36E77618R0088-0002001.pdf

PDF 67 KB Posted

Attached to
Perform X-Ray Room #3 Site-Prep Togus VAMC Federal contract opportunity
Solicitation number
36E77618R0088
Issued by
Department of Veterans Affairs Headquarters

About this file

36E77618R0088 0002 S05 - Technical Questions Tracking Spreadsheet - Togus - 7-18-18.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Perform X-Ray Room #3 Site-Prep Togus VAMC, newest first.
File Type Posted
36E77618C0035-000.docx DOCX document
36E77618R0088-0002000.docx DOCX document
36E77618R0088-0001000.docx DOCX document
36E77618R0088-0001001.pdf PDF
36E77618R0088-010.docx DOCX document
36E77618R0088-012.pdf PDF
36E77618R0088-011.docx DOCX document
36E77618R0088-002.doc DOC document
36E77618R0088-004.pdf PDF
36E77618R0088-013.docx DOCX document
36E77618R0088-003.docx DOCX document
36E77618R0088-009.pdf PDF
36E77618R0088-007.docx DOCX document
36E77618R0088-001.docx DOCX document
36E77618R0088-008.pdf PDF
36E77618R0088-005.pdf PDF
36E77618R0088-014.pdf PDF
36E77618R0088-006.zip ZIP file
36E77618R0088-000.docx DOCX document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36E77618R0088 PERFORM X-RAY ROOM #3 SITE PREP DESIGN BUILD - TOGUS TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

1. 7-15-18 7-16-18 Are permits required? No city and/or state permits are required on federal property for this construction project.

2. 7-15-18 7-16-18 Is this project tax exempt? No, bid should reflect all applicable taxes (see FAR Clause 52.229-3 on pg. 34 of the RFP).

3. 7-15-18 7-16-18 Please clarify that the proposal submission date of 7/26/18 is for phase I only and does not include any pricing? Phase II proposals will be requested after the government reviews phase I and selects 4 successful offerors for phase I.

Phase I does not include pricing and is due by 7/26/18. The statement concerning phase II proposals is correct.

4. 7-15-18 7-18-18 Are permits required? Please be advised that the previous answer to this question as cited in Item No. 1 GOVERNMENT RESPONSE has been rescinded. Permits are required and have been identified throughout the various attachments. It is the responsibility of the offeror to identify which permits are required prior to providing their proposal.

5.

6.

7.

8.

9.

10.

11.

12.

13.

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.