This document contains questions and answers regarding a federal solicitation for preventative maintenance of patient lifts at a VA medical center. The solicitation seeks preventative inspection and repair services for Liko overhead lifts on a base year plus four option years. Key clarifications provided in the questions and answers include: inspections will initially be completed by the end of February but may transition to quarterly thereafter; electronic delivery of service reports is acceptable; all lift fixing points must be inspected visually and mechanically; the checklist will note lift functions are operating as intended by the OEM design; and only Liko lifts remain in the scope after a Guldmann lift was removed from service.

36C25220Q0125 0001 36C25220Q0125 0001.docx

View the file

Other files

File Type Posted
36C25220Q0125-006.pdf PDF
36C25220Q0125-009.pdf PDF
36C25220Q0125-005.pdf PDF
36C25220Q0125-004.pdf PDF
36C25220Q0125-008.xlsx XLSX spreadsheet
36C25220Q0125-003.docx DOCX document
36C25220Q0125-002.docx DOCX document
36C25220Q0125-007.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 01-09-2020 695-20-3-133-0262

NONE

36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders

36C25220Q0125 01-09-2020

X X

X REFERENCE SOLICITATION 36C25220Q0125 for PATIENT LIFT PREVENTATIVE MAINTENANCE at TOMAH VA MEDICAL CENTER and AMEND to reflect the following: Provide answers to questions submitted by interested parties.

SOLICITATION CLOSE REMAINS WEDNESDAY JANUARY 15, 2020 AT 11:59 PM LOCAL.

ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.

CC: COR; FILE

SUSAN PASHOLK

CONTRACTING OFFICER

· Per the site visit the Preventative Inspection, is to be completed by the end of February. Is it the intention of the Government to have all the work completed by February and no additional PI’s completed until the next year?

· This is currently the intent.

· Typically, the PI’s would be done in sections throughout the year instead of all at once (i.e. 257 lifts divided by 12 months or 4 months), is this acceptable?

· After the first-year inspection is completed, the Facility may consider quarterly inspections for the remaining duration of the contract however this would require a bi-lateral contract modification.

· Can the requirement for the Field Service Report to be delivered via a flash drive be amended to be delivered electronically instead?

· This is acceptable as long as it is in accordance with the “Contract Deliverables” ,Section 7, Line Item E, (table 2). Delivery of Field Service Report shall be in format mutually agreed upon with VE facility and contractor.

· In reference to the PM Checklist

· Structural section, lines 1, 2 and 3. A visual check by Technicians will not confirm the proper connection, interface or the correct structural system is in place. We rely upon the initial installation certification for this. We will do a visual inspection of the existing equipment. Our direction requires inspecting for corrosion or damage.

· Is this Acceptable?

· Attachment C states, visual inspections, and amount of inspections is not quantified.

· Attachment E, states 20% of fixing points require visual inspection

· The requirement of the Tomah VA Medical Center is 100% of all fixing points be inspected, both visually and physically/mechanically.

· The below items are listed on the checklist, could these be removed to incorporate a statement that the PI will verify the function of the lifts are working in accordance with the OEM intended design. This would capture that all features, buttons, etc. are working as intended.

· a maximum of 2.5 inches per second with zero load.

· a maximum of 1.5 inches per second with maximum load.

· The checklist includes a NOTES: section. This would be the appropriate place to capture this and any relevant information.

· It was discussed at the site visit that the Guldmann Lift was to be removed, can you clarify that this is accurate and only Liko lifts will be included in this contract?

· The Guldman lift was removed from service and turned-in 18 January 2019.

· Currently Tomah VAMC is using only Liko overhead lifts