36C26118Q0171-019.docx
DOCX document 118 KB Posted
- Attached to
- HCHV Emergency Housing Sacramento County
- Solicitation number
- 36C26118Q0171
About this file
36C26118Q0171 36C26118Q0171.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26118D0045-003.docx | DOCX document | |
| 36C26118Q0171-022.docx | DOCX document | |
| 36C26118Q0171-020.docx | DOCX document | |
| 36C26118Q0171-024.docx | DOCX document | |
| 36C26118Q0171-023.docx | DOCX document | |
| 36C26118Q0171-021.docx | DOCX document | |
| 36C26118Q0171-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C26118Q0171
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
DUNS:
DUNS+4:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. 2/2012)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
612-18-1-2973-0007 36C26118Q0171 02-15-2018 Brian Trahan 916-923-4588 02-28-2018
1630 PST
612MCP
Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Northern California HealthCare System 6900 North Pecos Road, Bldg 6 North Las Vegas
NV
89086 X 624229 $15 Million
NET 30
X N/A X VA Northern California Healthcare System 5342 Dudley Blvd., Bldg. 209 McClellan
CA
95652
612MCP
Department of Veterans Affairs Department of Veterans Affairs VA Northern California HealthCare System 3230 Peacekeeper Way, Bldg. 209 McClellan
CA
95652-1012
Department of Veterans Affairs FMS VA-9(101) Financial Services Center PO Box 149971 Austin
TX
78714-9971 See CONTINUATION Page Northern California VA Health Care System Health Care for Homeless Veterans (HCHV) Contracted Emergency Residential Services (CERS) Emergency Housing IAW Performance Work Statement; Location: SACRAMENTO COUNTY In accordance with FAR 16.504, the Government intends to award a Single Award Indefinite Quantity Contract as a result of this solicitation.
See CONTINUATION Page X X Amanda J. Simmons Contracting Officer Table of Contents
| SECTION A | 1 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS | 1 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 4 |
| B.1 CONTRACT ADMINISTRATION DATA | 4 |
| B.2 DESCRIPTION/SCHEDULE/ORDERING/PERFORMANCE OF SERVICES | 5 |
| B.3 PRICE/COST SCHEDULE | 5 |
| ITEM INFORMATION | 5 |
| SECTION C - CONTRACT CLAUSES | 19 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (JAN 2017) | 19 |
| C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 25 |
| C.3 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016) | 25 |
| C.4 52.216-18 ORDERING (OCT 1995) | 27 |
| C.5 52.216-19 ORDER LIMITATIONS (OCT 1995) | 27 |
| C.6 52.216-22 INDEFINITE QUANTITY (OCT 1995) | 28 |
| C.7 52.232-19 AVAILABILITY OF FUNDS FOR THE NEXT FISCAL YEAR (APR 1984) | 28 |
| C.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (JAN 2008) | 28 |
| C.9 VAAR 852.203-71 DISPLAY OF DEPARTMENT OF VETERAN AFFAIRS HOTLINE POSTER (DEC 1992) | 29 |
| C.10 VAAR 852.228-71 INDEMNIFICATION AND INSURANCE (JAN 2008) | 29 |
| C.11 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012) | 30 |
| C.12 VAAR 852.237-70 CONTRACTOR RESPONSIBILITIES (APR 1984) | 31 |
| C.13 VAAR 852.215-71 EVALUATION FACTOR COMMITMENTS (DEC 2009) | 31 |
| C.14 VAAR 852.271-70 NONDISCRIMINATION IN SERVICES PROVIDED TO BENEFICIARIES (JAN 2008) | 31 |
| C.15 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL ITEMS (NOV 2017) | 32 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 39 |
| SECTION E - SOLICITATION PROVISIONS | 40 |
| E.1 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013) | 40 |
| E.2 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS (JAN 2017) | 41 |
| E.3 52.216-1 TYPE OF CONTRACT (APR 1984) | 46 |
| E.4 52.233-2 SERVICE OF PROTEST (SEP 2006) | 46 |
| E.5 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008) | 46 |
| E.6 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 47 |
| E.7 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998) | 47 |
| E.8 52.212-2 EVALUATION—COMMERCIAL ITEMS (OCT 2014) | 47 |
| E.9 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL ITEMS (NOV 2017) | 48 |
| E.10 VAAR 852.273-74 AWARD WITHOUT EXCHANGES (JAN 2003) | 64 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
(continuation from Standard Form 1449, block 18A.)
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C261 Amanda J. Simmons Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Northern California HealthCare System 6900 North Pecos Road, Bldg 6 North Las Vegas NV 89086
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [X] Monthly |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
Department of Veterans Affairs FMS VA-9(101) Financial Services Center
PO Box 149971 Austin TX 78714-9971 ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
B.2 DESCRIPTION/SCHEDULE/ORDERING/PERFORMANCE OF SERVICES
Description of Services This solicitation/contract will establish an Indefinite Delivery/Indefinite Quantity (IDIQ) Emergency Housing Services in Sacramento County for Department of Veteran Affairs to include Case Management on a per diem basis in accordance with Performance Work Statement.
Ordering/Performance Period
This IDIQ is for a 5-year ordering period of April 1, 2018 to March 31, 2023.
The contractor shall not be required to perform services under this contract after March 30, 2024.
Estimated Schedule of Services
30 DAYS per day 5490 DAYS per 6 months 10,980 DAYS per 12 months
The "DAY" unit is defined as room and board to accommodate one (1) veteran per bed per day. DAY is considered 24 hours. All services shall be provided in accordance with the Performance Work Statement.
B.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NO. |
| DESCRIPTION OF SUPPLIES/SERVICES |
| EST |
QTY
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 0001 |
| HCHV Residential Shelter Services |
| 5,490 |
| DY |
| ________________ |
| __________________ |
IAW Performance Work Statement.
Contract Period: Performance Period 1, 04-01-2018 09-30-2018
| 1001 |
| HCHV Residential Shelter Services |
| 10,980 |
| DY |
| __________________ |
| __________________ |
IAW Performance Work Statement.
Contract Period: Performance Period 2, 10-01-2018 09-30-2019
| 2001 |
| HCHV Residential Shelter Services |
| 10,980 |
| DY |
| __________________ |
| __________________ |
IAW Performance Work Statement.
Contract Period: Performance Period 3, 10-01-2019 09-30-2020
| 3001 |
| HCHV Residential Shelter Services |
| 10,980 |
| DY |
| __________________ |
| __________________ |
IAW Performance Work Statement.
Contract Period: Performance Period 4, 10-01-2020 09-30-2021
| 4001 |
| HCHV Residential Shelter Services |
| 10,980 |
| DY |
| __________________ |
| __________________ |
IAW Performance Work Statement.
Contract Period: Performance Period 5, 10-01-2021 09-30-2022
| 5001 |
| HCHV Residential Shelter Services |
| 5,490 |
| DY |
| __________________ |
| __________________ |
IAW Performance Work Statement.
Contract Period: Performance Period 6, 10-01-2022 03-31-2023
| GRAND TOTAL |
| __________________ |
The guaranteed minimum award amount for this contract is $1,000. The maximum aggregate value of orders that can be placed under this contract is $3,000,000.00. The Government does not guarantee that it will place any orders under this contract in excess of the guaranteed minimum award amount.
* EST QTY is founded upon utilizing 30 units per day, per performance period. This does not limit nor does it guarantee the number of units to any specific number of units at any time. The number of units being utilize may vary from day to day. The total number of units per period shall not be exceeded unless authorized in writing by a warranted, VA Contracting Officer.
NORTHERN CALIFORNIA VA HEALTH CARE SYSTEM
HEALTH CARE FOR HOMELESS VETERANS (HCHV)
CONTRACTED EMERGENCY RESIDENTIAL SERVICES (CERS)
EMERGENCY HOUSING
1. BACKGROUND
Ending homelessness among Veterans was established as a national priority by the Department of Veterans Affairs Secretary, Eric Shinseki, in November 2009 at the National Summit on Ending Veterans Homelessness. In June 2010, the U.S. Interagency Council on Homelessness (USICH) released Opening Doors: Federal Strategic Plan to Prevent and End Homelessness, which is fully aligned with this goal. Eliminating Veteran Homelessness remains one of three Agency Priority Goals for in VA’s 2014-2020 Strategic Plan.
The Health Care for Homeless Veterans (HCHV) program is an essential and critical part of VHA, providing a gateway to VA and community-based supportive services for eligible Veterans who are homeless. HCHV programs provide outreach services; care, treatment, and rehabilitative services, including case management services; and therapeutic transitional housing assistance under 38 U.S.C. 2032 in conjunction with Work Therapy under 38 U.S.C. 1718. The program uses Contracted Residential Services in community locations to engage homeless Veterans who have been underserved. Many of these Veterans would benefit from mental health and Substance Use Disorder (SUD) treatment but will not avail themselves of these services without the encouragement of outreach workers.
1. PROGRAM DESCRIPTION
The HCHV CERS Program exists to provide a means of removing homeless Veterans from the street or habitation unfit for humans and placing them in community-based, residential environments with sufficient supportive services to meet their basic needs and ultimately, facilitate the improvement of their overall health status and housing situation.
B.1. HCHV CERS Program characteristics:
B.1.1. Targets and prioritizes homeless Veterans who are eligible for VA health care, and are transitioning from chronic literal street homelessness, Veterans being discharged from institutions, and Veterans who recently became homeless and require safe and stable living arrangements while they seek permanent housing
B.1.2. Seeks to reduce barriers to immediate placement
B.1.3. Does not require any length of sobriety or abstinence from alcohol or other drugs as a condition of admission
B.1.4. Provides safe, secure, and wheelchair accessible housing as well as supportive services..
B.1.5. Lengths of Stay typically range from 30 to 90 days with the option to extend based on clinical need.
B.1.6. Veterans are expected to meaningfully engage their case managers and available Programming
B.1.7. Emphasis is placed on achieving placement in permanent housing or longer term residential programs that offer path to increased housing stabilization at the time of program exit, and reducing negative exits due to rule violations or other avoidable circumstances.
B.2. House Rules and Expectations B.2.1. Rules focus on staff and resident safety:
· No buying or selling of alcohol or drugs in the facility
· No use of illicit drugs in the facility
· No sexual activity between residents
· No violence or threats of violence
· Honor nightly curfew
B.2.2. When possible, infractions are to be used to engage residents, not simply as grounds for service termination. Negative discharges will be monitored as a measure of program quality.
B.2.3. Veterans are expected to engage programming and maintain communication with case managers at all times around matters relating to admission, stay, and treatment
B.3. Admission Practices B.3.1. Staff will assist residents with admission forms and eligibility determination with VA
B.3.2. Facility works to reduce barriers to admission:
· Accepts referrals throughout day if possible
· Flexibility with admission processes
B.4. Admission Criteria B.4.1. Homeless Veteran
B.4.2. Eligible for VA Health Care
B.5. Overview of Types of Services Available to Residents B.5.1. Safe, Secure housing (includes shared laundry and restroom facilities)
B.5.2. Three daily nutritious meals
B.5.3. Case Management and Care Coordination Services
B.5.4. Vocational Services
B.5.5. Benefits Services
B.5.6. Enhancement of Independent Living Skills
B.5.7. Permanent/ Transitional housing search support
1. PERFORMANCE WORK STATEMENT
C.1. OBJECTIVE
The Contractor shall provide emergency housing and supportive services for homeless Veterans in accordance with the HCHV CERS model requirements. Services are expected to consist of supportive, secure housing for homeless Veterans, many of whom may also be dealing with substance use disorders and/or mental illness. The program places an expectation on the Veteran to engage in supportive case management services, and also on the contractor to provide expertise and guidance for improving housing stability to ensure a transition from homelessness to permanent, stable housing. Contractors must comply with all HCHV CERS requirements as identified below.
C.2. HCHV CERS PROVIDER QUALIFICATIONS & CAPABILITY REQUIREMENTS
C.2.1. Capable of performing outreach or otherwise identifying and referring homeless Veterans with substance abuse disorders with a desire to pursue recovery by entering a residential treatment program to the contract program;
C.2.2. Capable of providing secure, separate housing and bathroom accommodations for males and females; common use of kitchen facilities and dining rooms is acceptable;
C.2.3. Capable of providing services twenty-four (24) hrs. a day for Veteran placements lasting up to ninety (90) days per Veteran. Extensions beyond initial ninety (90) days should be authorized in writing by VA Liaison; extensions beyond six (6) months must be prior-approved by the Social Work Service Contract Coordinator/ COR;
C.2.4. Capable of providing three daily nutritious meals and reasonable accommodation for special dietary needs;
C.2.5. Capable of offering a means for clients to wash their own clothes or otherwise tend to laundry;
C.2.6. Capable of providing secure, appropriate storage for both Veteran belongings and medication;
C.2.7. Capable of providing quality case management and treatment services that utilize a Recovery Model approach that includes elements of motivational interviewing, harm reduction, and critical time intervention ;
C.2.8. Capable of maintaining a minimum of one staff member on site at all times to ensure appropriate response to matters involving Veteran safety;
C.2.9. Capable of providing a working phone line and ensuring reasonably prompt communication with the VA is possible at all times;
C.3 DIRECT VETERAN CLINICAL SERVICES: 60% of time involves direct service to Veterans
C.3.1. Occupancy: The contractor will be responsible for ensuring that a minimally acceptable level of 80% occupancy of HCHV CERS funded beds is maintained at all times through independent outreach efforts as well as by collaboration with VA.
C.3.2 Care Planning: Contractor will engage the veteran in a collaborative assessment of needs, including barriers to stable housing, and create an initial plan of care to address those concerns within 14 days of admission. This plan is to be updated as needed throughout the Veterans episode of care.
C.3.3. Case Management: Contractor will provide individual case management meetings at least three (3) times per month (preferably once per week) that focus, at a minimum, on: housing search and stabilization, increasing income, any necessary coordination of ongoing participation in care provided by VA/community medical and/or mental health care providers, and ongoing discharge planning.
C.3.4. Medication Storage: Contractor is expected to provide, at a minimum, a means of securely and properly storing all medications brought into the program for Veteran use. Veterans may self-administer medications, but storage should ensure that no other residents are able to access an individual Veterans medications. Any suspicion or concern of misuse is to be reported to VA Liaison immediately following incident reporting protocol.
C.3.5. Exits to Independent Housing: The contractor is expected to promote a focus on achieving stable, independent housing for all Veterans referred for care; exits to permanent, independent housing will be monitored as an indicator of overall program quality utilizing data provided by the VHA Support Service Center’s Homeless Service Scorecard – the target rate for exits to this type of housing will be 35% or higher.
C.3.6. Negative Exits: The contractor is expected to facilitate Veteran completion of the HCHV CERS Program to the maximum extent possible, while still maintaining program integrity and safety; “Negative Exits,” which shall be defined as discharges involving Veterans being asked to leave the program due to rule violation or otherwise leaving the program without consulting program staff in any way, shall be monitored on a continuous basis utilizing data provided by the VHA Support Service Center’s Homeless Service Scorecard – the target rate for these types of exits will be 30% or less.
Per diem funds assist homeless veterans by helping to offset operating costs to ensure the availability of supportive housing and service centers tasked with furnishing outreach, rehabilitative services, vocational counseling and training, and transitional housing assistance. Code of Federal Regulations 38 § 61.30.
C.4. ADMINISTRATIVE SERVICES: 40% of time does not involve direct service to Veterans
C.4.1. Determination of Eligibility: The contractor is responsible for determining Veteran eligibility for placement into HCHV CERS Bed. A Veteran must be homeless and eligible for VA health care in order to be considered for admission to any CERS Program. Failure to establish eligibility prior to admission may result in denial of payment for services provided to ineligible Veterans.
C.4.2. Release of Information: The contractor shall ensure that a signed VA Release of Information (ROI) is obtained for any Veteran being admitted to an HCHV CERS Bed and placed into individual case record.
C.4.3. Individual Case Records: The contractor will maintain an individual case record for each referred Veteran. Case records must be maintained in security and confidence as required by the Confidentiality of Alcohol and Drug Abuse Patient Records (42 CFR part II) and the Confidentiality of Certain Medical Records (38 USC 7332), and in accordance with the Health Insurance Portability and Accountability Act (HIPAA: Pub. Law. 104–191). Records should contain at a minimum: Reason for referral; pertinent demographic information; copies of any medical prescriptions/orders issued by physicians; case management/treatment notes; any critical incident reports; and a final summary that include reason(s) for leaving, the Veteran’s known future plans, and follow-up locator information, if available.
C.4.4. Homeless Management Information System (HMIS) Data Reporting: Veterans served through VA’s HCHV CERS program must have client level data entered into the local Community Continuum of Care’s (CoC) HMIS. Data entered must include, at a minimum, the Universal Data Elements from the 2010 HMIS Data Standards.
C.4.5. Daily Census Sign-In Sheet: The contractor is responsible for collecting Veteran participant signatures on a daily census sign-in sheet to verify attendance in the program. This information is to be provided to the VA Liaison on a daily basis in order to ensure effective monitoring of bed utilization.
C.4.6. Incident Reporting: The contractor shall notify the VA immediately when any adverse critical incident involving a Veteran admitted to the program occurs. Critical Incidents shall include:
· Falls
· Elderly/Dependent Adult Abuse or Neglect
· Sexual Assault
· Fire (Veteran Involved)
· Medical or Mental Health Emergency (911 Calls)
· Hospitalization
· Suicidal ideation or attempt
· Homicidal ideation
· Assault (of other residents or Staff)
· Death
· Infectious Control Concerns (Bed Bugs, TB, etc.)
· Observation/ Possession of Weapons During normal business hours, the identified VA Liaison, HCHV Coordinator or COR should be contacted immediately by phone to report such an incident; if the incident occurs after hours, the local VA Facility Administrator on Duty (AOD) should be notified, also by telephone. A written report to the VA Liaison and/or COR should follow within 24 business hours. The report should list known precipitating factors or triggers. Contractor shall maintain a copy of all critical incident reports in the involved Veteran’s individual case record.
C.4.7. Extension Requests: The contractor is responsible for ensuring that all requests for extension of services beyond the initially authorized service period of 90 days are reviewed and approved in writing by the VA Liaison (or Social Work Service Contract Coordinator/ COR for requests exceeding six (6) months).
C.4.8. Satisfaction Surveys: The contractor will be responsible for administering, collecting, and delivering monthly to VA Liaison the Universal Stakeholder Participation and Experience Questionnaires (uSPEQ) Survey: This survey will be the primary tool for reporting Veteran satisfaction data in VA specialized homeless programs; it is to be administered to and collected from any Veterans who have resided in the program for at least of thirty (30) days.
C.4.9. Discharge Reporting: The contractor is responsible for notifying the identified VA Liaison (or designee) within 24 business hrs. that a discharge has occurred, and for providing a written report of discharge that contains the specific data required by the Northeast Program Evaluation Center (NEPEC) for documentation of discharge in the Homeless Operations and Management Evaluation System (HOMES) within 48 business hrs.
D. DELIVERABLES
D.1. QUALITY CONTROL BUSINESS PLAN: The contractor shall submit a Quality Control Business Plan that supports the program objectives and associated tasks. The CO shall review and comment as necessary to ensure that contract goals are met.
D.2. STAFFING AND SERVICE PLAN: The contractor shall provide a detailed staffing and service plan. Plan should demonstrate that sufficient professional personnel are employed to carry out the policies, responsibilities, and services required under this contract. The Contractor must identify each person functioning as “Key Personnel” under this contract, and provide the VA with a description of the services to be provided by each person. The Contractor shall assign to this contract personnel that by education and/or training (and, when required, certification or licensure) are qualified to provide the services required by this PWS. Contractor may be required to supply a resume(s) summarizing relevant skills and experience of any/all key personnel upon request. Minimum Key Personnel requirements are as follows:
D.2.1. One administrative staff member, or designee of equivalent professional capability (with the authority to make decisions regarding the facility and residents, or with contact information for an offsite administrator in case of emergency), on duty on the premises or providing awake supervision of residents and staff 24 hours a day, 7 days a week.
D.2.2. Sufficient case management/counseling personnel to provide direct services to Veteran residents. Case managers should have some training and experience working with homeless individuals; experience working with individuals dealing with chronic medical, mental health and substance abuse problems is highly desirable. Staff working with Veterans should be able to assess, anticipate, and effectively refer Veterans experiencing crises for additional support as appropriate.
D.2.4. At least one staff or security member with CPR certification on site and available in an emergency during each shift, 24 hours per day.
The contractor shall provide resumes for any proposed substitutions of key personnel, at least 15 days proposed date of substitution. substitution is to occur. The Contracting Officer shall notify the contractor within fifteen (15) calendar days after receipt of all required information if the VA is able to accept the proposed substitute key personnel. Temporary substitutions of key personnel shall be permitted in accordance with the contractor’s contingency plan. The contractor’s contingency plan to be utilized if personnel leave contractor’s employment or are unable to continue performance in accordance with the terms and conditions of the resulting contract should be submitted to CO as a part of proposal package. The CO is the ultimate authority on acceptable length for temporary substitution of key personnel.
The VA reserves the right to refuse or revoke acceptance of any key personnel if personal or professional conduct, or lack of required skills or experience jeopardizes patient care or interferes with the regular and ordinary operation of the facility and the HCHV CERS Program.
D.3. DOCUMENTATION OF SUPPORTIVE SERVICES: The Contractor shall provide written documentation constituted by the individual Veteran case record that verifies the provision of all supportive services required under this contract for each Veteran participant.
D.4. CARE PLAN: The written plan of care shall be completed and entered into the individual Veteran case record no later than day 14 days after being admitted to the program.
D.5. CRITICAL INCIDENT REPORTS: Written critical incident reports must be submitted to the VA Liaison within 24 business hours (VA Liaison/AOD to be notified immediately or as soon as possible when incidents occur).
D.6. EXTENSION REQUESTS: Written requests for extension are due prior to the 90th day when it is anticipated the Veteran will require additional time beyond the initially authorized service period, and prior to the expiration of the initial and any and all subsequent future extension authorizations.
D.7. DISCHARGE REPORTS: The HOMES Exit form shall be completed and submitted to the VA Liaison within 48 business hours (VA Liaison to be notified within 24 hours of discharge).
D.8. SATISFACTION SURVEYS: All Universal Stakeholder Participation and Experience Questionnaires (uSPEQ are to be provided to the VA Liaison at the end of each month.
D.9. DAILY CENSUS SIGN-IN SHEET: The daily census sign-in sheet should be provided to the VA Liaison daily; weekend or holiday sign-in sheets are to be provided to the VA Liaison the on the next business day.
D.10. INVOICES: The monthly invoice is computed at the daily rate multiplied by the total number of beds occupied by Veterans at midnight each night of the given month. Invoices should first be submitted to the VA Liaison for approval and signature by the 5th of the month immediately following the billing period in question. Once approved, invoices are to be submitted through the Tungsten Network (Electronic Invoicing System) by the 10th of the month immediately following the billing period in question.; all electronic invoices submitted should be accompanied by invoice bearing VA Liaison signature for reference of certifying official. (For additional information, Reference: VAAR 852.273-72 Electronic Submission of Payments pg.
23. and FAR 52.232-33 Payments by Electronic Funds Transfer—System for Award Management pg.27.) .
D.11. QUARTERLY PERFORMANCE REPORT: The contractor shall provide the COR with a written report detailing program data and activities on a quarterly basis. The report should contain, at minimum, the following information:
· Total Number of Veterans Served
· Occupancy rate
· Percent of Veterans discharged to independent housing
· Percent of negative discharges (i.e. discharges due to rule violation, failure to comply with program requirements, or unexpected discharges without prior consultation with staff).
· Other information the contractor feels pertinent, such as: quality improvement projects, changes in staffing or business practices, systems or resource concerns, etc.
DELIVERABLE TIME TABLE
| Deliverables |
| Due Dates |
| D.1. QUALITY CONTROL BUSINESS PLAN |
| Due upon solicitation close date |
| D.2. STAFFING AND SERVICE PLAN |
| Due upon solicitation close date |
| D.3. DOCUMENTATION OF SUPPORTIVE SERVICES: |
| Completed Veteran case record due upon case close out; due to VA upon request only. |
| D.4. CARE PLAN |
| Due in Veteran case record by day 14; due to VA upon request |
| D.5. CRITICAL INCIDENT REPORTS |
| Due within 24 business hours of a critical adverse event involving a Veteran |
| D.6. EXTENSION REQUESTS |
| Due prior to the expiration of any authorized period of service |
| D.7. DISCHARGE REPORTS |
| Due within 48 business hours of Veteran discharge |
| D.8. SATISFACTION SURVEYS |
| Due at the end of each monthly service period |
D.9. DAILY CENSUS SIGN-IN SHEET
Due daily
| D.10. INVOICES |
| Due to VA Liaison by the 5th of the month immediately following the billing period in question; due in Tungsten Network (electronic billing system) by the 10th of the month immediately following the billing period in question. |
Figure D.11.1
E. REFERRALS
E.1. The VA is capable in determining eligibility of Veterans prior to admission to contractor bed for services. The contractor is expected to work with identified VA Liaison or other designees to confirm eligibility; it is understood that payment for Veterans admitted without an initial determination of eligibility may not be authorized if the Veteran is found to be ineligible.
E.1.2. A list of authorized VA ordering personnel, including primary identified VA Liaison, shall be made available to the contractor upon award of the contract. VA employees may be added or deleted from this list during the term of the contract at the discretion of VA. The contractor shall not deviate from the list of individuals authorized to approve admissions without an updated list.
E.1.3. Referral constitutes authorization of an initial service period of up to 90 days (unless otherwise specified).
F. ABSENCES AND CANCELLATION
F.1. The Contractor shall notify VAMC of any absences from the facility. Absences of the patient from the facility in excess of forty-eight (48) hours will not be reimbursable except those with the prior approval of the VAMC coordinator. Should a patient referred to a residential treatment facility absent himself/herself in an unauthorized manner, payment for services for that Veteran to the contract facility would be continued for a maximum period of two days provided there is an active outreach attempt on the part of the contractor facility staff to return the Veteran to the residential treatment program and a strong likelihood that the patient will return. Management of Negative Exits will be an element of quality assurance review of this program.
F.2. The contractor may consider providing an authorized absence (or “pass”) for purposes that are expected to further the recovery goals of a Veteran (e.g., job-related absences, family visits, housing searches, medical, etc.). All requests for passes must be documented in writing in the Veterans individual case record. Authorized absences shall not exceed 48 hours in any given month for any single Veteran, unless otherwise approved by contractor and VA Liaison.
F.3. VA reserves the right to remove any or all Veterans from the facility at any time without additional cost, when it is determined to be in the best interest of the Veteran or VA.
G. CONDUCT
G.1. The contractor shall comply with the principles listed in 38 CFR 17.707(b) to provide housing and supportive services in a manner that is free from religious discrimination.
G.2. Local law enforcement and/or fire departments should be contacted for assistance and intervention as appropriate and indicated by any given circumstances.
G.3. The contractor shall also notify the VA Liaison, AOD, or COR immediately of any high risk situations involving veterans with suicidal and/or homicidal threats or ideation, episodes of physical or sexual violence, sexual activities, safety concerns, or activities involving illegal substances so that appropriate response may be coordinated.
G.4. In the event of a medical or psychiatric emergency, it is agreed that every effort will be made to facilitate Veteran access to local VA Medical Center for care. If a VA Medical Center is not available in the vicinity or is otherwise inconveniently located, the Contractor will advise the VA Liaison or AOD of the facility to which the Veteran has been admitted. The Contractor will also be expected to assist Veteran’s requiring non-urgent services with accessing appropriate care from a VA or community facility, as appropriate.
H. COMPLAINTS
The identified VA Liaison and the Contracting Officer’s Representative (COR) will monitor the services being provided in all HCHV CERS Facilities. The contractor is expected to cooperate with VA Staff and COR by providing information and answering questions in a timely manner when requested. Contractor shall refer complaints received directly from Veterans to the identified VA Liaison or COR within 48 hours of complaint. All complaints received by the VA Liaison or COR will be immediately forwarded to the contractor and shall be investigated promptly. After investigation and clarification of disposition, the contractor shall respond to the VA Liaison or COR within five (5) working days or less with proposed resolution or plan for corrective action. The CO shall be notified in instances where the proposed course of action or response does not appear sufficient to resolve any given complaint.
I. TRAVEL
The contractor is expected to assist Veterans with arranging local transportation to scheduled meetings and appointments. The contractor is expected to help Veterans understand and learn how to utilize public transportation; this includes providing access to information and clarifying instructions necessary to effectively utilize public transit systems. If contractor and VA staff both determine that public transportation is not available, adequate, or appropriate for any Veteran, the contractor will be expected to assist the Veteran with identifying potential alternative modes of transport, however, under no circumstances is the contractor expected to provide transportation to a Veteran directly.
J. FACILITIES
J.1. General requirements: It is the responsibility of the Contractor to properly maintain its facilities and the VA shall have no responsibility for paying or reimbursing the Contractor for such expenses. The contract facility must:
J.1.1 Have a current occupancy permit issued by the local and state governments in the jurisdiction where the facility is located.
J.1.2. Be in compliance with existing standards of State safety codes and local, and/or State health and sanitation codes.
J.1.3. Meet the requirements of the Americans with Disabilities Act (ADA) (Public Law 100-336, 42 USC 12101-12213) pertaining to handicapped accessibility in effect on the date of contract award.
J.1.4. Where applicable, be licensed under State or local authority.
J.1.5. Where applicable, be accredited by the State.
J.1.6. Be equipped with operational air conditioning /heating systems
J.1.7. Be kept clean free of dirt, grime, mold, or other hazardous substances and damaged noticeably detract from the overall appearance.
J.1.8. Be equipped with first aid equipment and an evacuation plan in case of emergency.
J.1.9. Have windows and doors that can be opened and closed in accordance with manufacturer standards.
J.1.10. Have an aggressive on-going plan to address bed bug infestation. This policy must be a part of your written response to this solicitation. On-going bed bug infestation will be grounds for immediate discharge of Veterans from the facility
J.2. Fire Safety Requirements:
J.2.1. The building must meet the requirements of the applicable residential occupancy chapters of the current version of NFPA 101, National Fire Protection Association's Life Safety Code. Any equivalencies or variances must be approved by VANCHCS Director
J.2.2. Fire exit drills must be held at least quarterly. Residents must be instructed in evacuation procedures when the primary and/or secondary exits are blocked. A written fire plan for evacuation in the event of fire shall be developed and reviewed annually. The plan shall outline the duties, responsibilities and actions to be taken by the staff and residents in the event of a fire emergency. This plan shall be implemented during fire exit drills.
A written policy regarding tobacco smoking in the facility shall be established and enforced.
J.2.4. Portable fire extinguishers shall be installed at the facility. Use NFPA 10, Portable Fire Extinguishers, as guidance in selection and location requirements of extinguishers. Requirements for fire protection equipment and systems shall be in accordance with NFPA 101. All fire protection systems and equipment, such as the fire alarm system, smoke detectors, and portable extinguishers, shall be inspected, tested and maintained in accordance with the applicable NFPA fire codes and the results documented.
J.3 Inspection: Prior to the award of any contract and annually thereafter during any subsequent contracted performance periods, a multidisciplinary VA team consisting of a social worker, dietitian or nutrition and food service professional, nursing staff, VA Police, and a Safety and Occupational Health Specialist, as well as any other subject matter experts determined necessary by the medical center director, COR, HCHV Coordinator, or VA Liaison, shall conduct a survey of the contractor’s facilities to be used to provide Veterans food, shelter, and clinical services to assure the facility provides acceptable level quality care in a safe environment. Additional inspections may also be carried out, announced or unannounced at any other time as deemed necessary by VA.
The contractor will be advised of the findings of the inspection team. If deficiencies are noted during any inspection, the contractor will be given a reasonable amount of time (typically 30 days) to take corrective action and to notify the Contracting Officer that the corrections have been made. A contract will not be awarded until noted deficiencies have been eliminated. Failure by the Contractor to take corrective action within the reasonable time provided will be reported to the VA Contracting Officer. If corrections are not made to the satisfaction of the VA, the Contracting Officer will be notified, and shall be the final arbiter on the necessary resulting consequences and action.
The inspection of the Contractor facilities will include inspection for conformity to the current Life Safety Code as described in paragraph 5, and will also include the following:
J.3.1. General observation of residents to determine if they maintain an acceptable level of personal hygiene and grooming.
J.3.2.Assessment of whether the facility meets applicable fire, safety and sanitation standards.
J.3.3. Determining whether the facility is in attractive surroundings conducive to social interaction and the fullest development of the resident's rehabilitative potential.
J.3.4. Observation of facility operations to see if appropriate organized activity programs are available during waking hours (including evenings) and degree to which a high level of activity is observed in the facility, such as individual professional counseling, physical activities, assistance with health and personal hygiene.
J.3.5. Seeking evidence of facility-community interaction, demonstrated by the nature of scheduled activities or by information about resident flow out of the facility, e.g., community activities, volunteers, local consumer services, etc. This should include not less than one homeless Veteran or formally homeless Veteran on the board of directors or the equivalent policy making entity. It should also include attempts to involve homeless Veterans through employment, volunteer services, or otherwise in construction, rehabilitation, maintaining, and operation of the program.
J.3.6. Observation of staff behavior and interaction with residents to determine if they convey an attitude of genuine concern and caring.
J.3.7. Inspecting the types of meals and other nutrition provided to residents to see if appetizing, nutritionally adequate meals are provided in a setting, which encourages social interaction and if nutritious snacks between meals and bedtime are available for those requiring or desiring additional food, when it is not medically contraindicated.
J.3.8. Making a spot check of Veterans’ records to ensure accuracy with respect to Veterans’ length of stay and services provided to the Veterans.
All Department of Veterans Affairs inspection findings for residential facilities furnishing treatment and rehabilitative services to eligible Veterans shall, to the extent necessary, be made available to all government agencies charged with the responsibility of licensing or otherwise regulating or inspecting such institutions.
K. CERTIFICATION & ACCREDITATION REQUIREMENTS
The C&A requirements do not apply, and a Security Accreditation Package is not required.
RECORDS MANAGEMENT LANGUAGE
Records Management Language for Contracts Required The following standard items relate to records generated in executing the contract and should be included in a typical Electronic Information Systems (EIS) procurement contract:
1. Citations to pertinent laws, codes and regulations such as 44 U.S.C chapters 21, 29, 31 and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and Part 1228.
2. Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.
3. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.
4. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.
5. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.
6. The Government Agency owns the rights to all data/records produced as part of this contract.
7. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.
8. Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].
9. No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.
10. Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.
36C26118Q0171
Page 1 of Page 1 of
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (JAN 2017)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or…