36E77618R0085 Attachment 16 - Section 31 20 11 Earth Moving.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36E77618R0085-0002000.docx | DOCX document | |
| 36E77618R0085-0001000.docx | DOCX document | |
| 36E77618R0085-020.pdf | ||
| 36E77618R0085-008.pdf | ||
| 36E77618R0085-022.pdf | ||
| 36E77618R0085-006.pdf | ||
| 36E77618R0085-005.pdf | ||
| 36E77618R0085-021.pdf | ||
| 36E77618R0085-003.pdf | ||
| 36E77618R0085-004.pdf | ||
| 36E77618R0085-011.pdf | ||
| 36E77618R0085-001.docx | DOCX document | |
| 36E77618R0085-014.pdf | ||
| 36E77618R0085-012.pdf | ||
| 36E77618R0085-015.pdf | ||
| 36E77618R0085-009.pdf | ||
| 36E77618R0085-026.pdf | ||
| 36E77618R0085-010.pdf | ||
| 36E77618R0085-007.pdf | ||
| 36E77618R0085-013.pdf | ||
| 36E77618R0085-002.pdf | ||
| 36E77618R0085-024.docx | DOCX document | |
| 36E77618R0085-018.pdf | ||
| 36E77618R0085-023.docx | DOCX document | |
| 36E77618R0085-019.pdf | ||
| 36E77618R0085-025.pdf | ||
| 36E77618R0085-016.pdf | ||
| 36E77618R0085-000.docx | DOCX document |
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Greater Los Angeles Healthcare Center
Sepulveda, California
Turn Key Photovoltaic Solar System
Project Number: 691A4-18-110SM
31 20 11 - 1
SECTION 31 20 11
EARTH MOVING
PART 1 - GENERAL
1.1 DESCRIPTION:
This section specifies the requirements for furnishing all equipment, materials, labor and techniques for earthwork including excavation, fill, backfill and site restoration utilizing fertilizer, seed and/or sod.
1.2 DEFINITIONS:
A. Unsuitable Materials:
1. Fills: Topsoil, frozen materials; construction materials and materials subject to decomposition; clods of clay and stones larger than 75 mm (3 inches); organic materials, including silts, which are unstable; and inorganic materials, including silts, too wet to be stable.
2. Existing Subgrade (except footings): Same materials as above paragraph, that are not capable of direct support of slabs, pavement, and similar items, with the possible exception of improvement by compaction, proofrolling, or similar methods of improvement.
B. Earthwork: Earthwork operations required within the new construction area.
C. Degree of Compaction: Degree of compaction is expressed as a percentage of maximum density obtained by the test procedure presented in ASTM
D698.
D. The term fill means fill or backfill as appropriate.
1.3 RELATED WORK:
A. Materials testing and inspection during construction: Section 01 45 29, TESTING LABORATORY SERVICES.
B. Protection of existing utilities, fire protection services, existing equipment, roads, and pavements: Section 01 00 00, GENERAL REQUIREMENTS.
1.4 CLASSIFICATION OF EXCAVATION:
A. Unclassified Excavation: Removal and disposal of pavements and other man-made obstructions visible on the surface; utilities, and other items including underground structures indicated to be demolished and removed;
31 20 11 - 2 together with any type of materials regardless of character of material and obstructions encountered.
1.5 APPLICABLE PUBLICATIONS:
A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only.
B. American Nursery and Landscape Association (ANLA):
2004....................American Standard for Nursery Stock
C. American Association of State Highway and Transportation Officials
(AASHTO):
T99-01 (R2004)..........Moisture-Density Relations of Soils Using a 2.5 kg (5.5 lb) Rammer and a 305 mm (12 inch) Drop
T180-01 (2004)..........Moisture-Density Relations of Soils Using a
4.54-kg [10 lb] Rammer and a 457 mm (18 inch)
Drop
D. American Society for Testing and Materials (ASTM):
D698-07.................Laboratory Compaction Characteristics of Soil
Using Standard Effort
D1557-02................Laboratory Compaction Characteristics of Soil
Using Modified Effort
E. Standard Specifications of California State Department of
Transportation, latest revision.
PART 2 - PRODUCTS
2.1 MATERIALS:
A. Fills: Materials approved from on site and off site sources having a minimum dry density of 1760 kg/m3 (110 pcf), a maximum Plasticity Index of 6, and a maximum Liquid Limit of 30.
B. Granular Fill:
1. Under concrete slab, crushed stone or gravel graded from 25 mm (1 inc
h) to 4.75 mm (No. 4).
2. Bedding for sanitary and storm sewer pipe, crushed stone or gravel graded from 13 mm (1/2 inch) to 4.75 mm (No. 4).
PART 3 - EXECUTION
3.1 SITE PREPARATION:
A. Clearing: Clearing within the limits of earthwork operations as described or designated by the Project Engineer. Work includes removal
31 20 11 - 3 of trees, shrubs, paving, debris, trash and any other obstructions.
Remove materials from the Medical Center.
B. Grubbing: Remove stumps and roots 75 mm (3 inches) and larger diameter.
Undisturbed sound stumps, roots up to 75 mm (3 inches) diameter, and nonperishable solid objects which will be a minimum of 900 mm (3 feet) below subgrade or finished embankment may be left.
C. Trees and Shrubs: Trees and shrubs, not shown for removal, may be removed from the areas within 4500 mm (15 feet) of new construction and
2250 mm (7’-6”) of utility lines if such removal is approved in advance by the Project Engineer. Trees and shrubs, shown to be transplanted, shall be dug with a ball of earth and burlapped in accordance with the latest issue of the, "American Standard for Nursery Stock", of the
American Association of Nurserymen, Inc. Transplant trees and shrubs to a permanent or temporary position within two hours after digging.
Maintain trees and shrubs held in temporary locations by watering as necessary and feeding semi-annually with liquid fertilizer with a minimum analysis of 5 percent nitrogen, 10 percent phosphorus and 5 percent potash. Maintain plants moved to permanent positions as specified for plants in temporary locations until the conclusion of the contract. Box, and otherwise protect from damage, existing trees and shrubs which are not shown to be removed in the construction area.
Repair immediately damage to existing trees and shrubs by trimming, cleaning and painting damaged areas, including the roots, in accordance with standard industry horticultural practice for the geographic area and plant species. Building materials shall not be stored closer to trees and shrubs, that are to remain, than the farthest extension of their limbs.
D. Stripping Topsoil: Unless otherwise indicated on the drawings, the limits of earthwork operations shall extend anywhere the existing grade is filled or cut or where construction operations have compacted or otherwise disturbed the existing grade or turf. Strip topsoil as defined herein, or as indicated in the geotechnical report, from within the limits of earthwork operations as specified above unless specifically indicated or specified elsewhere in the specifications or shown on the drawings. Topsoil shall be fertile, friable, natural topsoil of loamy character and characteristic of the locality. Topsoil shall be capable of growing healthy horticultural crops of grasses. Stockpile topsoil and protect as directed by the Project Engineer. Eliminate foreign material, such as weeds, roots, stones, subsoil, frozen clods, and similar foreign materials, larger than 0.014 m3 (1/2 cubic foot) in volume, from soil as
31 20 11 - 4 it is stockpiled. Retain topsoil on the station. Remove foreign materials larger than 50 mm (2 inches) in any dimension from topsoil used in final grading. Topsoil work, such as stripping, stockpiling, and similar topsoil work, shall not, under any circumstances, be carried out when the soil is wet so that the tilth of the soil will be destroyed.
1. Concrete Slabs and Paving: Score deeply or saw cut to insure a neat, straight cut, sections of existing concrete slabs and paving to be removed where excavation or trenching occurs. Extend pavement section to be removed a minimum of 300 mm (12 inches) on each side of widest part of trench excavation and insure final score lines are approximately parallel unless otherwise indicated. Remove material from the Medical Center.
E. Disposal: All materials removed from the property shall be disposed of at a legally approved site, for the specific materials, and all removals shall be in accordance with all applicable Federal, State and local regulations. No burning of materials is permitted onsite.
3.2 EXCAVATION:
A. Trench Earthwork:
1. Utility trenches:
a. Excavate to a width as necessary for sheeting and bracing and proper performance of the work.
b. Grade bottom of trenches with bell-holes, scooped-out to provide a uniform bearing.
c. Support piping on undisturbed earth unless a mechanical support is shown.
d. The length of open trench in advance of pipe laying shall not be greater than is authorized by the Project Engineer.
B. Site Earthwork: Excavation shall be accomplished as required by drawings and specifications. Remove subgrade materials, that are determined by the Project Engineer as unsuitable, and replace with acceptable material. When unsuitable material is encountered and removed, the contract price and time will be adjusted in accordance with Articles, DIFFERING SITE CONDITIONS, CHANGES and CHANGES-SUPPLEMENT of the GENERAL
CONDITIONS as applicable. Adjustments to be based on meters (yardage) in cut section only.
C. Finished elevation of subgrade shall be as follows:
1. Pavement Areas - bottom of the pavement or base course as applicable.
31 20 11 - 5
2. Planting and Lawn Areas - 100 mm (4 inches) below the finished grade, unless otherwise specified or indicated on the drawings.
3.3 FILLING AND BACKFILLING:
A. General: Do not fill or backfill until all debris, unsatisfactory soil materials, obstructions, and deleterious materials have been removed from the excavation. Proof-roll exposed subgrades with a fully loaded dump truck. Use excavated materials or borrow for fill and backfill, as applicable. Do not use unsuitable excavated materials. Do not backfill until foundation walls have been completed above grade and adequately braced, waterproofing or dampproofing applied, and pipes coming in contact with backfill have been installed, and inspected and approved by
Project Engineer.
B. Proof-rolling Existing Subgrade: Proof-roll with a fully loaded dump truck. Make a minimum of one pass in each direction. Remove unstable uncompactable material and replace with granular fill material completed to mix requirements specified.
C. Placing: Place material in horizontal layers not exceeding 200 mm (8 inches) in loose depth and then compacted. Do not place material on surfaces that are muddy, frozen, or contain frost.
D. Compaction: Use approved equipment (hand or mechanical) well suited to the type of material being compacted. Do not operate mechanized vibratory compaction equipment within 3000 mm (10 feet) of new or existing building walls without the prior approval of the Project
Engineer. Moisten or aerate material as necessary to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment used. Compact each layer to not less than
95 percent of the maximum density determined in accordance with the following test method ASTM D698.
3.4 GRADING:
A. General: Uniformly grade the areas within the limits of this section, including adjacent transition areas. Smooth the finished surface within specified tolerance. Provide uniform levels or slopes between points where elevations are indicated, or between such points and existing finished grades. Provide a smooth transition between abrupt changes in slope.
B. Cut rough or sloping rock to level beds for foundations. In unfinished areas fill low spots and level off with coarse sand or fine gravel.
31 20 11 - 6
C. Slope backfill outside the building away from the building walls for a minimum distance of 1800 mm (6 feet).
D. The finished grade shall be 150 mm (6 inches) below bottom line of windows or other building wall openings unless greater depth is shown.
E. Place crushed stone or gravel fill under concrete slabs on grade tamped and leveled. The thickness of the fill shall be 150 mm (6 inches), unless otherwise indicated.
F. Finish subgrade in a condition acceptable to the Project Engineer at least one day in advance of the paving operations. Maintain finished subgrade in a smooth and compacted condition until the succeeding operation has been accomplished. Scarify, compact, and grade the subgrade prior to further construction when approved compacted subgrade is disturbed by contractor's subsequent operations or adverse weather.
G. Grading for Paved Areas: Provide final grades for both subgrade and base course to +/- 6 mm (0.25 inches) of indicated grades.
3.5 DISPOSAL OF UNSUITABLE AND EXCESS EXCAVATED MATERIAL:
A. Disposal: Remove surplus satisfactory soil and waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off
Medical Center property.
1. Remove waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off Medical Center property.
B. Place excess excavated materials suitable for fill and/or backfill on site where directed.
C. Remove from site and dispose of any excess excavated materials after all fill and backfill operations have been completed.
D. Segregate all excavated contaminated soil designated by the Project
Engineer from all other excavated soils, and stockpile on site on two
0.15 mm (6 mil) polyethylene sheets with a polyethylene cover. A designated area shall be selected for this purpose. Dispose of excavated contaminated material in accordance with State and Local requirements.
3.6 CLEAN-UP:
Upon completion of earthwork operations, clean areas within contract limits, remove tools, and equipment. Provide site clear, clean, free of debris, and suitable for subsequent construction operations. Remove debris, rubbish, and excess material from the Medical Center.