36E77618R0088-0001001.pdf
PDF 66 KB Posted
- Attached to
- Perform X-Ray Room #3 Site-Prep Togus VAMC Federal contract opportunity
- Solicitation number
- 36E77618R0088
About this file
36E77618R0088 0001 Technical Questions Tracking Spreadsheet - Togus - 7-17-18.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36E77618C0035-000.docx | DOCX document | |
| 36E77618R0088-0002000.docx | DOCX document | |
| 36E77618R0088-0002001.pdf | ||
| 36E77618R0088-0001000.docx | DOCX document | |
| 36E77618R0088-010.docx | DOCX document | |
| 36E77618R0088-012.pdf | ||
| 36E77618R0088-004.pdf | ||
| 36E77618R0088-013.docx | DOCX document | |
| 36E77618R0088-003.docx | DOCX document | |
| 36E77618R0088-009.pdf | ||
| 36E77618R0088-007.docx | DOCX document | |
| 36E77618R0088-001.docx | DOCX document | |
| 36E77618R0088-011.docx | DOCX document | |
| 36E77618R0088-002.doc | DOC document | |
| 36E77618R0088-008.pdf | ||
| 36E77618R0088-005.pdf | ||
| 36E77618R0088-014.pdf | ||
| 36E77618R0088-006.zip | ZIP file | |
| 36E77618R0088-000.docx | DOCX document |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36E77618R0088 PERFORM X-RAY ROOM #3 SITE PREP DESIGN BUILD - TOGUS TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET
ITEM
NO.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
1. 7-15-18 7-16-18 Are permits required? No city and/or state permits are required on federal property for this construction project.
2. 7-15-18 7-16-18 Is this project tax exempt? No, bid should reflect all applicable taxes (see FAR Clause 52.229-3 on pg. 34 of the RFP).
3. 7-15-18 7-16-18 Please clarify that the proposal submission date of 7/26/18 is for phase I only and does not include any pricing? Phase II proposals will be requested after the government reviews phase I and selects 4 successful offerors for phase I.
Phase I does not include pricing and is due by 7/26/18. The statement concerning phase II proposals is correct.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
ITEM
NO.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
17.
18.
19.
20.
21.
22.
23.
ITEM
File details come from the government source that posted it.