36C26219Q0506-0002001.pdf
PDF 115 KB Posted
- Attached to
- 36C26219C0094_SERVICE to REPLACE Ceiling Tiles Federal contract opportunity
- Solicitation number
- 36C26219Q0506
About this file
36C26219Q0506 0002 S05 RFI001 with VA response.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26219C0094-000.docx | DOCX document | |
| 36C26219Q0506-0002004.docx | DOCX document | |
| 36C26219Q0506-0002005.pdf | ||
| 36C26219Q0506-0002007.pdf | ||
| 36C26219Q0506-0002000.docx | DOCX document | |
| 36C26219Q0506-0002006.pdf | ||
| 36C26219Q0506-0002002.pdf | ||
| 36C26219Q0506-0002003.pdf | ||
| 36C26219Q0506-0001004.pdf | ||
| 36C26219Q0506-0001005.pdf | ||
| 36C26219Q0506-0001003.docx | DOCX document | |
| 36C26219Q0506-0001001.pdf | ||
| 36C26219Q0506-0001000.docx | DOCX document | |
| 36C26219Q0506-0001002.pdf | ||
| 36C26219Q0506-001.docx | DOCX document | |
| 36C26219Q0506-002.pdf | ||
| 36C26219Q0506-000.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI FORM
Contractor Name:
Address:
Phone/Fax:
Send to: cecil.nichols@va.gov
RFI
(REQUEST FOR INFORMATION)
PROJECT NO.:
RFI NO.:
PROJECT NAME:
SERVICE to REPLACE Ceiling Tiles, VA San
Diego
DATE REQUESTED:
03/25/2019
SOLICITATION NO.:
36C26219Q0506
REFERENCE:
DRAWING:
SPECIFICATION
SECTION:
DESCRIPTION OF PROBLEM OR INFORMATION BEING REQUESTED
Please be specific as possible:
1. Will Contractor be required to set-up containments?
2. Will clearances be required? If clearances are required, who is responsible –
Contractor or VA?
3. Will the VA allow Contractor to use VA’s mobile mini containments for individual tiles?
4. Will there be differential in pricing or an ability for an add-on for tiles that are caulked into the grid?
5. Will Contractor have to re-caulk previously caulked ceiling tiles if replaced?
6. Will Contractor be required to caulk any new ceiling tiles when installed?
7. Will the VA remove the contents in offices prior to setting containment?
8. Will the VA be handling the waste; regardless as to if it is hazardous or non-hazardous?
9. Are tiles considered friable ACM or non-hazardous if cleaned?
PROJECT MANAGER’S RESPONSE
1. Yes, Contractor be required to set-up containments.
2. Yes, VA will be responsible for clearances.
3. Yes, VA will allow awarded Contractor to use mobile mini containment.
4. No, there will be no differential in pricing or ability for an add-ons.
mailto:cecil.nichols@va.gov
5. No, re-caulking of previously caulked ceiling tiles is not required.
6. No, caulking of new ceiling tiles is not required.
7. No, Contractor will be required to move furniture.
8. Yes, VA be handling the waste regardless of hazardous or non-hazardous.
9. All tiles in Building 1 are considered ACM and must be disposed of in accordance with federal, state, and local requirements.
AMENDMENT NO.:
VA PROJECT ENGINEER/MANAGER:
TIM CONROY, COR
DATE:
3/26/2019
File details come from the government source that posted it.