Questions and Answers.pdf

PDF 74 KB Posted

Attached to
Mobile Chiller Tie - In
Solicitation number
36C25725Q0099
Issued by

About this file

This document contains Questions and Answers related to a federal contract opportunity for a Mobile Chiller Tie-In at Building 202 for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17.

The key details include: There are no specific requirements for the type and size of the tie-ins, a temporary chiller is not included and will not be bid separately, the distance from the chilled water pipe tie-in to the termination point outside the loading dock is to be determined by the vendor during the site visit, the amount of 6-inch pipe to be installed is also to be determined by the vendor during the site visit, the piping is to be installed under the floor in a non-confined space, and the jacketing material for exterior insulation is not specified - any material rated for outside/exterior use is acceptable. No sketches or photos will be provided, as the vendor is expected to determine the details during the site visit.

View the file

Other files

File Type Posted
S02 36C25725Q0099.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q: Do you have any specifica ons for the type and size of Tie‐In’s for this bid?

A: This can be answered in the SOW.

Q: Is a temporary chiller included in this bid? If not, will that be bid separately?

A: No and no.

Q: The scope of work does not define the distance from the CH Water Pipe e in to the termina on point outside the loading dock. Can you provide a sketch or as built that shows this rou ng?

A: This can be determined by the vendor during the site visit.

Q: How many feet of 6in. pipe is to be installed?

Q: Since the scope states to run under the floor, please define if the piping is to be installed above the ceiling of the floor below or if this is a space without a ceiling or is the pipe to be run in a crawl space below the floor? If a crawl space, how high is the space? Is it considered a confined space?

A: Under floor; not confined space.

Q: Please provide a sketch or phots of the pump and e in points for the piping.

Q: Please specify the jacke ng material to be used for exterior insula on.

A: Not specific; any material rated for outside/exterior use.

File details come from the government source that posted it. Updated .