36C26118B0603-003.pdf
PDF 337 KB Posted
- Solicitation number
- 36C26118B0603
About this file
36C26118B0603 (4-11-2018)Final specs signed--Pages 1-100.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26118C0118-000.docx | DOCX document | |
| 36C26118B0603-0003000.docx | DOCX document | |
| 36C26118B0603-0003001.pdf | ||
| 36C26118B0603-0002002.pdf | ||
| 36C26118B0603-0002000.docx | DOCX document | |
| 36C26118B0603-0002001.docx | DOCX document | |
| 36C26118B0603-0001000.docx | DOCX document | |
| 36C26118B0603-0001001.pdf | ||
| 36C26118B0603-0001002.pdf | ||
| 36C26118B0603-007.pdf | ||
| 36C26118B0603-005.pdf | ||
| 36C26118B0603-001.docx | DOCX document | |
| 36C26118B0603-004.pdf | ||
| 36C26118B0603-006.docx | DOCX document | |
| 36C26118B0603-002.pdf | ||
| 36C26118B0603-000.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT
CONVERT PROCURED RESIDENTIAL LOTS TO SURFACE LEVEL PARKING
Project No. 654-823
OWNER
VA SIERRA NEVADA HEALTH CARE SYSTEM
975 Kirman Ave.
Reno, NV 98502
Contracting Officer: Brett Vegeto
(775)785-7179
Contracting Officer Representative: Philip Feiler
(775)326-5789
CONVERT PROCURED RESIDENTIAL LOTS TO SURFACE LEVEL PARKING
VA PROJECT NUMBER: 654-823
CIVIL ENGINEER CERTIFICATION
This project design has been prepared at the direction of Allen Westersund, PE, the responsible professional civil engineer licensed in the State of Nevada.
6/30/2018
PROJECT CIVIL ENGINEER
Allen Westersund, PE
PBS Engineering and Environmental 4412 SW Corbett Avenue Portland, Oregon 97239
Allen Westersund, PE
Digitally signed by Allen Westersund, PE Date: 2018.04.11 13:34:30 -07'00'
08-01-17
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 10 Table of Contents 00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-15 01 32 16.15 Project Schedules 04-13 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 29 Testing Laboratory Services 08-17 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17 02 65 00 Underground Storage Tank Removal 08-16 02 82 13 Asbestos Abatement 04-15
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
SPECIAL SPECIFICATIONS, REPORTS AND APPLICATIONS
200.00 Aggregates for Base Courses
202.00 Cement and Related Materials
205.00 Water
301.00 Removal of Existing Improvements
302.00 Subgrade Preparation
308.00 Aggregate Base Courses
312.00 Concrete Curbs, Gutters, Walks, Driveways and Alley
Returns
336.00 Inspection and Testing
337.00 Composition of Mixtures
GPR Investigation to Locate UST’s, Piping, or Tank
Related Items Pre-Demolition Hazardous Building Materials Survey
Report Geotechnical Engineering Report NV Energy Service Only Information Sheet
07-01-15
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GI1 Title Sheet VF1 Existing Conditions CD1 Site Demolition Plan CS1 Site Dimension Plan CG1 Grading Plan CG2 Erosion and Sediment Control Plan DT1 Details DT2 Details HA1 Hazardous Materials Abatement
- - - END - - -
11-01-15
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 USE OF ROADWAYS
1.15 TEMPORARY TOILETS
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures and site improvements, and furnish labor and materials and perform work to
Convert Procured Residential Lots to Surface Level Parking, as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of KF Davis Engineering, Inc. and PBS Engineering and
Environmental, Inc., as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All testing, inspections and fees shall be coordinated and paid for by the Contractor. Before placement and installation of work subject to tests by a testing laboratory, the Contractor shall notify the laboratory and the COR in sufficient time to enable testing laboratory personnel and the COR to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR or laboratory.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
01 00 00 -2
1.3 STATEMENT OF BID ITEM(S)
ITEM I, DEMOLITION OF ON-SITE IMPROVEMENTS
Work includes demolition and removal of: residence and garage buildings including footings, basement walls and slabs; concrete walkway, gravel surfacing, above and below ground utilities, utility services, fencing and gates, mailboxes, trees and vegetation, brick wall and all other materials lying outside City of Reno right-of-way. Scope shall also include asbestos abatement, underground storage tank abatement, filling and compaction of excavations, hazardous material sampling/testing, geotechnical sampling/testing and payment of all costs related to decommissioning gas and electrical services.
ITEM II, DEMOLITION OF OFF-SITE IMPROVEMENTS
Work includes demolition and removal of: concrete sidewalk, drive approaches, curb and gutter, asphalt pavement, sawcutting and all other improvements lying within City of Reno right-of-way. Scope shall also include all costs related to sampling, testing and inspection.
ITEM III, GENERAL ON-SITE CONSTRUCTION
Work includes excavation and off-haul, earthwork and general construction of: concrete perimeter curb, crushed rock parking surface, wheel stops, parking dividers and all other construction lying outside City of Reno right-of-way. Scope shall also include all costs related to sampling, testing and inspection.
ITEM IV, GENERAL OFF-SITE CONSTRUCTION
Work includes general construction of concrete curb and gutter, sidewalk, drive approach, sidewalk cross drain and all other construction lying within City of Reno right-of-way. Scope shall also include all costs related to sampling, testing and inspection.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
01 00 00 -3
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. No photography of VA premises is allowed without written permission of the Contracting Officer.
3. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or
01 00 00 -4 sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be within the limits of construction and out of public right-of-way.
E. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
F.Utilities Services: Where necessary to remove existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the utility provider. All such actions shall be coordinated with the Utility Company involved.
Gas and electrical services shall be removed by NV Energy. The contractor shall arrange a “Down and Out” for removal of overhead electrical service by calling NV Energy at (775)834-7590. Gas service and meter removal will require that the contractor file a “Service Only
Information Sheet” application. A blank copy of this application is included in the Specifications. The contractor shall include all costs related to decommissioning utilities in their bid.
G. Phasing:
Construction phasing is not required for this project.
H. Access Control Plans:
Prior to construction the Contractor shall assemble an Access Control
Plan detailing provisions for materials storage, site transportation, traffic control and pedestrian access within public right-of-way and obtain approval from VA and City of Reno. See Appendix A12 in the City of Reno Public Works Design Manual.
I. Construction Fence:
Before construction operations begin, Contractor shall provide a chain link construction fence, 6-foot minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches).
01 00 00 -5
Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
J. All existing utilities and underground structures within the project area shall be removed and disposed of. Abandoning underground utilities or structures in place will not be allowed.
K. To minimize interference of construction activities with flow of vehicular and pedestrian traffic, comply with the following:
1. Keep roads, walks and entrances to grounds clear of construction materials, debris and standing construction equipment and vehicles.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas in which construction will occur, and areas which are anticipated routes of access.
Contractor shall note any discrepancies between drawings and existing conditions at site and submit to COR in writing.
Contractor shall designate areas for working space, materials storage and routes of access to areas of work.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of legally at a certified landfill. Asbestos containing materials and other hazardous waste shall be disposed of per these specification, the plans, City of Reno and Washoe County requirements.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third
01 00 00 -6 party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove and replace existing facilities within City of Reno right-of-way as necessary to install new work. Materials and workmanship shall conform to City of Reno standards.
B. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing utilities and other existing improvements which are not scheduled for discontinuance or abandonment.
C. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site geotechnical and hazardous material investigations by PBS Engineering and Environmental, Inc.
(FAR 52.236-4)
01 00 00 -7
B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically in the geotechnical engineering report.
C. The site geotechnical and hazardous material investigations are included in the Special Specifications and shall be considered part of the contract documents.
D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work as indicated on the drawings and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.
B. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.14 USE OF ROADWAYS
A. For hauling, use only established public roads.
1.15 TEMPORARY TOILETS
A. Existing toilet and restroom facilities may not be used by the
Contractor’s workmen. Contractor shall provide portable chemical
01 00 00 -8 toilets in a number sufficient for the number of workmen on site.
Location of the toilets shall be approved by COR. Keep such places clean and free from flies and conduct regular cleaning and pumping in conformance with manufacturers recommended intervals.
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
A. The contractor shall be responsible for providing electrical power for use during construction.
B. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.
C. Water (for Construction and Testing): Furnish temporary water service by means of a water truck. Connection to City of Reno water services on-site shall not be allowed. Coordinate metering and filling of water truck from City of Reno fire hydrants with the City of Reno and VA.
Contractor shall be responsible for obtaining temporary construction meter and paying all fees to the City.
D. Fuel: Natural and LP gas will not be provided and shall be furnished and paid by the Contractor at Contractor's expense.
- - - E N D - - -
02-01-15
01 32 16.15 - 1
SECTION 01 32 16.15
PROJECT SCHEDULES
PART 1- GENERAL
1.1 DESCRIPTION:
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements
(Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COTR).
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.
C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.
1.3 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/events except procurement activities and meetings. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Prorate overhead, profit and general conditions on all work activities/events for the entire project length. The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish, late finish.
These cash flow curves will be used by the Contracting Officer to assist him in determining approval or disapproval of the cost loading.
Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
01 32 16.15 - 2
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in Article, FAR 52.232 – 5 (PAYMENT UNDER
FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.236 – 83 (PAYMENT
UNDER FIXED-PRICE CONSTRUCTION CONTRACTS).
C. In accordance with FAR 52.236 – 1 (PERFORMANCE OF WORK BY THE
CONTRACTOR) and VAAR 852.236 – 72 (PERFORMANCE OF WORK BY THE
CONTRACTOR), the Contractor shall submit, simultaneously with the cost per work activity/event of the construction schedule required by this
Section, a responsibility code for all activities/events of the project for which the Contractor's forces will perform the work.
D. The Contractor shall cost load work activities/events for all BID ITEMS including ASBESTOS ABATEMENT. The sum of each BID ITEM work shall equal the value of the bid item in the Contractors' bid.
1.4 PROJECT SCHEDULE REQUIREMENTS
A. Show on the project schedule the sequence of work activities/events required for complete performance of all items of work. The Contractor
Shall:
1. Show activities/events as:
a. Contractor's time required for submittal of shop drawings, templates, fabrication, delivery and similar pre-construction work.
b. Contracting Officer's and Architect-Engineer's review and approval of shop drawings, equipment schedules, samples, template, or similar items.
c. Interruption of VA Facilities utilities, delivery of Government furnished equipment, and rough-in drawings, project phasing and any other specification requirements.
d. Test, balance and adjust various systems and pieces of equipment, maintenance and operation manuals, instructions and preventive maintenance tasks.
e. VA inspection and acceptance activity/event with a minimum duration of five work days at the end of each phase and immediately preceding any VA move activity/event required by the contract phasing for that phase.
2. Show not only the activities/events for actual construction work for each trade category of the project, but also trade relationships to
01 32 16.15 - 3 indicate the movement of trades from one area, for at least five trades who are performing major work under this contract.
3. Break up the work into activities/events of a duration no longer than 20 work days each or one reporting period, except as to non-construction activities/events (i.e., procurement of materials, delivery of equipment, concrete and asphalt curing) and any other activities/events for which the COTR may approve the showing of a longer duration. The duration for VA approval of any required submittal, shop drawing, or other submittals will not be less than
20 work days.
4. Describe work activities/events clearly, so the work is readily identifiable for assessment of completion. Activities/events labeled
"start," "continue," or "completion," are not specific and will not be allowed. Lead and lag time activities will not be acceptable.
5. The schedule shall be generally numbered in such a way to reflect either discipline, phase or location of the work.
B. The Contractor shall submit the following supporting data in addition to the project schedule:
1. The appropriate project calendar including working days and holidays.
2. The planned number of shifts per day.
3. The number of hours per shift.
Failure of the Contractor to include this data shall delay the review of the submittal until the Contracting Officer is in receipt of the missing data.
C. To the extent that the Project Schedule or any revised Project Schedule shows anything not jointly agreed upon, it shall not be deemed to have been approved by the COTR. Failure to include any element of work required for the performance of this contract shall not excuse the
Contractor from completing all work required within any applicable completion date of each phase regardless of the COTR’s approval of the
Project Schedule.
D. Compact Disk Requirements and CPM Activity/Event Record Specifications:
Submit to the VA an electronic file(s) containing one file of the data required to produce a schedule, reflecting all the activities/events of the complete project schedule being submitted.
01 32 16.15 - 4
1.5 PAYMENT TO THE CONTRACTOR:
A. Monthly, the contractor shall submit an application and certificate for payment using VA Form 10. reflecting updated schedule activities and cost data in accordance with the provisions of the following Article, PAYMENT AND PROGRESS REPORTING, as the basis upon which progress payments will be made pursuant to Article, FAR 52.232 – 5 (PAYMENT
UNDER FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.236 – 83
(PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS). The Contractor shall be entitled to a monthly progress payment upon approval of estimates as determined from the currently approved updated project schedule. Monthly payment requests shall include: a listing of all agreed upon project schedule changes and associated data, minus retainage; and an electronic file (s) of the resulting monthly updated schedule.
B. Approval of the Contractor’s monthly Application for Payment shall be contingent, among other factors, on the submittal of a satisfactory monthly update of the project schedule.
1.6 PAYMENT AND PROGRESS REPORTING
A. Monthly schedule update meetings will be held on dates mutually agreed to by the COTR and the Contractor. Contractor and their CPM consultant
(if applicable) shall attend all monthly schedule update meetings. The
Contractor shall accurately update the Project Schedule and all other data required and provide this information to the COTR three work days in advance of the schedule update meeting. Job progress will be reviewed to verify:
1. Actual start and/or finish dates for updated/completed activities/events.
2. Remaining duration for each activity/event started, or scheduled to start, but not completed.
3. Logic, time and cost data for change orders, and supplemental agreements that are to be incorporated into the Project Schedule.
4. Changes in activity/event sequence and/or duration which have been made, pursuant to the provisions of following Article, ADJUSTMENT OF
CONTRACT COMPLETION.
5. Completion percentage for all completed and partially completed activities/events.
6. Logic and duration revisions required by this section of the specifications.
01 32 16.15 - 5
7. Activity/event duration and percent complete shall be updated independently.
1.7 RESPONSIBILITY FOR COMPLETION
A. If it becomes apparent from the current revised monthly progress schedule that phasing or contract completion dates will not be met, the
Contractor shall execute some or all of the following remedial actions:
1. Increase construction manpower in such quantities and crafts as necessary to eliminate the backlog of work.
2. Increase the number of working hours per shift, shifts per working day, working days per week, the amount of construction equipment, or any combination of the foregoing to eliminate the backlog of work.
3. Reschedule the work in conformance with the specification requirements.
B. Prior to proceeding with any of the above actions, the Contractor shall notify and obtain approval from the COTR for the proposed schedule changes. If such actions are approved, the representative schedule revisions shall be incorporated by the Contractor into the Project
Schedule before the next update, at no additional cost to the
Government.
1.8 ADJUSTMENT OF CONTRACT COMPLETION
A. The contract completion time will be adjusted only for causes specified in this contract. Request for an extension of the contract completion date by the Contractor shall be supported with a justification, CPM data and supporting evidence as the COTR may deem necessary for determination as to whether or not the Contractor is entitled to an extension of time under the provisions of the contract. Submission of proof based on revised activity/event logic, durations (in work days) and costs is obligatory to any approvals. The schedule must clearly display that the Contractor has used, in full, all the float time available for the work involved in this request. The Contracting
Officer's determination as to the total number of days of contract extension will be based upon the current computer-produced calendar-dated schedule for the time period in question and all other relevant information.
B. The Contractor shall submit each request for a change in the contract completion date to the Contracting Officer in accordance with the provisions specified under FAR 52.243 – 4 (Changes) and VAAR 852.236 –
01 32 16.15 - 6
88 (Changes – Supplemental). The Contractor shall include, as a part of each change order proposal, a sketch showing all CPM logic revisions, duration (in work days) changes, and cost changes, for work in question and its relationship to other activities on the approved network diagram.
C. All delays due to non-work activities/events such as RFI’s, WEATHER, STRIKES, and similar non-work activities/events shall be analyzed on a month by month basis.
05-01-17
01 33 23 - 1
SECTION 01 33 23
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
PART 1 – GENERAL
1.1 DESCRIPTION
A. This specification defines the general requirements and procedures for submittals. A submittal is information submitted for VA review to establish compliance with the contract documents.
B. Detailed submittal requirements are found in the technical sections of the contract specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective technical specifications at no additional cost to the government.
C. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.
1.2 DEFINITIONS
A. Preconstruction Submittals: Submittals which are required prior to issuing contract notice to proceed or starting construction. For example, Certificates of insurance; Surety bonds; Site-specific safety plan; Construction progress schedule; Schedule of values; Submittal register; List of proposed subcontractors.
B. Shop Drawings: Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be integrated and coordinated.
C. Product Data: Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions, and brochures, which describe and illustrate size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work. Samples of warranty language when the contract requires extended product warranties.
01 33 23 - 2
D. Samples: Physical examples of materials, equipment, or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged. Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project. Field samples and mock-ups constructed to establish standards by which the ensuing work can be judged.
E. Design Data: Calculations, mix designs, analyses, or other data pertaining to a part of work.
F. Test Reports: Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work. Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
G. Certificates: Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor. The purpose is to document procedures, acceptability of methods, or personnel qualifications for a portion of the work.
H. Manufacturer's Instructions: Pre-printed material describing installation of a product, system, or material, including special notices and MSDS concerning impedances, hazards, and safety precautions.
I. Manufacturer's Field Reports: Documentation of the testing and verification actions taken by manufacturer's representative at the job site on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must indicate whether the material, product, or system has passed or failed the test.
J. Operation and Maintenance Data: Manufacturer data that is required to operate, maintain, troubleshoot, and repair equipment, including manufacturer's help, parts list, and product line documentation. This data shall be incorporated in an operations and maintenance manual.
K. Closeout Submittals: Documentation necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a phase of construction on a multi-phase contract.
1.3 SUBMITTAL REGISTER
A. The submittal register will list items of materials for which submittals are required by the specifications. This list may not be all inclusive
01 33 23 - 3 and additional submittals may be required by the specifications. The
Contractor is not relieved from supplying submittals required by the contract documents but which have been omitted from the submittal register.
B. The submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period.
C. The VA will provide the initial submittal register in electronic format. Thereafter, the Contractor shall track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the
VA.
D. The Contractor shall update the submittal register as submittal actions occur and maintain the submittal register at the project site until final acceptance of all work by Contracting Officer.
E. The Contractor shall submit formal monthly updates to the submittal register in electronic format. Each monthly update shall document actual submission and approval dates for each submittal.
1.4 SUBMITTAL SCHEDULING
A. Submittals are to be scheduled, submitted, reviewed, and approved prior to the acquisition of the material or equipment.
B. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow time for potential resubmittal.
C. No delay costs or time extensions will be allowed for time lost in late submittals or resubmittals.
D. All submittals are required to be approved prior to the start of the specified work activity.
1.5 SUBMITTAL PREPARATION
A. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
B. Collect required data for each specific material, product, unit of work, or system into a single submittal. Prominently mark choices, options, and portions applicable to the submittal. Partial submittals will not be accepted for expedition of construction effort. Submittal will be returned without review if incomplete.
01 33 23 - 4
C. If available product data is incomplete, provide Contractor-prepared documentation to supplement product data and satisfy submittal requirements.
D. All irrelevant or unnecessary data shall be removed from the submittal to facilitate accuracy and timely processing. Submittals that contain the excessive amount of irrelevant or unnecessary data will be returned with review.
E. Provide transmittal form SSC 3000 for each submittal.
F. The Contractor is responsible for reviewing and certifying that all submittals are in compliance with contract requirements before submitting for VA review. Proposed deviations from the contract requirements are to be clearly identified. All deviations submitted must include a side by side comparison of item being proposed against item specified. Failure to point out deviations will result in the VA requiring removal and replacement of such work at the Contractor's expense.
G. Stamp, sign, and date each submittal transmittal form indicating action taken.
1.6 SUBMITTAL FORMAT AND TRANSMISSION
A. Provide submittals in electronic format, with the exception of material samples. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer.
B. Compile the electronic submittal file as a single, complete document.
Name the electronic submittal file specifically according to its contents.
C. Electronic files must be of sufficient quality that all information is legible. Generate PDF files from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required.
D. Provide electronic documents over 5MB through an electronic FTP file sharing system such as Builder’s Exchange or Procore. Confirm that the electronic FTP file sharing system can be accessed from the VA computer network. The Contractor is responsible for setting up, providing, and maintaining the electronic FTP file sharing system for the construction contract period of performance and three months beyond the contractor period of performance.
01 33 23 - 5
E. Provide hard copies of submittals when requested by the Contracting
Officer. Up to 3 additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the VA.
1.7 SAMPLES
A. Samples of imported fill, crushed rock, granular material and all other applicable materials shall be submitted for testing to the laboratory by the contractor. Quantities provided shall be in accordance with direction of the testing laboratory.
B. Product data for concrete material shall be submitted for review.
C. Product data and shop drawings for all fabricated items shall be submitted for review.
1.8 OPERATION AND MAINTENANCE DATA
A. Operation and maintenance data is not required for this project.
1.9 TEST REPORTS
Post-construction test reports for soil compaction and soil analysis are required for this project. See Sections 02 65 00 and 31 20 11.
1.10 VA REVIEW OF SUBMITTALS AND RFIS
A. The VA will review all submittals for compliance with the technical requirements of the contract documents. The Architect-Engineer for this project will assist the VA in reviewing all submittals and determining contractual compliance. Review will be only for conformance with the applicable codes, standards and contract requirements.
B. Period of review for submittals begins when the VA COR receives submittal from the Contractor.
C. Period of review for each resubmittal is the same as for initial submittal.
D. VA review period is 15 working days for submittals.
E. VA review period is 10 working days for RFIs.
F. The VA will return submittals to the Contractor with the following notations:
1. "Approved": authorizes the Contractor to proceed with the work covered.
01 33 23 - 6
2. "Approved as noted": authorizes the Contractor to proceed with the work covered provided the Contractor incorporates the noted comments and makes the noted corrections.
3. "Disapproved, revise and resubmit": indicates noncompliance with the contract requirements or that submittal is incomplete. Resubmit with appropriate changes and corrections. No work shall proceed for this item until resubmittal is approved.
4. "Not reviewed": indicates submittal does not have evidence of being reviewed and approved by Contractor or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals after taking appropriate action.
1.11 APPROVED SUBMITTALS
A. The VA approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.
B. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.
C. After submittals have been approved, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
D. Retain a copy of all approved submittals at project site, including approved samples.
1.12 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
02-01-17
01 35 26 -1
SECTION 01 35 26
SAFETY REQUIREMENTS
TABLE OF CONTENTS
TABLE OF CONTENTS
1.1 APPLICABLE PUBLICATIONS:
1.2 DEFINITIONS:
1.3 REGULATORY REQUIREMENTS:
1.4 ACCIDENT PREVENTION PLAN (APP):
1.5 ACTIVITY HAZARD ANALYSES (AHAs):
1.6 PRECONSTRUCTION CONFERENCE:
1.7 “SITE SAFETY AND HEALTH OFFICER” (SSHO) and “COMPETENT PERSON” (CP):
1.8 TRAINING:
1.9 INSPECTIONS:
1.10 ACCIDENTS, OSHA 300 LOGS, AND MAN-HOURS:
1.11 PERSONAL PROTECTIVE EQUIPMENT (PPE):
1.12 INFECTION CONTROL
1.13 FIRE SAFETY
1.14 ELECTRICAL
1.15 FALL PROTECTION
1.16 SCAFFOLDS AND OTHER WORK PLATFORMS
1.17 EXCAVATION AND TRENCHES
1.18 CRANES
1.19 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
1.20 CONFINED SPACE ENTRY
1.21 WELDING AND CUTTING
1.22 LADDERS
01 35 26 -2
SECTION 01 35 26
SAFETY REQUIREMENTS
1.1 APPLICABLE PUBLICATIONS:
A. Latest publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
B. American Society of Safety Engineers (ASSE):
A10.1-2011...........Pre-Project & Pre-Task Safety and Health
Planning
A10.34-2012..........Protection of the Public on or Adjacent to
Construction Sites
A10.38-2013..........Basic Elements of an Employer’s Program to
Provide a Safe and Healthful Work Environment
American National Standard Construction and
Demolition Operations
C. American Society for Testing and Materials (ASTM):
E84-2013.............Surface Burning Characteristics of Building
Materials
D. The Facilities Guidelines Institute (FGI):
FGI Guidelines-2010Guidelines for Design and Construction of
Healthcare Facilities
E. National Fire Protection Association (NFPA):
10-2013..............Standard for Portable Fire Extinguishers
30-2012..............Flammable and Combustible Liquids Code
51B-2014.............Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2014..............National Electrical Code
70B-2013.............Recommended Practice for Electrical Equipment
Maintenance
70E-2015 ............Standard for Electrical Safety in the Workplace
99-2012..............Health Care Facilities Code
241-2013.............Standard for Safeguarding Construction, Alteration, and Demolition Operations
F. The Joint Commission (TJC)
TJC Manual ..........Comprehensive Accreditation and Certification
Manual
G. U.S. Nuclear Regulatory Commission
01 35 26 -3
10 CFR 20 ...........Standards for Protection Against Radiation
H. U.S. Occupational Safety and Health Administration (OSHA):
29 CFR 1904 .........Reporting and Recording Injuries & Illnesses
29 CFR 1910 .........Safety and Health Regulations for General
Industry
29 CFR 1926 .........Safety and Health Regulations for Construction
Industry
CPL 2-0.124..........Multi-Employer Citation Policy
I. VHA Directive 2005-007
1.2 DEFINITIONS:
A. Critical Lift. A lift with the hoisted load exceeding 75% of the crane’s maximum capacity; lifts made out of the view of the operator
(blind picks); lifts involving two or more cranes; personnel being hoisted; and special hazards such as lifts over occupied facilities, loads lifted close to power-lines, and lifts in high winds or where other adverse environmental conditions exist; and any lift which the crane operator believes is critical.
B. OSHA “Competent Person” (CP). One who is capable of identifying existing and predictable hazards in the surroundings and working conditions which are unsanitary, hazardous or dangerous to employees, and who has the authorization to take prompt corrective measures to eliminate them (see 29
CFR 1926.32(f)).
C. "Qualified Person" means one who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training and experience, has successfully demonstrated his ability to solve or resolve problems relating to the subject matter, the work, or the project.
D. High Visibility Accident. Any mishap which may generate publicity or high visibility.
E. Accident/Incident Criticality Categories:
No impact – near miss incidents that should be investigated but are not required to be reported to the VA;
Minor incident/impact – incidents that require first aid or result in minor equipment damage (less than $5000). These incidents must be investigated but are not required to be reported to the VA;
Moderate incident/impact – Any work-related injury or illness that results in:
01 35 26 -4
1. Days away from work (any time lost after day of injury/illness onset);
2. Restricted work;
3. Transfer to another job;
4. Medical treatment beyond first aid;
5. Loss of consciousness;
6. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (5) above or,
7. Any incident that leads to major equipment damage (greater than $5000).
These incidents must be investigated and are required to be reported to the VA;
Major incident/impact – Any mishap that leads to fatalities, hospitalizations, amputations, and losses of an eye as a result of contractors’ activities. Or any incident which leads to major property damage (greater than $20,000) and/or may generate publicity or high visibility. These incidents must be investigated and are required to be reported to the VA as soon as practical, but not later than 2 hours after the incident.
F. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
1.3 REGULATORY REQUIREMENTS:
A. In addition to the detailed requirements included in the provisions of this contract, comply with 29 CFR 1926, comply with 29 CFR 1910 as incorporated by reference within 29 CFR 1926, comply with ASSE A10.34, and all applicable federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern except with specific approval and acceptance by the
Contracting Officer Representative or Government Designated Authority
(Safety Officer).
01 35 26 -5
1.4 ACCIDENT PREVENTION PLAN (APP):
A. The APP (aka Construction Safety & Health Plan) shall interface with the Contractor's overall safety and health program. The APP shall be submitted by the contractor to the COTR prior to the start of any physical work activities on site. Include any portions of the
Contractor's overall safety and health program referenced in the APP in the applicable APP element and ensure it is site-specific. The
Government considers the Prime Contractor to be the "controlling authority" for all worksite safety and health of each subcontractor(s).
Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
B. The APP shall be prepared as follows:
1. Written in English by a qualified person who is employed by the
Prime Contractor articulating the specific work and hazards pertaining to the contract (model language can be found in ASSE
A10.33). Specifically articulating the safety requirements found within these VA contract safety specifications.
2. Address both the Prime Contractors and the subcontractors work operations.
3. State measures to be taken to control hazards associated with materials, services, or equipment provided by suppliers.
4. Address all the elements/sub-elements and in order as follows:
a. SIGNATURE SHEET. Title, signature, and phone number of the following:
1) Plan preparer (Qualified Person such as corporate safety staff person or contracted Certified Safety Professional with construction safety experience);
2) Plan approver (company/corporate officers authorized to obligate the company);
3) Plan concurrence (e.g., Chief of…