36E77619R0066-192.docx

DOCX document Posted

Attached to
Correct Mechanical Deficiencies Design-Build Minneapolis VAMC Federal contract opportunity
Solicitation number
36E77619R0066
Issued by
Department of Veterans Affairs Office of Information Service Center

About this file

36E77619R0066 Attachment 1 - SOW - Correct Mechanical Deficiencies.docx

View the file

Other files for this federal contract opportunity

Other files attached to Correct Mechanical Deficiencies Design-Build Minneapolis VAMC, newest first.
File Type Posted
36E77619R0066-0003004.pdf PDF
36E77619R0066-0003003.docx DOCX document
36E77619R0066-0003005.docx DOCX document
36E77619R0066-0003004.pdf PDF
36E77619R0066-0003005.docx DOCX document
36E77619R0066-0003003.docx DOCX document
36E77619R0066-0002001.docx DOCX document
36E77619R0066-0002001.docx DOCX document
36E77619R0066-0001005.docx DOCX document
36E77619R0066-0001005.docx DOCX document
36E77619R0066-207.pdf PDF
36E77619R0066-205.pdf PDF
36E77619R0066-204.pdf PDF
36E77619R0066-199.pdf PDF
36E77619R0066-195.pdf PDF
36E77619R0066-200.pdf PDF
36E77619R0066-191.docx DOCX document
36E77619R0066-206.zip ZIP file
36E77619R0066-201.pdf PDF
36E77619R0066-194.docx DOCX document
36E77619R0066-193.docx DOCX document
36E77619R0066-202.zip ZIP file
36E77619R0066-203.zip ZIP file
36E77619R0066-198.zip ZIP file
36E77619R0066-197.zip ZIP file
36E77619R0066-196.zip ZIP file
36E77619R0066-192.docx DOCX document
36E77619R0066-196.zip ZIP file
36E77619R0066-203.zip ZIP file
36E77619R0066-206.zip ZIP file
36E77619R0066-199.pdf PDF
36E77619R0066-198.zip ZIP file
36E77619R0066-194.docx DOCX document
36E77619R0066-205.pdf PDF
36E77619R0066-201.pdf PDF
36E77619R0066-207.pdf PDF
36E77619R0066-204.pdf PDF
36E77619R0066-191.docx DOCX document
36E77619R0066-195.pdf PDF
36E77619R0066-202.zip ZIP file
36E77619R0066-197.zip ZIP file
36E77619R0066-193.docx DOCX document
36E77619R0066-200.pdf PDF
36E77619R0066-001.docx DOCX document
36E77619R0066-001.docx DOCX document
36E77619R0066-000.docx DOCX document
36E77619R0066-000.docx DOCX document
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

618-17-116 Correct Mechanical Deficiencies – Minneapolis VAMC

618-17-116 Correct Mechanical Deficiencies – Minneapolis VAMC

Scope of Work for Design-Build Correct Mechanical Deficiencies for Minneapolis Minnesota Project Number 618-17-116

General: Contractor shall provide Design-Build services to Correct Mechanical Deficiencies (18) in Minneapolis, Minnesota.

PART I GENERAL

A. Specific Design Build Requirements:

The Design Build (DB) project 618-17-116, Correct Mechanical Deficiencies 18 (CMD 18) project, Design Build Requirements are described in sections A.1. through A.6. below. The design phase has been completed for all items in A.1., while the design phase for items in sections A.2. through A.6 requires varying amounts of design input to complete construction documents. Remaining design effort for sections A.2. through A.6 is described below.

1. Item A.1. items a. through n. are fully designed with Construction Document Drawings and Specifications attached to this submittal. No additional design required. Items 1.d., 1.e. and 1.f. are sole sourced with Trans Vac and Swiss Log respectively. CLIN 0001

a. Building 10 – Replace underground water main in the vicinity of Buildings 9/10/11.

b. Building 49 - Replace damaged portion of downstream of exhaust fan #2 and reinsulate.

c. Building 49 - Replace 15 roof-mounted exhaust fans. Remove 5 unused/abandoned fans and associated ductwork.

d. Building 49 - Overhaul chiller including rebuilding of vanes and replacing motor bearings.

e. Building 68 - Remove and replace existing rooftop air handling units (3). There are three units which are beyond their service life and currently require significant maintenance. The existing transition curb will be reused.

f. Building 70 - Upgrade existing TransVac Waste Handling System as noted on drawings, including new doors, fan, dry scrubber, floor coating in dumpster area, amongst other items. In addition, cleaning of the excessive buildup will be completed prior to component replacement.

g. Building 70 – Remove and replace (28) linen chute access doors.

h. Building 70 – Upgrade pneumatic tube delivery system as noted on drawings to include standalone ethernet system.

i. Building 70 – Ward 1D corridor and nursing stations will be provided with the correct sprinkler heads (existing sprinkler heads are concealed, and recessed type is required).

j. Building 70 - Revise Sprinkler Mains in 1Q for access to drain system. Relocate piping, valves, and controls.

k. Building 70 - There are (11) domestic water risers that extends from the basement through the fourth floor; HW, CK, HWR. New branch valves at each riser are required; quantity (~185) indicated in drawings.

l. Building 70 - Replace eighteen (18) outside air dampers located in mechanical rooms throughout the building. Exact dampers indicated on drawings.

m. Building 78 – Re-venting of existing boiler exhaust in parking garage to terminate away from sidewalk.

2. Item A.2. consists of providing 2 each ALMiG Lento, air cooled, oil free, VSD, 25 hp air compressors with integrated dryer. These air compressors serve the facility laboratory and are located in the basement of Building 70, Room BD-101. The air compressors are to be procured by the design-build contractor and installed by VA Pipe Shop staff. The commissioning and training of the equipment is provided by Applied Air. CLIN 0002

3. Item A.3. consists of replacing 2 each cooling tower condenser pump motors; 69-P2 and 69-P3, associate VFD’s and circuit breakers. There are currently 4 each cooling tower/chiller combinations located in Building 69 (Energy Center) providing chilled water to the Minneapolis VAMC campus. Of the 4 current condensate pump motors/VFD/Circuit Breakers, 1 is new, 1 is approximately 8 years old, and 2 are original to the facility (~35 years old). These 2 original motors, (Numbered 69-P2 and 69-P3) VFD’s, and circuit breakers are past their useful life and need to be replaced as they are high reliability equipment. The one new motor/VFD/Circuit breaker was replaced in 2019 as part a project replacing 3 of the 4 cooling towers and other ancillary equipment. Contained in the attached specifications is the submittal approved for the referenced motors, VFDs, and circuit breakers. Design requirements are minimal for section A.3. Required motors/VFD’s/Circuit breakers are replacement in kind. CLIN 0003

4. Item A.4. consists of the installation of 2 steam coils into AHU 27. The VA purchased these (2) steam coils and require only the installation. Contained in the attached specifications is the cut sheet for the steam coils. This is government provided, contractor installed. CLIN 0004

5. Item A.5. consists installing upgraded boiler controls on each of 4 boilers located in Building 69 (energy center) Minneapolis VAMC campus. A full submittal is contained in the attached specifications. The design portion of the boiler control upgrade is included in the attached submittal. Boiler control design engineers are utilized for specific equipment maximizing efficiency in the design phase of DB. CLIN 0005

6. Item A.6. consists of DB to replace AHU’s within the Laundry facility Building 70. The original design of this project was completed in 2015, however, construction was not completed due to a funding issue. Although a CD set of drawings and specifications are available, some maintenance has been completed since the completion of design as well as potentially outdated specifications. The project includes replacement of AHU-51, AHU-52, AHU-53, AHU-57 and other associate equipment. The original design does not include AHU-57, which is a make-up air unit for the commercial dryers. The full CD set is available; however, we consider this design package to be approximately at the 65% design phase. CLIN 0006

B. General Design Requirements for Items Requiring Design:

1. The Contractor shall completely survey all existing spaces affected by the renovation (A.2. through A.6.). Survey shall include architectural, electrical, mechanical, structural, and low voltage systems.

2. The Contractor shall meet with site staff to review details of all equipment and gather comments after each design submission (A.2. through A.6.). The Contractor shall include Facilities Engineering in all design meetings. The Contractor shall also plan for a kick-off meeting with Facilities Engineering to walk the site, pull as-built drawings, set design requirements, and understand fully the scope of the project requirements.

3. All equipment shall be removed and disposed of by the construction contractor. The VA will not retain any equipment and it shall not be “abandoned in place.”

4. Energy saving is a priority for the VA. The design should incorporate features to minimize energy use.

5. Environmental conditions shall be maintained to other spaces.

6. Phased construction is required. The phasing shall be clearly depicted in both the 01 0000 specification section and the drawing set SOW Appendix 1.

C. General Requirements:

1. The VA will provide for the use of Submittal Exchange during all phases of the DB project. The Design Build team is expected to submit all documentation using Submittal Exchange for the life of the project.

2. Accuracy of Planning Information: The DB shall conduct a thorough site visit to investigate all aspects of the project and information shown on Government – Provided As-Builts. This information is the best available, but the Government does not guarantee its accuracy or completeness. The AE’s investigation shall include validation of all field conditions. DB shall document as-built conditions. The DB's investigation shall include validation of all field conditions.

3. Discrepancies in Planning Information: The DB shall promptly report to the Contracting Officer in writing any discrepancies between this contract and the planning information provided by the Government. The DB shall make no adjustments to his work due to the discrepancy before the Contracting Officer has reviewed the matter and forwarded his determination to the DB. The DB's failure to report any such discovered discrepancy or to wait for the Contracting Officer's determination shall be at the DB’s risk and expense.

4. Change Orders: Any work that is not addressed by the contract and is considered a change order shall be immediately brought to the attention of the Contracting Officer. No “out-of-scope” or additional work shall be executed by the DB prior to negotiation and approval by the Contracting Officer.

5. Ownership of Drawings: All designs, drawings, specifications, notes, and other work developed in the performance of this contract shall be and remains the sole property of the Government and may be used on any other work without additional compensation to the DB. With respect thereto, the DB agrees not to assert any rights and not to establish any claim under the design patent or copyright laws.

6. The DB Contractor shall provide a Brand Name or Equal Products List to identify all items in the specifications designated as brand name specified or equal. The list shall identify each item with the specification section in which the salient characteristics of each item are defined.

7. The DB shall provide a list of all items specified for which no substitutions will be accepted. The list shall identify each item with the specification section in which the item is defined.

8. The DB team shall meet with site staff to review details of the drawings and to gather comments after each design submission (35%, 95%). The DB team shall include Facilities Engineering in all design meetings. The DB team shall also plan for a kick-off meeting with Facilities Engineering to walk the site, pull as-built drawings, more specifically set design requirements and understand the full scope of the project requirements.

9. Environmental conditions shall be maintained to other spaces.

10. Design documents shall clearly show all infection control requirements. The Contractor shall coordinate with the station multi-disciplinary committee and infection control prevention staff to develop and design the infection control risk assessment (ICRA).

11. AE Response times for Submittals and RFI’s shall be the following (calendar days):

a. Critical = 2 days

b. Urgent = 7 days

c. Normal = 14 days

d. Critical and urgent submittals shall be pre-identified on the submittal log. These should be minimized.

D. Construction Phasing and Utility Outages: Many components of the CMD 18 project are independent of others, and as such may be completed simultaneously. Three major material handling systems will be upgraded; Trash, Linen, and Pneumatic Tube Delivery systems. With the complexity of these systems, they will likely be fully decommissioned during upgrade construction. For these three systems, strict adherence to scheduling is essential. General phasing will be generally completed as follows:

1. At D+15, the ALMIG air compressors for the laboratory will be ordered. The VA Pipe Shop staff will install.

2. HVAC components shall be constructed/replace during shoulder seasons as scheduled with the COR.

3. All utility outages will be coordinated with the COR and appropriate shop supervisor.

a. Utility outages shall be scheduled to minimize the impact on the medical facility. These are typically after hours; 1800 to 0500 Monday through Friday as well as Saturdays and Sundays.

b. Outages shall be scheduled a minimum of 14 days prior to service interruption.

c. A master plan for water outages will be prepared approximately 30 days in advance of the replacement of branch valves. The potential exists that main riser valves may not adequately hold for main riser shutdowns. Alternate planning must be completed in the event main riser valves are not able to stop the water flow in their respective risers.

d. Electrical power outages shall be scheduled with electric shop staff to provide emergency power during outage.

E. Proposed Schedule Design (Calendar Days)

1. Notice to Proceed D=Day

2. Design initiated (A.2. through A.7.) – D+7

a. 35% Submission – D+35

b. 35% Review by VA Complete – D+49

c. 95% Submission – D+70

d. 95% Review by VA Complete – D+84

e. 100% Submission – D+98

f. 100% Review by VA Complete – D+112

g. Documents Complete (CD Issue) – D+119

F. Proposed Construction Schedule (Calendar Days)

1. Notice to Proceed D=Day

2. Order ALMIG Laboratory Air Compressors – D+15

3. Complete schedule of individual components - D+30 Due to the complex nature of the project, a construction schedule will be produced by the contractor and reviewed/approved by the COR. The DB contractor shall create schedule using data from section D.

Total Period of Performance – 365 calendar days

G. References: The DB shall incorporate, but not be limited to references for design, available at http://www.cfm.va.gov/til/spec.asp; or from the project engineer, as applicable:

1. Construction Criteria Base or Whole Building Design Guide.

2. Minneapolis VA Medical Center Design Standards

3. VA Design Guides/Design Manuals

4. VA Master Specifications

5. VHA National CAD Standards and Details

6. VA BIM Guide

7. International Building Codes, State and Federal Regulations, ASHRAE Standards

8. NFPA and Life Safety Code

H. Government Provided Materials:

1. The VAMC Project Manager shall provide the DB with all available as-built and utility locations. The DB shall visit the project site to field-verify the information shown on the as-builts. The VAMC does not guarantee the accuracy or completeness of the as-builts. The DB shall promptly report any discrepancies to the VAMC Project Manager for clarification.

2. The VAMC Project Manager will provide specification section 010000, General Conditions to the DB. The DB shall modify the specification section to meet project requirements.

3. Minneapolis VA Medical Center Design Standards

4. The Minneapolis VA BIM Standards – v1.0

I. Design Pricing: Include pricing for items including:

1. Drawing reproduction

2. Travel costs

3. As-Built documentation in REVIT

J. Design Deliverables:

1. Design Services- Provide all items for a complete set of construction documents.

a. Document existing mechanical and plumbing conditions for the construction

b. Design shall be completed using AutoDesk Revit 2019. See attached “Minneapolis VA BIM Management Plan Worksheet” and “Minneapolis VA Revit Model Standards V1” for additional requirements and information.

c. Produce all contract drawings; 35% review set, 95% review set, 100% review, and final construction documents. Digital drawings shall be provided in Revit 17 (.rvt) format and Adobe PDF.

d. The DB shall prepare an Excel format submittal log based on the Specifications and provide for review and comment at 95%.

e. Site visits, as necessary, during design phase to complete the design. In the cost proposal, describe the number of site visits that will be required for each discipline.

f. The DB shall arrange site visits with appropriate disciplines as they deem necessary to complete the design.

g. A/E shall use the existing VA facilities drawings and update the existing as-built drawings to reflect contract documents.

h. DB shall provide a Revit model documenting the as-built condition post-construction phase. The model will be prepared in AutoDesk Revit 2019 format. Provide digital and hardcopy drawings documenting the as-built condition.

K. Magnitude of Construction: $5,000,000 to $10,000,000

L. Qualifications of Designers: The design of architectural, structural, mechanical, or other engineering features of the work shall be accomplished by architects or engineers registered within the VISN 23 region (MN, ND, SD, IA, NE). The Construction Specifications and Drawings shall bear the seal and signature of the registered professional architect or engineer responsible for its design.

M. Attachments

1. Specification Section 01 00 00 General Requirements

2. Minneapolis VA Design Standards

N. Security Requirements: Security requirements include VA Directive 6500.6, appendix C, paragraphs 3.a, 6.a, 7.a, Appendix D. Appendix B, C, and D is included as Attachment 10 to the solicitation.

PART II - POST AWARD REQUIREMENTS

Construction Document Preparation

A.Design Review Submissions:
1.The Design-Build Team A/E (DB A/E) shall prepare and submit complete construction documents for review and approval by the VA in accordance with standard professional practice, the Department of Veterans Affairs RFP (VA RFP), and prevailing codes.
2.The documents may be divided into multiple review submission packages. The VA will review as many as six (6) package submissions (examples: demolition, civil, architectural, structural, mechanical, Electrical, plumbing etc.) to facilitate the start of construction.
3.All submission packages will be reviewed at SD, DD, and CD completion stages. If any package is not complete for the required stage a post review may be required the cost of which will be borne by the DB Team.
4.Each review submission package shall include 4 hard copy sets and 1 electronic set on Submittal Exchange. The package will include an index of drawings (by sheet number and title) and specifications (by section number and title) submitted. The packages will be distributed to the VA Project Manager.
B.Design Review Meetings:
1.A review meeting to resolve design issues will be held for each design review package submitted. The meeting will include discussion of VA comments on functional relationships and technical peer review comments (by others).
2.Participants will include RFP A/E, VA Staff and DB team members as appropriate for the specific package to be reviewed and others. The DB team members will each allow for (1) full day for each discipline/package design review meeting. DB team management will be present at each review meeting.
3.The DB team shall allow a minimum of ten (10) working days for each review cycle. A cycle includes:
a)The VA’s receipt of the design review submission package.
b)The review meeting.
c)DB teams’ receipt of comments from the VA.
4.Coordination of the review meeting schedules will be the responsibility of the VA Project Manager (for the VA and RFP AE) and the DB Team Project Manager (for the DB Team). See section H. Quality Assurance/Quality Control.
C.Electronic Media:
1.Design review submission drawings and final Construction Document submission drawings will be executed in the latest AutoCAD version. If completed using Revit, construction documents shall be saved back to latest AutoCAD format if requested by station.
2.The drawings included in the VA RFP will be available to the DB team in electronic format for use in preparing the construction drawings. The CADD drawing files are provided without warranty or obligation on the part of the VHA as to accuracy or information contained in the files. The user shall independently verify all information in the files.
3.Design review submission specifications and other 8 1/2 by 11 formatted material and final Construction Document submission specifications and other 8 1/2 by 11 formatted material will be executed in the latest version of Microsoft Word and/or Adobe.
4.The construction record drawings shall be completed in the latest version of Revit or AutoCAD as specified by station.
D.Professional Licensing:
1.The DB A/E who prepares the construction documents shall be a professional architect or engineer licensed in the state in which the design work is completed.
2.The professional seal indicating such license by the state shall appear on the final construction documents. The architect whose seal is shown will be known as the Architect of Record. The DB A/E shall certify compliance with the VA RFP and all applicable codes.
E.Approved Construction Documents:
1.The final construction document submission package will be submitted by the DB team for approval by the VA after completion of the CD review cycle for the final package to be submitted by the DB team. The VA will have 5 days to take approval action.
2.The final construction documents submission package will include a full set of construction documents including all disciplines/packages.
3.The final construction documents submission package will incorporate all VA supplied comments from the earlier SD and DD submission package reviews and will comply with the VA RFP.
4.If the final construction documents submission package is not complete a post submittal may be required the cost of which will be borne by the DB Team.
5.The approved final construction documents include such details that the project can be constructed and will be used for construction of the project.
F.Construction Drawing Preparation - Mandatory material and equipment schedules and details may be indicated either on the drawings or in the specifications, at the option of the DB team. The construction drawings shall include a coordinated set of the following:
1.Structural drawings including framing plans, schedules, and details, including general notes and all calculations.
2.Architectural drawings including floor plans, wall sections, reflected ceiling plans, toilet and bath details, door schedules and details, window schedules and details, room finish schedules, and other details.
3.Fire protection drawings including ceiling plans, fire protection diagrams, equipment schedules, and details, including general notes and all related calculations.
4.Plumbing drawings including floor plans, riser diagrams, equipment schedules, plumbing fixture schedules, and details, including general notes, and all related calculations.
5.HVAC drawings including floor plans, one-line flow diagrams, equipment schedules, and details, including general notes and all related calculations. Also provide sections for mechanical equipment rooms and sequence of operation for all HVAC equipment.
6.Electrical drawings including floor plans (power, lighting, and other systems), one-line diagrams, panel schedules, equipment schedules, light fixture schedules calculations and details.
G.Construction Specifications - Project specifications shall include specifications for all products, materials, equipment, methods, and systems shown on the construction drawings in accordance with standard professional practice and the VA RFP. The specification submitted for review shall include:
1.The name of the manufacturer, the product name, model number, or other identification as appropriate to clearly identify the product that will be used in the construction of the project;
2.Other data as appropriate to clearly identify the product that will be used in the construction of the project i.e. shop drawings, product data, and samples as required by the VA RFP documents; and
3.The required stamp of the licensed architect or engineer of record will be considered as certification of compliance with the RFP requirements.
H.Design Requirements - Compliance with codes and standards.
1.Project design shall be in compliance with applicable standards and codes described in VA Program Guides and design materials included or referenced in the solicitation materials.
2.The DB team shall provide prompt, written notification to the Contracting Officer concerning conflicts with, or recommended deviations from codes, laws, regulations, standards, and opinions of review officials as described above. No work altering the scope of this contract shall be undertaken prior to receipt of written approval from the Contracting Officer.
I.Quality Assurance/Quality Control:
1.To reduce design errors and omissions, the DB team shall develop and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort.
2.Within 2 weeks of receipt of Notice to Proceed, the DB Team will submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the DB Team member responsible for QA/QC.

Construction Period Submittals

1.The DB contractor shall distribute a total of 2 sets of the approved construction documents prepared by the DB Team to the VA, as directed by the VA Project Manager.
2.Other submittals - The DB team shall submit test results, certificates, manufacturer’s instructions, manufacturers field reports, etc. as required by the VA RFP specifications, to the VA Project Manager.
3.Project record drawings - The DB team will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process as required by the RFP specifications. The project record drawings will be available for review by the VA Project Manager at all times.
4.Shop drawings and submittals - The DB A/E shall check government furnished and/or the DB construction contractor's shop drawings, detail drawings, schedules, descriptive literature and samples, testing labor-laboratory reports, field test data and review the color, texture and suitability of materials for conformity with the RFP Documents and construction documents. The DB A/E shall recommend approval, disapproval, or other suitable disposition to the VA Project Manager. The VA Project Manager will have final approval authority. The DB A/E shall notify the VA Project Manager in writing of any and all deviations from the requirements of the construction documents that he has found in the submittals.

Project Close-Out: The DB team shall comply with the requirements in FAR 4.804 Closeout of Contract Files, for submission of final RFP as built drawings, manuals, and other documents as noted. Required as built drawings and specifications will be submitted in the same format required for the construction documents.

Site Visits and Inspections: During the construction period the D-B A-E shall make weekly visits to the project site when requested by the COR. The COR may also request visits for special purposes. Only registered architects and engineers thoroughly familiar with the project may make these site visits. The COR has the prerogative to determine the professional discipline(s) required for any visit. The D-B A-E shall observe the construction, advise the COR of any deviations or deficiencies or solutions to issues discussed. A site inspection report which includes the purpose of the inspection, items reviewed, deficiencies observed, recommendations and additional actions required, shall be furnished to the COR within three work days following the site visit date.

---End--- Scope of Work (SOW) 1