3a_SOW.docx
DOCX document 22 KB Posted
- Attached to
- ROOF REPLACEMENT
- Solicitation number
- 70Z02721Q3CV26500
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12a_Construction Clauses Provisions FAC 2021-04.doc | DOC document | |
| 12a_RFQ 1449 Solicitation Form.pdf | ||
| 7n_Wage Rates.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR
WATER TREATMENT FACILITY ROOF REPLACE
CONTENTS
1. Introduction
2. Scope of Work
3. Period of Performance
4. Deliverables
5. Schedule
6. Acceptance Criteria
7. Quality Assurance
8. Contracting Officer’s Representative
9. Notes
1.0 INTRODUCTION
The U.S. Coast Guard, Station Annapolis, located at 3425 Thomas Point Rd. Annapolis Maryland, has had major deterioration of the roof located on the Water Treatment Facility Building servicing the stations well pumps and water treatment equipment. Damage is causing puddling of rain water and leaking into the building below.
2.0 SCOPE OF WORK- The work is to be accomplished through the following task.
2.1. Contractor shall provide services and materials to remove and dispose of existing installed roofing materials, plywood substrate, and rafters underneath substrate.
2.2. Contractor shall provide services and materials to install new ½ OSB decking, taper insulation to create slope to gutters, install new down cap sheet roofing system with slope at 3 edges and drip edge at gutter, secure gutters and new downspout.
3.0 PERIOD OF PERFORMANCE
3.1. Period of performance shall be within 2 weeks of acceptance of award.
4.0 DELIVERABLES
4.1. The contractor shall provide the following:
4.1.1. All materials needed for roofing system, substrate, flashing, drip edges, gutters, and downspouts.
4.1.2. Equipment needed to complete roof removal and install.
4.1.3. Removal and disposal of old roofing system and associated materials.
5.0 SCHEDULE. The schedule for milestones and deliverables is given in the following table.
| ITEM |
| DESCRIPTION |
| QTY |
| DUE DATE |
| 1 |
| Complete removal and install of new roof. |
| 1 |
| NLT 2 weeks |
6.0 ACCEPTANCE CRITERIA
7.1 The government reserves the right to witness the evaluation and repair processes.
7.2 The government will review the repair work in its entirety prior to issuing approval.
7.0 QUALITY ASSURANCE
7.1. All work shall be developed to commercial standards.
8.0 CONTRACTING OFFICER’S REPRESENTATIVE
8.1. The Contracting Officer’s Representative (COR) at the U.S. Coast Guard Station Annapolis will be MK1 Philip Hanaburgh (410) 267-8108.
8.2. The Alternate Contracting Officer’s Representative (ACOR) at the U.S. Coast Guard Station Annapolis will be MK2 Daniel Narke (410) 267-8108.
9.0 NOTES
All Government Furnished Information and work product shall remain the property of the U.S. Coast Guard and shall not be released to any third party or published without prior approval from the COR.
File details come from the government source that posted it. Updated .