S04 -Site Visit Meeting Doc 10.25.docx
DOCX document 18 KB Posted
- Attached to
- Z2DA--T2 660-22-357 Support Automated Inventory System Install Federal contract opportunity
- Solicitation number
- 36C25922R0097
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 660-22-357 Site Visit Attendance 2022 10 25.pdf | ||
| Attachment 1 Amended Data and Power Drop Locations.pdf | ||
| 660-21-706 Response to RFI Questions.pdf | ||
| 36C25922R0097 0002.docx | DOCX document | |
| Salt Lake City VA - Power _ Data Estimates 10-6-22 .xlsx | XLSX spreadsheet | |
| 36C25922R0097 0001.docx | DOCX document | |
| Engineering Building Parking Map.pdf | ||
| 660-22-357 Site Visit Attendance 2022 09 23.pdf | ||
| S04 -Site Visit Meeting Doc.docx | DOCX document | |
| Past Performance Questionnaire.docx | DOCX document | |
| 660-22-357 SPECS.pdf | ||
| 36C25922R0097_1.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Meeting
FOR
The contractor is to provide all labor, tools, materials, equipment and supervision required to Support Automated Inventory System Install at the Salt Lake City VA Medical Center.
Location: Salt Lake City VA Medical Center
AGENDA:
· Introduction of Christina Beeler-Blackburn CO, Brandon Wilkins COR, and Sylwia Zak CS
· The pre-bid meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send Quote:
· Electronic submissions to sylwia.zak@va.gov
· Pertinent Dates:
· Questions due on 11/1/2022 at 1 PM MT via email
· Quotes due on 11/15/2022 at 11 AM MT via email
· Prospective bidders are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective bidders are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded
· Masks are required at all times while on VA property. Entrance screenings will be conducted each day.
· Confirmation of construction range is between $250,000.00 and $500,000.00
· Bid Guarantee & Payment/Performance Bonds: Are required at 20% of bid price of $3,000,000.00 whichever is less.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 90 calendar days.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.