................................................................... - 142 - 49-1.11 CONTRACTOR SUPPLIED EQUIPMENT ...................................................................................... - 142 - 49-2.02 TRENCHING AND BORING ........................................................................................................ - 143 - 49-2.02.A EARTH SAW TRENCHING .......................................................................................................... - 143 - 49-2.02.B DIRECTIONAL BORE .................................................................................................................. - 143 - 49-2.04 FOUNDATIONS ......................................................................................................................... - 144 - 49-2.05 STANDARDS, STEEL PEDESTALS, AND POSTS ........................................................................... - 144 - 49-2.06 CONDUIT .................................................................................................................................. - 145 - 49-2.07 PULL BOXES .............................................................................................................................. - 146 - 49-2.08 CONDUCTORS ........................................................................................................................... - 147 - 49-2.08.A SIGNAL INTERCONNECT CABLE ................................................................................................ - 148 - 49-2.08.A TRAFFIC SIGNAL INTERCONNECT ............................................................................................. - 148 - 49-2.08.A.(1) CONDUIT .................................................................................................................................. - 148 - 49-2.08.A.(2) EXISTING SPLICE BOXES AND PULL BOXES ............................................................................... - 149 - 49-2.08.A.(3) FIBER SPLICE BOXES AND PULL BOXES ..................................................................................... - 149 - 49-2.08.B INTERCONNECT CABLE TESTING AFTER INSTALLATION ........................................................... - 150 - 49-2.08.B TRAFFIC SIGNAL INTERCONNECT CABLE AND SYSTEM TESTING .............................................. - 150 - 49-2.09 WIRING ..................................................................................................................................... - 151 - 49-2.11 SERVICE .................................................................................................................................... - 151 - 49-2.11.A METERED SERVICE (120/208 VOLT, 120/240 VOLT) ................................................................ - 151 - 49-2.14 SCHEDULE OF VALUES .............................................................................................................. - 151 -

49-3 CONTRACTOR SUPPLIED EQUIPMENT ........................................................................... - 152 - 49-4 TRAFFIC SIGNAL FACES AND FITTINGS......................................................................... - 152 -

49-4.01 VEHICLE SIGNAL FACES ............................................................................................................ - 152 - 49-4.03 BACKPLATES ............................................................................................................................. - 152 -viii

49-4.04 PEDESTRIAN SIGNAL FACES ...................................................................................................... - 152 - 49-4.05 AUDIBLE PEDESTRIAN SIGNALS ................................................................................................ - 153 -

49-5 DETECTORS .......................................................................................................................... - 153 - 49-5.01 VEHICLE DETECTORS ................................................................................................................ - 153 - 49-5.01.A CONSTRUCTION MATERIALS .................................................................................................... - 154 - 49-5.01.B INSTALLATION DETAILS ............................................................................................................ - 154 - 49-5.01.D VIDEO DETECTOR SYSTEM........................................................................................................ - 155 - 49-5.02 VIDEO OR HYBRID VIDEO/RADAR DETECTION SYSTEM ........................................................... - 155 - 49-5.02.A INSTALLATION .......................................................................................................................... - 156 - 49-5.02.B WARRANTY ............................................................................................................................... - 157 - 49-5.02 EMERGENCY VEHICLE DETECTOR CABLE, DETECTORS, AND PHASE SELECTORS ..................... - 157 - 49-5.03 EMERGENCY VEHICLE DETECTOR CABLE, DETECTORS, AND PHASE SELECTORS ..................... - 157 - 49-5.03 PEDESTRIAN PUSH BUTTONS ................................................................................................... - 157 - 49-5.04 PEDESTRIAN PUSH BUTTONS ................................................................................................... - 157 - 49-6 LIGHTING .................................................................................................................................. - 158 - 49-6.03 LIGHT EMITTING DIODE (LED) LUMINAIRES ............................................................................. - 158 - 49-6.04 STREET LIGHTS ......................................................................................................................... - 158 -

49-7 AGENCY – SUPPLIED EQUIPMENT ................................................................................... - 158 - 49-7.01 SIGNAL MAST ARM STREET NAME SIGNS ................................................................................ - 159 -

49-9 PAYMENT .............................................................................................................................. - 159 - 49-10 APPROVED EQUALS ............................................................................................................ - 159 - 49-11 PAYMENT .............................................................................................................................. - 159 - SECTION 50 - CONSTRUCTION MATERIALS...................................................................................... - 161 - 50-1 PORTLAND CEMENT ........................................................................................................... - 161 - 50-2 CONCRETE AGGREGATES ................................................................................................. - 161 - 50-3 WATER FOR CONCRETE ..................................................................................................... - 161 - 50-4 PREMOULDED EXPANSION JOINT FILLER ..................................................................... - 161 - 50-5 PORTLAND CEMENT CONCRETE ..................................................................................... - 161 -

50-5.01 COMPOSITION .......................................................................................................................... - 161 - 50-5.02 PROPORTIONING ...................................................................................................................... - 162 - 50-5.03 MIXING AND TRANSPORTING .................................................................................................. - 162 - 50-5.04 WATER CONTROL ..................................................................................................................... - 162 -

50-6 CURING COMPOUNDS FOR CONCRETE .......................................................................... - 162 - 50-7 AGGREGATE BASES ............................................................................................................ - 162 -

50-15 CONTROL DENSITY BACKFILL/CONTROLLED LOW STRENGTH MATERIAL ........ - 162 -

50-15.01 CONTROL DENSITY BACKFILL .................................................................................................... - 163 - 50-17 ASPHALT, LIQUID ASPHALT, AND ASPHALTIC EMULSION ....................................... - 163 -ix

APPENDICES

APPENDIX A

STATE DBE FORMS ................................................................................................................................................. A

APPENDIX B

SHRA REQUIREMENTS............................................................................................................................................ B

APPENDIX C

REVISED COUNTY STANDARD DRAWINGS ............................................................................................................. C

APPENDIX D

COUNTY MAINTENANCE DETAIL DRAWINGS......................................................................................................... D

APPENDIX E

ENVIRONMENTAL HAZARDOUS WASTE IDENTIFICATION…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .