36C25619R0071-003.pdf
PDF 4 MB Posted
- Solicitation number
- 36C25619R0071
About this file
36C25619R0071 Contract Specifications.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25619C0094-P00001000.docx | DOCX document | |
| 36C25619C0094-001.docx | DOCX document | |
| 36C25619R0071-0002005.docx | DOCX document | |
| 36C25619R0071-0002006.pdf | ||
| 36C25619R0071-0002001.pdf | ||
| 36C25619R0071-0002000.docx | DOCX document | |
| 36C25619R0071-0002004.pdf | ||
| 36C25619R0071-0002002.pdf | ||
| 36C25619R0071-0002003.pdf | ||
| 36C25619R0071-0001003.pdf | ||
| 36C25619R0071-0001002.docx | DOCX document | |
| 36C25619R0071-002.pdf | ||
| 36C25619R0071-006.docx | DOCX document | |
| 36C25619R0071-004.pdf | ||
| 36C25619R0071-001.docx | DOCX document | |
| 36C25619R0071-005.docx | DOCX document | |
| 36C25619R0071-000.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
G.V. (SONNY) MONTGOMERY VAMC
1500 EAST WOODROW WILSON DRIVE
JACKSON, MS 39216
PROJECT No. 586-18-118
NEW WATER WELL & TREATMENT STATION
AND
REPLACEMENT OF ELEVATED
WATER STORAGE TANK
100% SUBMISSION
SPECIFICATIONS
March 14, 2019
A/E Team
5190 Canal Blvd Ste 201 New Orleans, LA 70124
504-835-8013
TABLE OF CONTENTS 1
SPECIFICATIONS
PROJECT No. 586-18-118
NEW WATER WELL & TREATMENT STATION
AND
REPLACEMENT OF ELEVATED WATER STORAGE TANK
G.V. SONNY MONTGOMERY VAMC
JACKSON, MISSISSIPPI
March 14, 2019
TABLE OF CONTENTS
DIVISION 01: GENERAL REQUIREMENTS
Section 01 10 00 Summary Section 01 30 00 Administrative Requirements Section 01 32 16 Construction Progress Schedule Section 01 33 00 Submittal Procedures Section 01 40 00 Quality Requirements Section 01 50 00 Temporary Facilities and Controls Section 01 57 13 Temporary Erosion Checks Section 01 57 23 Silt Fence Section 01 60 00 Product Requirements Section 01 70 00 Execution and Closeout Requirements Section 01 71 13 Mobilization – Demobilization
DIVISION 03: CONCRETE
Section 03 00 00 Concrete General
DIVISION 04: MASONRY
Section 04 22 00 New Well Equipment House
DIVISION 07: THERMAL AND MOISTURE PROTECTION
Section 07 41 13 Metal Roofing
DIVISION 26: ELECTRICAL
Section 26 00 10 Electrical General Provisions Section 26 05 05 Selective Demolition for Electrical Section 26 05 19 Conductors (Low Voltage, 600 Volts) Section 26 05 26 Grounding Section 26 05 29 Outlet Boxes, Junction Boxes and Gutters Section 26 05 33 Raceways Section 26 24 16 Panelboards Section 26 27 26 Switches and Receptacles Section 26 28 19 Disconnects (Motor & Circuit & Separate Circuit Breakers) Section 26 41 00 Lightning Protection System (Additions & Modifications)
DIVISION 31: EARTHWORK
Section 31 00 00 Earthwork
DIVISION 32: EXTERIOR IMPROVEMENTS
Section 32 12 16 Asphalt Paving Section 32 17 23 Pavement Markings Section 32 31 13 Welded Ornamental Fence System Section 32 92 00 Seeding, Fertilizing and Mulching
DIVISION 33: UTILITIES
Section 33 09 10 Process Instrumentation and Controls
TABLE OF CONTENTS 2
Section 33 11 13 Potable Water Wells Section 33 14 00 Water Distribution System Section 33 16 11 Composite Elevated Water Storage Tank Section 33 16 96 Tank Hydrodynamic Mixing System Section 33 40 00 Storm Drainage
DIVISION 40: PROCESS PIPE, VALVES & INSTRUMENTATION
Section 40 42 13 Piping Insulation
DIVISION 46: WATER & WASTEWATER EQUIPMENT
Section 46 31 11 Chlorination System
01 10 00-1
SECTION 01 10 00
SUMMARY
PART 1- GENERAL
1-01 PROJECT SUMMARY
A. The Project:
1. Name: G.V. (Sonny) Montgomery VAMC
New Water Well & Treatment Station
Jackson, Mississippi
B. The Project will consist of the following:
1. Construction Drawings dated March 14, 2019.
2. Project Manual dated March 14, 2019.
3. Issue Date – March 27, 2019
1-02 SECTION INCLUDES
A. Contract Description.
B. Precedence of Documents.
C. Work Limitations.
D. Contractor use of site and premises.
E. Contractor's duties.
F. Time of Completion.
G. Construction Progress Scheduling.
H. Delays, Extension of Time and Liquidated Damages;
I. Selection of Superintendent.
J. Alternates.
1-03 CONTRACT DESCRIPTON
A. Contract Type:Stipulated sum as described in AIA Document A101 -
Owner/Contractor Agreement.
1-04 PRECEDENCE OF DOCUMENTS
A. The Contract Documents are complimentary; what is called for by one is as binding as if called for by all. In resolving conflicts, errors and discrepancies, the documents shall be given precedence in the following order: Agreement, Condition of Contract, Specifications and Drawings. Within the project manual the order of precedence shall be as follows: Addenda, Instruction to Bidders, General Conditions, Supplementary Conditions, General Requirements, Technical
Provisions. Figured dimension drawings shall govern scaled dimensions and detailed drawings shall govern over general drawings. Any work that may reasonably be inferred from the specifications or drawings as being required to
01 10 00-2 produce the intended results shall be supplied whether or not it is specifically called for. Work, materials or equipment described in works which so applied have a well-known technical or trade meaning shall be deemed to refer to such recognized standards.
1-05 WORK LIMITATIONS
A. Confine all work to areas designated on the construction drawings dated March
14, 2019.
B. Contractor parking shall be coordinated with the Owner.
C. Do not use the Owner's parking lot, elevator, stairs, dining facilities, sanitary facilities and storage facilities. The General Contractor will be required to leave the existing parking lot, service area, and fire lane open for traffic at all times.
D. Utility Outages and Shutdown: Notify Owner and Engineer 7 days prior to scheduled shutdown/interruption of existing services/utilities. Contractor shall receive written authorization prior to proceeding with shutdown.
E. Construct work in phases to accommodate Owner's occupancy requirements during the construction period, coordinate construction schedule and operations with Owner and Engineer.
F. Cooperate with Owner to minimize conflict, and to facilitate Owner's operations.
Schedule work to accommodate the Owner's occupancy.
1-06 CONTRACTOR'S USE OF PREMISES
A. Confine operations at site to areas permitted by:
1. Law.
2. Ordinances.
3. Permits.
4. Contract Documents.
5. Owner.
B. Do not unreasonably encumber site with materials or equipment.
C. Do not load structure with weight that will endanger structure.
D. Assume full responsibility for protection and safekeeping of products stored on premises.
E. Move any stored products which interfere with operations of Owner or other
Contractors.
01 10 00-3
F. Obtain and pay for use of additional storage or work areas needed for operations.
G. Limit use of work and storage to the area indicated on the drawings.
1-07 CONTRACTOR'S DUTIES
A. Except as specifically noted, provide and pay for:
1. Labor, materials, and equipment.
2. Tools, construction equipment and machinery.
3. Water, heat and utilities required for construction.
4. Other facilities and services necessary for proper execution and completion of work.
B. Pay legally required sales, consumer, use payroll, privilege and other taxes.
C. Secure and pay for, as necessary for proper execution and completion of work, and as applicable at the time of the receipt of the bids:
1. Permits.
2. Government Fees.
3. Licenses.
D. Give required notices.
E. Comply with codes, ordinances, rules, regulations, orders and other legal requirements of public authorities which bear on performance of work.
F. Promptly submit written notice to Professional of observed variance of Contract
Documents for legal requirements. It is not the Contractor's responsibility to make certain that drawings and specifications comply with codes and regulations. Appropriate modifications to Contract Documents will adjust necessary changes. Assume responsibility for work known to be contrary to such requirements, without notice.
G. Enforce strict discipline and good order among employees. Do not employ or work unfit persons, or persons not skilled to assigned task.
H. Provide a written safety plan.
1-08 TIME OF COMPLETION
A. It is the Owner's intent that the construction start immediately after signing the
Contract or on the date named in the Engineer's written order to proceed and all work of the Contract to be completed as expeditiously as possible and within the time mutually agreed upon with the Owner.
01 10 00-4
B. Time of completion is of the essence of the Contract and shall be closely coordinated as outlined in the Construction Progress Scheduling.
1-09 CONSTRUCTION PROGRESS SCHEDULING
A. Critical Path Method (CPM) of construction scheduling will be employed in accordance with the following detailed specifications:
1. A monthly review of the CPM with the Architect and all principal sub-contractors will be held at the General Contractor's field office.
2. A monthly update of the CPM will be submitted with the General
Contractor's request for payment. Failure to furnish this update may be grounds for withholding payment until the update is furnished.
3. Each principal sub-contractor will submit monthly request for payment to the General Contractor and copies of these requests for payment will be furnished with the CPM and the Contractor's Request for Payment.
Should any principal sub-contractor fail to furnish this request for payment, it may be grounds for withholding payment until such items are furnished.
4. Should construction fall behind schedule over 30 days as revealed by the
CPM, the Engineer will then require the General Contractor to provide overtime or additional shifts as is required to provide additional crews or additional overtime may be cause for withholding payment until such time as the Contractor adequately mans the project.
1-10 DELAYS, EXTENSION OF TIME, AND LIQUIDATED DAMAGES
A. It is hereby understood and mutually agreed that the order to proceed issued by the Engineer will be the start of the total time involved for construction of the project. On acceptance of building by the Owner, and issuance of a Certificate of Substantial Completion by the Engineer, the Time Clause of this contract shall terminate.
B. If the said Contractor shall neglect, fail or refuse to complete the work within the time herein specified, then the Contractor does hereby agree as a part of the consideration for the awarding of this Contract to pay the Owner the amount specified herein as a penalty in lieu of liquidated damages for such breach of contract as hereinafter set forth for each and every calendar day that the Contract shall be in default after the time allotted herein for completing the work.
C. It is further agreed that time is of the essence of each and every portion of the
Contract and of the specifications wherein a definite and certain length of time is fixed for the performance of any act whatsoever, but where hereunder an additional time is allowed by the Engineer for the completion of any work, the new time limit fixed by such extension shall not be charged with liquidated damages.
01 10 00-5
D. If the Contractor is delayed at any time in the progress of the work by an act or neglect of the Owner, by the Engineer, or of any employee or either, then the time of completion shall be extended for such reasonable time as the Engineer at the Owner's direction may decide.
E. All work of this Contract· shall be substantially completed and ready for Owners occupancy in calendar days based on commencement date stipulated in Notice to Proceed. If the Contractor shall neglect, fail, or refuse to complete work by the time specified without properly obtained extension of time, the Contractor will be required to pay liquidated damages to the Owner in the amount of
$500/day.
F. It is mutually agreed between the Contractor, Owner and Engineer that if the
Contractor cannot obtain pieces of equipment, materials or sub-contracts because of a strike of the manufacturer, railroads, transportation, or of the sub-contractor, then the General Contractor may request that the Engineer accept a substitution to the Owner. If the Owner elects not to accept the substitution, the time of completion may be extended until such time as the material becomes available or supplier or sub-contractor can properly man the project. If the
Owner elects to accept the substitution of materials, or subcontractors, then the
Contractor will proceed with the allowed substitution without extension. If the
Owner elects not to accept the substitution of materials or subcontractor and directs the Contractor to complete the building without these facilities, the
General Contractor will proceed with the building and complete same without the above-mentioned material supplier or sub- contractor without extension of completion time.
1-11 SELECTION OF SUPERINTENDENT
A. The Owner reserves the right to approve the selection of the Contractor's superintendent prior to beginning construction. The Contractor shall submit for the Owner's review a listing of projects that the proposed superintendent has completed.
PART 2 - PRODUCTS
Not Used.
PART 3 - EXECUTION
Not Used
**END OF SECTION**
01 30 00-1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 - GENERAL
1-01 SECTION INCLUDES
A. Coordination and project conditions.
B. Field engineering.
C. Preconstruction meeting.
D. Progress meetings.
E. Pre-installation meetings.
F. Cutting and patching.
G. Special procedures.
1-02 COORDINATION AND PROJECT CONDITIONS
A. Coordinate scheduling, submittals, and Work of various sections of Project
Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.
B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, operating equipment.
C. Coordinate space requirements, supports, and installation of mechanical and electrical work indicated diagrammatically on Drawings. Follow routing shown for pipes, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
D. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion.
E. Coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.
1-03 FIELD ENGINEERING
01 30 00-2
A. Verify set-backs and easements; confirm drawing dimensions and elevations.
B. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering practices.
1-04 PRECONSTRUCTION MEETING
A. Owner and Engineer will schedule meeting after Notice to Proceed.
B. Attendance Required: Owner, Engineer, Contractor, Contractor's Superintendent and Major sub-contractor.
C. Agenda:
1. Execution of Owner-Contractor Agreement.
2. Submission of executed bonds and insurance certificates.
3. Distribution of Contract Documents.
4. Submission of list of Subcontractors, list of products, schedule of values, and progress schedule.
5. Designation of personnel representing parties in Contract, and
Architect/Engineer.
6. Procedures and processing of field decisions, submittals, substitutions, Applications for payments, proposal request, Change Orders, and
Contract closeout procedures.
7. Use of premises by Owner and Contractor.
8. Owner's requirements.
9. Construction facilities and controls provided by Owner.
10. Temporary utilities.
11. Security and housekeeping procedures.
12. Schedules.
13. Applications for Payment procedures.
14. Procedures for testing.
15. Procedures for maintaining record of documents.
16. Requirements for start-up equipment.
17. Inspection and acceptance of equipment put into service during construction period.
D. Engineer will record minutes and distribute copies within five (5) working days after meeting to participants, with copies to Owner, General Contractor and those affected by decisions made.
1-05 PROGRESS MEETINGS
A. General Contractor to schedule and administer meetings throughout progress of the Work at maximum monthly intervals.
B. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.
01 30 00-3
C. Attendance Required: Job superintendent, major subcontractors and suppliers, Owner, Engineer, as appropriate to agenda topics for each meeting.
D. Agenda:
1. Review minutes of previous meetings.
2. Review of Work progress.
3. Field observations, problems, and decisions.
4. Identification of problems impeding planned progress.
5. Review of submittals schedule and status of submittals.
6. Review of off-site fabrication and delivery schedules.
7. Maintenance of progress schedule.
8. Corrective measures to regain projected schedules.
9. Planned progress during succeeding work period.
10. Coordination of projected progress.
11. Maintenance of quality and work standards.
12. Effect of proposed changes on progress schedule and coordination.
13. Other business relating to Work.
E. Record minutes and distribute copies within three working days after meeting to participants, with copies to Engineer, Owner, and those affected by decisions made.
1-06 PRE-INSTALLATION MEETINGS
A. When required in individual specification sections, convene pre-installation meetings at Project site prior to commencing work of specific section.
B. Require attendance of parties directly affecting, or affected by, Work of specific section.
C. Notify Engineer seven days in advance of meeting date.
D. Prepare agenda and preside at meeting:
1. Review conditions of installation, preparation and installation procedures.
2. Review coordination with related work.
E. General Contractor will record minutes and distribute copies within three days after meeting to participants, with copies to Engineer, Owner, and those affected by decisions made.
PART 2 - PRODUCTS
PART 3 - EXECUTION
01 30 00-4
3-01 CUTTING AND PATCHING
A. Employ·skilled and experienced installer to perform cutting and patching.
B. Submit written request in advance of cutting or altering elements affecting:
1. Structural integrity of element.
2. Integrity of weather-exposed or moisture-resistant elements.
3. Efficiency, maintenance, or safety of element.
4. Visual qualities of sight exposed elements.
5. Work of Owner or separate contractor.
C. Execute cutting, fitting, and patching including excavation and fill, to complete
Work, and to:
1. Fit the several parts together, to integrate with other Work.
2. Uncover Work to install or correct ill-timed Work.
3. Remove and replace defective and non-conforming Work.
4. Remove samples of installed Work for testing.
5. Provide openings in elements of Work for penetrations of mechanical and electrical work.
D. Execute work by methods to avoid damage to other Work, and to provide proper surfaces to receive patching and finishing.
E. Cut masonry and concrete materials using masonry saw or core drill, F. Restore Work with new products in accordance with requirements of Contract
Documents.
G. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.
H. Identify hazardous substances or conditions exposed during the Work to
Engineer for decision or remedy.
3-02 SPECIAL PROCEDURES
A. Materials: As specified in product sections; match existing with new products for patching and extending work.
B. Employ skilled and experienced installer to perform alteration work.
C. Cut, move, or remove items as necessary for access to alterations and renovation Work. Replace and restore at completion.
D. Remove debris and abandoned items from area and from concealed spaces.
01 30 00-5
E. Where new Work abuts or aligns with existing, provide smooth and even transition. Patch Work to match existing adjacent Work in texture and appearance.
01 30 00-6
01 32 16-1
SECTION 01 32 16
CONSTRUCTION PROGRESS SCHEDULE
PART 1 - GENERAL
1-01 SECTION INCLUDES
A. References.
B. Quality assurance.
C. Format.
D. Schedules.
E. Submittals.
F. Review and evaluation.
G. Updating schedules.
H. Distribution.
1-02 REFERENCES
A. The Use of CPM in Construction - A Manual for General Contractors and the
Construction Industry, Washington, D.C., The Associated General Contractors of
America (AGC).
1-03 QUALITY ASSURANCE
A. Scheduler: Contractor's personnel Owner's Consultant Specialist Consultant specializing in CPM scheduling with two years minimum experience in scheduling construction work of complexity comparable to this Project, and having use of computer facilities capable of delivering detailed graphic printout within 48 hours of request.
B. Contractor's Administrative Personnel: two years minimum experience in using and monitoring CPM schedules on comparable projects.
1-04 FORMAT
A. Listings: Reading from left to right, in ascending order for each activity. Identify each activity with applicable specification section number.
B. Diagram Sheet Size: 24 inches (600mm) high x 36 inches (900 mm) wide.
01 32 16-2
C. Scale and Spacing: To allow for notations and revisions.
1-05 SCHEDULES
A. Prepare network analysis diagrams and supporting mathematical analyses using
Critical Path Method, under concepts and methods outlined in AGC's "The Use of
CPM in Construction- A Manual for General Contractors and the Construction
Industry".
B. Illustrate order and interdependence of activities and sequence of work; how start of given activity depends on completion of preceding activities, and how completion of activity may restrain start of subsequent activities.
C. Illustrate complete sequence of construction by activity, identifying work of separate stages. Indicate dates for submittals including dates for Owner furnished items and return of submittals; dates for procurement and delivery of critical products; and dates for installation and provision for testing. Include legend for symbols and abbreviations used.
D. Mathematical Analysis: Tabulate each activity of detailed network diagrams, using calendar dates, and identify for each activity:
1. Preceding and following event numbers.
2. Activity description.
3. Estimated duration of activity, in maximum 15 day intervals.
4. Earliest start date.
5. Earliest finish date.
6. Actual start date.
7. Actual finish date.
8. Latest start date.
9. Latest finish date.
10. Total and free float; accrue float time to Owner and to Owner's benefit.
11. Monetary value of activity, keyed to Schedule of Values.
12. Percentage of activity completed.
13. Responsibility.
E. Analysis Program: Capable of accepting revised completion dates, and re-computation of scheduled dates and float.
F. Required Sorts: List activities in sorts or groups:
1. By preceding work item or event number from lowest to highest.
2. By longest float, then in order of early start.
3. By responsibility in order of earliest possible start date.
4. In order of latest allowable start dates.
5. In order of latest allowable finish dates.
6. Contractor's periodic payment request sorted by Schedule of Values listings.
7. Listing of basic input data generating report.
01 32 16-3
8. Listing of activities on critical path.
G. Coordinate contents with schedule of values in Section 01 33 00 - Submittal
Procedures.
1-06 SUBMITTALS
A. Within 15 days after date established in Notice to Proceed, submit proposed preliminary network diagram defining planned operations for first 60 days of
Work, with general outline for remainder of Work.
B. Participate in review of preliminary and complete network diagrams jointly with
Engineer.
C. Within 20 days after joint review of proposed preliminary network diagram, submit draft of proposed complete network diagram for review. Include written certification that major mechanical and electrical Subcontractors have reviewed and accepted proposed schedule.
D. Within 10 days after joint review, submit complete network analysis consisting of network diagrams and mathematical analysis.
E. Submit updated network schedules with each Application for Payment.
F. Submit number of opaque reproductions Contractor requires, plus two copies
Engineer will retain.
1-07 REVIEW AND EVALUATION
A. Participate in joint review and evaluation of network diagrams and analysis with
Engineer at each submittal.
B. Evaluate project status to determine work behind schedule and work ahead of schedule.
C. After review, revise network diagrams and analysis incorporating results of review, and resubmit within 10 days.
1-08 UPDATING SCHEDULES
A. Maintain schedules to record actual start and finish dates of completed activities.
B. Indicate progress of each activity to date of revision, with projected completion date of each activity. Annotate diagrams to graphically depict current status of
Work.
01 32 16-4
C. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.
D. Indicate changes required to maintain Date of Substantial Completion.
E. Submit sorts required to support recommended changes.
F. Prepare narrative report to define problem areas, anticipated delays, and impact on schedule. Report corrective action taken or proposed and its effect.
1-09 DISTRIBUTION
A. Following joint review, distribute copies of updated schedules to Contractor's project site file, Subcontractors, Engineer.
B. Instruct recipients to promptly report, in writing, problems anticipated by projections shown in schedules.
PART 2 – PRODUCTS
Not Used
PART 3 - EXECUTION
01 33 00-1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1-01 SECTION.INCLUDES
A. Submittal procedures.
B. Construction progress schedules.
C. Proposed products list.
D. Product data.
E. Shop drawings.
F. Samples.
G. Test reports.
H. Certificates.
I. Manufacturer's instructions.
J. Manufacturer's field reports.
K. Construction Photographs
1-02 SUBMITTAL PROCEDURES
A. Transmit each submittal with Engineer accepted form.
B. Sequentially number transmittal forms. Mark revised submittals with original number and sequential alphabetic suffix.
C. Identify Project, Contractor, subcontractor and supplier; pertinent drawing and detail number, and specification section number, appropriate to submittal.
D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of · products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with requirements of the Work and Contract Documents.
E. Schedule submittals to expedite Project, and deliver to Engineer. Coordinate submission of related items.
01 33 00-2
F. For each submittal for review, allow 15 days excluding delivery time to and from
Contractor.
G. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of completed Work.
H. Allow space on submittals for Contractor and Engineer review stamps.
I. When revised for resubmission, identify changes made since previous submission.
J. Distribute copies of reviewed submittals as appropriate. Instruct patties to promptly report inability to comply with requirements.
K. Submittals not requested will not be recognized or processed.
1-03 CONSTRUCTION PROGRESS SCHEDULES
A. Submit initial schedules within 15 days after date of Owner-Contractor
Agreement. After review, resubmit required revised data within ten days.
B. Submit revised Progress Schedules with each Application for Payment.
C. Distribute copies of reviewed schedules to Project site file, subcontractors, suppliers, and other concerned patties.
D. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.
E. Submit computer generated horizontal bar chart with separate line for each section of work, identifying first work day of each week.
F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities, Indicate early and late start, early and late finish, float dates, and duration, G. Indicate estimated percentage of completion for each item of Work at each submission.
H. Submit separate schedule of submittal dates for shop drawings, product data, and samples, including Owner furnished products and products identified under
Allowances, and dates reviewed submittals will be required from Engineer.
Indicate decision dates for selection of finishes.
I. Indicate delivery dates for Owner furnished products and products identified under Allowances.
01 33 00-3
J. Revisions to Schedules:
1. Indicate progress of each activity to date of submittal, and projected completion date of each activity.
2. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes.
3. Prepare narrative report to define problem areas, anticipated delays, and impact on Schedule. Report corrective action taken, or proposed, and its effect.
1-04 PROPOSED PRODUCTS UST
A. Within 15 days after date of Owner-Contractor Agreement, submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.
B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.
1-05 PRODUCT DATA
A. Product Data: Submit to Engineer for review for limited purpose of checking for conformance with information given and design concept expressed in Contract
Documents.
B. Submit number of copies Contractor requires, plus two copies Engineer will retain.
C. Mark each copy to identify applicable products, models, options, and other data.
Supplement manufacturers' standard data to provide information specific to this
Project.
D. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
E. After review, produce copies and distribute in accordance with SUBMITTAL
PROCEDURES article and for record documents.
1-06 TEST REPORTS
A. Submit for Engineer's knowledge as contract administrator or for Owner.
B. Submit test reports for information for limited purpose of assessing conformance with information given and design concept expressed in Contract
Documents.
1-07 CERTIFICATES
01 33 00-4
A. When specified in individual specification sections, submit certification by manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.
B. Indicate material or product conforms to or exceeds specified requirements.
Submit supporting reference data, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.
1-08 MANUFACTURER'S FIELD REPORTS
A. Submit reports for Engineer's benefit as contract administrator or for Owner.
B. Submit report in duplicate within 5 days of observation to Engineer for information.
C. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.
PART 2 – PRODUCTS
Not Used
PART 3 – EXECUTION
01 40 00-1
SECTION 01 40 00
QUALITY REQUIREMENTS
PART 1- GENERAL
1-01 SECTION INCLUDES
A. Quality control and control of installation.
B. References.
C. Inspecting.
D. Manufacturers' field services.
E. Examination.
F. Preparation.
1-02 QUALITY CONTROL AND CONTROL OF INSTALLATION
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship to produce Work of specified quality.
B. Comply with manufacturers' instructions, including each step in sequence.
C. When manufacturers' instructions conflict with Contract Documents, request clarification from Engineer before proceeding.
D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Perform Work by persons qualified to produce required and specified quality.
F. Verify field measurements are as indicated on Shop Drawings or as instructed by manufacturer.
G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.
1-03 REFERENCES
A. For products or workmanship specified by association, trade, or other consensus standards, comply with requirements of standard, except when more rigid requirements are specified or are required by applicable codes.
01 40 00-2
B. Conform to reference standard by date of issue current on date of Contract
Documents, except where specific date is established by code.
C. Obtain copies of standards where required by product specification sections.
D. When specified reference standards conflict with Contract Documents, request clarification from Engineer before proceeding.
1-04 INSPECTING
A. Field observations will be performed by an Engineer representative.
1-05 MANUFACTURERS' FIELD SERVICES
A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.
B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.
B. Verify existing substrate is capable of structural support or attachment of new
Work being applied or attached.
C. Examine and verify specific conditions described in individual specification sections.
D. Verify utility services are available, of correct characteristics, and in correct locations.
01 50 00-1
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1-01 SUMMARY
A. Section Includes:
1. Temporary Utilities: Electricity, lighting, heat, ventilation, telephone service, water and sanitary facilities.
2. Temporary Controls: Barriers, enclosures and fencing, protection of the
Work, and water control.
3. Construction Facilities: Parking, progress cleaning.
B. Related Sections:
1. Sections 01 70 00 - Execution and Closeout Requirements: Final cleaning.
1-02 TEMPORARY ELECTRICITY
A. Costs: By Owner; connect to Owner's existing power service. Do not disrupt
Owner's use of service. Owner will pay cost of energy used. Exercise measures to conserve energy.
B. Provide temporary electric feeder, if needed.
C. Provide power outlets for construction operations, with branch wiring and distribution boxes located as required. Provide flexible power cords as required.
D. Provide main service disconnect and over-current protection at convenient location.
E. Permanent convenience receptacles may not be utilized during construction.
F. Provide adequate distribution equipment, wiring, and outlets to provide single phase branch circuits for power and lighting.
1. Provide 20 ampere duplex outlets, single phase circuits for power tools.
2. Provide 20 ampere, single phase branch circuits for lighting.
1-03 TELEPHONE SERVICE
A. Provide, maintain, and pay for telephone service to field office at time of project mobilization.
1-04 TEMPORARY WATER SERVICE
01 50 00-2
A. Connect to existing water source for construction operations at time of project mobilization.
B. Owner will pay cost of water used. Exercise measures to conserve water.
C. Extend branch piping with outlets located so water is available by hoses with threaded connections. Provide temporary pipe insulation to prevent freezing.
1-05 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide at time of project mobilization.
1-06 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas to allow for
Owner's use of site, and to protect existing facilities and adjacent properties from damage from construction operations.
B. Protect non-owner vehicular traffic, stored materials, site, and structures from damage.
1-07 ENCLOSURES AND FENCING
A. Construction commercial grade chain link fence.
B. Provide six (6) feet high fence around construction site; equipment with vehicular and pedestrian gates with locks.
1-08 SECURITY
A. Coordinate with Owner's security program.
1-09 PARKING
A. Parking shall be coordinated with Owner.
1-10 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.
1-11 PROJECT IDENTIFICATION
A. Provide project sign of exterior grade plywood and wood frame construction, painted with exhibit lettering by professional sign painter, to Engineer’s design.
Colors to be selected.
01 50 00-3
B. Erector site at location established by Engineer.
C. No other signs are allowed without Owner permission except those required by law.
1-12 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary utilities, equipment, facilities, materials, prior to Final
Application for Payment.
B. Clean and repair damage caused by installation or use of temporary work.
C. Restore existing and permanent facilities used during construction to original condition. Restore permanent facilities used during construction to like new condition.
PART 2 - PRODUCTS
PART 3 – EXECUTION
01 50 00-4
01 57 13-1
SECTION 01 57 13
TEMPORARY EROSION CHECKS
PART 1 - GENERAL
1-01 DESCRIPTION
A. This work consists of furnishing, constructing and maintaining baled hay or straw erosion checks for the retention of soil along the toe of fill slopes, around inlets, swale areas, small ditches, sediment basins and other areas as directed by the Engineer in accordance with the requirements shown on the plans and these specifications. Also, the work includes removing and disposing of the erosion checks and silt accumulations as directed by the Engineer.
B. Measurement and payment for temporary erosion checks will be made only when ordered and a pay item is included in proposal. The quantity is estimated for proposal purposes only and will be dependent upon actual conditions which occur during construction of the project.
PART 2 - MATERIALS
2-01 VEGETATIVE MATERIALS FOR MULCH
A. Type I. Approved baled straw of wheat, oat, rye grain, or rice or broomsage of Bahia grass (with seed heads) which has reached maturity prior to cutting.
B. Type II. Approved baled hay produced from Bermuda, Bahia, Fescue, Dallis Grass, any of the Lespedezas, or combinations thereof.
C. All of the above materials shall have been properly cured prior to baling and shall be reasonably free from Johnson Grass and other obnoxious grasses and weeds.
Vegetative materials shall be reasonably bright in color, dry, and shall not be musty, moldy, or of otherwise low quality. Vegetative material that is wet or that has been baled green (nor cured properly) shall not be used.
D. Unless otherwise permitted in writing by the Engineer, Type I shall be furnished and used. The Engineer may permit the use of Type II when the Contractor has furnished satisfactory evidence in writing that Type I material is not available.
PART 3 - EXECUTION
3-01 GENERAL
A. The erosion checks shall be constructed at the locations and according to the requirements shown on the plans or as directed by the Engineer. Erosion checks required along the toe of fill slopes shall be constructed prior to grading operations at the site. For other locations, the erosion checks shall be constructed when directed by the Engineer.
01 57 13-2
B. The soil shall be excavated at least three inches in depth to embed the baled material.
After securing in place, a sufficient quantity of the excavated material shall be placed around the erosion check and compacted to prevent undermining.
3-02 MAINTENANCE AND REMOVAL
A. The Contractor shall maintain the erosion checks and remove and dispose of silt accumulations as directed by the Engineer.
B. When the erosion checks are no longer needed, they shall be removed and the
Contractor shall dispose of the silt accumulations and treat the disturbed areas in accordance with the contract requirements.
PART 4 - MEASUREMENT AND PAYMENT
A. Measurement: No measurement.
B. Payment: Erosion checks will be paid in Erosion Control item, and shall be full compensation for completing, maintaining and removal of the erosion checks and the removal and disposal of silt accumulations.
** END OF SECTION **
01 57 23-1
SECTION 01 57 23
TEMPORARY SILT FENCE
PART 1 - GENERAL
1-01 DESCRIPTION
A. This work consists of furnishing, constructing and maintaining a water permeable filter type fence for the purpose of removing suspended soil particles from the water passing through it in accordance with the requirements shown on the plans and these specifications.
B. It is understood that measurement and payment for silt fence will be made only when ordered and a pay item is included in the proposal. The quantities are estimated for bidding purposes only, and may be varied dependent upon actual conditions which occur during construction of the project.
PART 2 - MATERIALS
2-01 GEOTEXTILE FABRIC
A. Unless specified otherwise, the fabric may be woven or nonwoven. The fabric shall consist only of long chain polymeric yarns of filaments such as polypropylene, poly-ethylene, polyester, polyamide or polyvinylidene-chloride and shall be formed into a stable network such that the yarns or filaments retain their relative position. The fabric shall be mildew resistant and inert to biological degradation and naturally encountered chemicals, alkalies and acids. Fabric which is not protected from sunlight after installation shall contain stabilizers and/or inhibitors to make it resistant to deterioration from direct sunlight, ultraviolet rays and heat.
B. The edges of the fabric shall be selvaged or finished in such a manner to prevent the outer yarn or filaments from raveling. The fabric shall be free of defects or flaws which affect the required physical properties.
C. Fabric shall be manufactured in widths of not less than three feet. Sheets of fabric may be sewn or bonded together at the factory or other approved locations but deviation from the physical requirements will not be permitted.
D. Tests for manufacturer's certification shall be conducted with fabric as shipped by the manufacturer and acceptance testing will be conducted with fabric from the project.
2-02 WOVEN WIRE BACKING
A. The silt fence shall be reinforced with a woven wire backing. The wire backing shall be at least 32 inches high and have no less than six horizontal wires. Vertical wires shall be
01 57 23-2 spaced no more than 12 inches apart. The top and bottom wire shall be 10 gage or larger. All other wire shall be no smaller than 12-1/2 gage.
2-03 POSTS
A. Wood or steel posts may be used. Wood posts shall have a minimum diameter of three inches and length of five feet and shall be straight enough to provide a fence without noticeable misalignment. Steel tee posts shall be five long, approximately 1-3/8 inches wide, 1-3/8 inches deep and 1/8 inch thick with a nominal weight of 1.33 pounds per foot prior to fabrication. The posts shall have projections, notches or holes for fastening the wire backing or fabric to the posts.
2-04 STAPLES
A. Staples shall be made of nine gage wire with a minimum length of one inch after bending.
2-05 IDENTIFICATION
A. Each roll of fabric or container shall be visibly labeled with the name of the manufacturer, type of fabric or trade name, lot number and quantity of material.
2-06 MANFACTURER'S CERTIFICATION
A. The Contractor shall furnish to the Engineer three copies of the manufacturer's certified test reports and certification that each lot complies with the requirements of the contract. All fabric, steel pins, washers, fence posts, woven wire and wire staples are subject to approval by the Engineer upon delivery to the work site and prior to incorporating in the work.
PART 3 - EXECUTION
3-01 PLACEMENT OF THE FENCE
A. The silt fences shall be constructed at the locations shown on the plans or as directed by the Engineer.
B. All posts shall be installed so that no more than three feet of the post shall protrude above the ground. Extra post for bracing shall be installed as directed by the Engineer.
The woven wire shall be securely fastened to the wood posts with staples. When metal posts are used, the wire shall be fastened to the post with wire or other approved means. The bottom edge of the fabric shall be buried 6" below ground surface to prevent undermining. When splicing of the fabric is necessary, two posts shall be installed approximately 18" apart and each piece of fabric shall be fastened to both posts.
01 57 23-3
The fabric will be rejected if it has defects, rips, holes, flaws, deterioration, of damage incurred during manufacture, transportation, storage or installation
3-02 MAINTENANCE AND REMOVAL
A. The Contractor shall maintain the silt fence and the fabric shall be removed and replaced when deteriorated to such an extent that it reduces the effectiveness of the silt fence.
B. Unless otherwise directed, all temporary silt fences shall be removed. Upon removal, the Contractor shall remove and dispose of any excess silt accumulations, dress the area to give a pleasing appearance and vegetate all bare areas in accordance with the contract requirements. The temporary materials will remain the property of the
Contractor and may be used at other locations provided the materials are acceptable to the Engineer.
PART 4 - MEASUREMENT AND PAYMENT
A. Measurement: No measurement.
B. Payment: Silt Fence will be paid in Erosion Control item, and shall be full compensation for completing, maintaining and removal of the silt fence and the removal and disposal of silt accumulations.
01 60 00-1
SECTION 01 60 00
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1-01 SECTION INCLUDES
A. Products.
B. Product delivery requirements.
C. Product storage and handling requirements.
D. Product options.
E. Product substitution procedures.
F. Equipment electrical characteristics and components.
1-02 PRODUCTS
A. Furnish products of qualified manufacturers suitable for intended use. Furnish products of each type by single manufacturer unless specified otherwise.
B. Do not use materials and equipment removed from existing premises, except as specifically permitted by Contract Documents.
C. Furnish interchangeable components from same manufacturer for components being replaced.
1-03 PRODUCT DELIVERY REQUIREMENTS
A. Transport and handle products in accordance with manufacturer's instructions.
B. Promptly inspect shipments to ensure products comply with requirements, quantities are correct, and products are undamaged.
C. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage.
1-04 PRODUCT STORAGE AND HANDLING REQUIREMENTS
A. Store and protect products in accordance with manufacturers' instructions.
B. Store with seals and labels intact and legible.
01 60 00-2
C. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to product.
D. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.
E. Store loose granular materials on solid flat surfaces in well-drained area. Prevent mixing with foreign matter.
F. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement or damage.
G. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.
1-05 PRODUCT OPTIONS
A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description.
B. Products Specified by Naming One or More Manufacturers: Products of one of manufacturers named and meeting specifications, no options or substitutions allowed.
C. Products Specified by Naming One or More Manufacturers with Provision for
Substitutions: Submit request for substitution for any manufacturer not named in accordance with the following article.
1-06 PRODUCT SUBSTITUTION PROCEDURES
A. Several of the Specification Sections included in this Project Manual list only one or two manufacturers in certain products. These are meant to establish a quality level, and should not be interpreted as proprietary specifications. Substitutions are invited and welcomed if they meet the same quality level, finish and overall performance of the manufacturers listed. Substitutions will not be considered during the bidding process. Substitutions will be reviewed for approval by the
Engineer for a thirty (30) day period after date of Notice to Proceed is issued.
B. Substitutions may be considered when a product becomes unavailable through no fault of Contractor.
C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.
D. A request constitutes a representation that Contractor:
1. Has investigated proposed product and determined that it meets or exceeds quality level of specified product.
01 60 00-3
2. Will provide same warranty for Substitution as for specified product.
3. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to
Owner.
4. Waives claims for additional costs or time extension which may subsequently become apparent.
5. Will reimburse Owner and Architect/Engineer for review or redesign services associated with re-approval by authorities having jurisdiction.
E. Substitutions will not be considered when they are indicated or implied on Shop
Drawing or Product Data submittals, without separate written request, or when acceptance will require revision to Contract Documents.
F. Substitution Submittal Procedure:
1. Submit three copies of request for Substitution for consideration. Limit each request to one proposed Substitution.
2. Submit Shop Drawings, Product Data, and certified test results attesting to proposed product equivalence. Burden of proof is on proposer.
3. Engineer will notify Contractor in writing of decision to accept or reject request.
4. Substitution request form at end of section.
PART 2 - PRODUCTS
2.1 EQUIPMENT ELECTRICAL CHARACTERISTICS AND COMPONENTS
A. Wiring Terminations: Furnish terminal lugs to match branch circuit conductor quantities, sizes, and materials indicated. Include lugs for terminal box.
B. Cord and Plug: Furnish minimum 6 foot (2 m) cord and plug including grounding connector for connection to electric wiring system. Cord of longer length is specified in individual specification sections.
PART 3- EXECUTION
01 70 00-1
SECTION 01 70 00
EXECUTION AND CLOSEOUT REQUIREMENTS
1-01 SECTION INCLUDES
A. Substantial completion.
B. Closeout procedures.
C. Final cleaning.
D. Starting of systems.
E. Demonstration and instructions.
F. Protecting installed construction.
G. Project record documents.
H. Operation and maintenance data.
I. Spare parts and maintenance products.
J. Product…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.