Replace steam and condensate lines between buildings 20 & 37 Federal contract opportunity
Solicitation number
36C25219B0033
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

36C25219B0033 36C25219B0033_1.docx

View the file

Other files for this federal contract opportunity

Other files attached to Replace steam and condensate lines between buildings 20 & 37, newest first.
File Type Posted
36C25219B0033-0001000.docx DOCX document
36C25219B0033-002.pdf PDF
36C25219B0033-005.pdf PDF
36C25219B0033-007.pdf PDF
36C25219B0033-004.pdf PDF
36C25219B0033-012.pdf PDF
36C25219B0033-011.pdf PDF
36C25219B0033-017.docx DOCX document
36C25219B0033-014.docx DOCX document
36C25219B0033-010.pdf PDF
36C25219B0033-006.pdf PDF
36C25219B0033-008.pdf PDF
36C25219B0033-015.docx DOCX document
36C25219B0033-016.pdf PDF
36C25219B0033-009.pdf PDF
36C25219B0033-003.pdf PDF
36C25219B0033-013.pdf PDF
36C25219B0033-000.docx DOCX document
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25219B0033

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (

Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25219B0033 X 02-14-2019 578-18-3-6985-0385 578-19-011 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 3001 Green Bay Rd, Bldg 1, Rm 329 North Chicago IL 60064-3048 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 3001 Green Bay Rd, Bldg 1, Rm 329 North Chicago IL 60064-3048 Alea Barnes 224-610-3673 Replace Steam Line Between Buildings 37 and 20 - Project # 578-19-011

The Edward Hines Jr VA Hospital has a requirement to replace the existing steam/condensate lines between Building 37 and Building 20 with new piping and install a telecommunicate. This project will take place on the Edward Hines Jr VA Hospital Campus, Hines, Illinois.

Pre-bid site visit information can be found in section 52.236-27 of this solicitation.

All questions regarding this solicitation should be submitted to alea.barnes@va.gov no later than five (5) calendar days after the pre-bid site visit.

The project magnitude range is between $500,000.00 and $1,000,000.00.

NAICS: 238220 (Plumbing, Heating, and Air-Conditioning Contractors)/ Size Standard $15.0 million

This procurement is a 100% set-aside for CVE-Verified Service-Disabled Veteran-Owned Small Business (SDVOSB) Firms per the authority 38 USC 8127 (Public Law 109461). In accordance with VAAR 819.7003(b), at the time of submission of bid, the bidder must represe nt that it is an SDVOSB concern;

a small business concern under the NAICS code assigned to the the acquisition; and

SDVOSB/VOSB listed as verified in VIP database at: https://www.vip.vetbiz.gov.

If submitting a bid as a joint-venture, bidders must include a copy of the joint-venture agreement.

NOTICE: VA and/or a third party (support contractor) will require access to VA contractor records to assess contractor compliance with the limitations on subcontracting requirements included at VAAR 852.219-10.

All bidders are responsible for monitoring and downloading any amendments from FedBizOpps https://www.fbo.gov.

Only one award will be issued.

X X 52.211-10 X 1:00pm CST 03-18-2019 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 3001 Green Bay Rd, Bldg 1, Rm 329 North Chicago, IL 60064-3048 Department of Veterans Affairs Financial Services Center PO Box 149971 Austin TX 78714-9971 877-353-9791 512-460-5540

Statement of Work

Replace Steam Line Between Buildings 37 and 20 Project 578-19-011

References:1)VA’s Technical Information Library (TIL)
2)Master Construction Specifications (PG-18-1)
3)Standard Details (PG-18-4)
4)Environmental Planning Guidance (PG-18-17)
5)2013 Historic Preservation Plan for the Edward Hines Jr. Veterans Affairs Hospital (available on request)
6)2017 Statement of Conditions Survey for the Edward Hines Jr. Veterans Affairs Hospital (available on request)

A) Mission.

Engineering Service’s mission is the total oversight and management of the environment of care, as it pertains to the physical infrastructure and base plant operations, at the Edward Hines VA Hospital. Engineering support is for customers that include, but are not limited to, patients, visitors, clinic staff and administrative employees.

B) Goals.

The goal of this project is replacing the existing steam and condensate lines between Building 20 and Building 37 with new piping, and install a Telecommunications Duct.

C) Current Conditions.

The existing underground steam distribution piping has outlived its life expectancy and is leaking. The project area includes the steam pit in Building 20, the stream pit in Building 37, The Vault in the parking lot, and the underground steam distribution piping location between the two buildings. The area between the two buildings is a paved roadway, parking lot with landscaping next to each building.

D) Justification.

The existing underground steam distribution piping has outlived its life expectancy and is leaking. These pipes left in their current condition, could fail leaving building 20 without heat during the winter leading to wasted resources and higher utility costs. This project will correct a portion of FCA deficiency #100732 Steam Distribution which was graded as a “D” E) Objectives.

The objectives of this project are to:

1)Repair the steam distribution system by removing and replacing the underground piping.
2)Replacing piping components inside the Building 20 steam pit and Building 37 steam pit.
3)Installing isolation valves and warm up by-pass systems inside bldg. 37.
4)Perform the work in a manner least likely to interfere with the daily operations of the campus.
5)Restore the landscape, roadway, curbs, gutters, and fencing to conditions that existed before the project.

F) Acronyms and Definitions.

The following is a listing of acronyms and/or definitions to terms that may be used in this document.

COContracting Officer
CORContracting Officers Representative as delegated by the CO
CSContracting Specialist assigned by the CO
EHVAHEdward Hines Veterans Affairs Hospital
GCGeneral Contractor (firm)
IDIQIndefinite Delivery Indefinite Quantity
LFLinear or Lineal Feet
NTPNotice to Proceed
OITOffice of Information & Technology
PDTProject Delivery Team – Typically comprised of the CO/CS, the COR, and EHVAH staff
RFIRequest for Information
SFSquare Feet
VADepartment of Veteran Affairs

G) Requirements.

Where a conflict exists between the Statement of Work (SOW) requirements and the requirements of other associated contract documents, the SOW requirements shall prevail.

This SOW presumes the contractor will not need access to the Hines LAN or any VA Sensitive Information to execute the contract.

The awarded Contractor will adhere to all codes, standards, guidelines and design requirements found in the VA’s Technical Information Library (TIL) including but not limited to the following:

1) Pre-bid site visit:

a. A pre-construction site walk through is encouraged and should be coordinated by the CO. The intent of this walkthrough is to give the contractor access to the project site so that an accurate evaluation of the project requirements and site assessment can be made.

2) RFI Submittals:

a. The contractor shall submit any RFI’s resulting from the site visit within five (5) calendar days after the inspection to the CO.

b. Unless otherwise stated the contractor shall allow the COR and CO five (5) working days to respond to an RFI.

3) Infection Control Barrier (ICB):

a. Temporary construction partitions shall be smoke-tight and built of noncombustible materials that will not contribute to the development or spread of fire.

b. Barriers shall not obstruct access to emergency services and for fire, police, and other emergency forces.

c. The contractor shall provide and install a rigid infection control panel system manufactured by Edge Guard out of Bement, Illinois or an approved equal. http://www.edge-guard.com/home.html. Salient details of the infection control barrier are:

i. The ICB must be fire-rated.

ii. The barrier must be water resistant; capable of being cleaned and sanitized.

iii. Installation of the barrier shall not:

1. Generate dust outside the barrier.

2. Generate excess noise outside the barrier.

3. Generates excess fumes outside the barrier.

iv. Demobilization of the barrier shall not:

1. Generate dust outside the barrier.

2. Generate excess noise outside the barrier.

3. Generates excess fumes outside the barrier.

4. Require floor, wall or ceiling repairs upon removal.

v. The barrier should be environmentally responsible.

1. The materials should be reusable.

2. The materials should not contribute to unnecessary waste to our landfills.

d. Fire-rated plastic sheeting, may be used to supplement the rigid infection control panel system. COR approval is required.

i. Contractor shall submit an RFI requesting approval during the bid period.

e. Wood studs, plywood, OSB, particle board, pressboard, or other flammable materials are not allowed at Hines.

f. Manometers shall be installed on the ICB adjacent to every entrance of the work zone to monitor negative pressure within the work zone.

g. All doors to rooms inside the work zone but directly impacted by the work shall have their doors shut and the perimeters taped to prevent the migration of dust and debris into these rooms.

h. Cover all sprinkler heads (daily), signs, data transmitters, and light fixtures. Cover the supply and return diffusers within the work zone to prevent the spread of dust and fumes to other areas outside the work zone.

i. Rigid infection control panel system and manometers are to be submitted and approved by the COR prior to installation.

j. The following is a manner acceptable to Hines Infection Control to maintain negative pressure inside an infection control barrier with no reasonable access to discharge air to the exterior.

i. Install a floor-to-ceiling infectious control barrier (ICB) meeting the fire-rating required.

ii. Cover all sprinkler heads (daily), signs, data transmitters, and light fixtures. Cover the supply and return diffusers within the work zone to prevent the spread of dust and fumes to other areas outside the work zone.

iii. Place the air scrubber inside the ICB with a HEPA filter. The air scrubber will draw air from inside the ICB.

iv. Place a flapper valve connection on the ICB near to the ceiling.

v. Route the filtered air from the scrubber via a collapsible duct to the flapper valve thus maintaining negative pressure inside the ICB.

vi. If the power should accidently get cutoff, the flapper valve will swing close thereby maintaining the integrity of the ICB.

4) The contractor shall post and maintain the final signed ICRA and ILSM (when issued) at the entrance to the ICB for the duration of the project. The contractor will update the postings when new documents are issued.

5) Equipment Lead time:

a. Equipment lead times line shall be incorporated in to the project schedule and used in conjunction with the baseline for the project start date.

6) EHVAH Permits:

a. Unless otherwise stated the contractor shall submit for all required VA permits (i.e. above ceiling or dig) fourteen (14) calendar days prior to the event based on the approved project schedule with the COR.

7) Project Pay Applications:

a. All submitted project pay applications require certified payroll and waste report documents to be current with each pay submission.

b. Certified payroll documents shall be submitted to the COR weekly.

c. Approval of all invoices will require documents to be current.

8) Work outside of normal business hours or weekends:

a. All work performed after hours or on weekends requires coordination with the COR and shall be requested fourteen (14) calendar days prior in writing or e-mail to the COR for approval.

b. No work shall take place without written or e-mail confirmation from the project COR.

9) Utility Shutdowns:

a. Contractor shall provide twenty-one (21) calendar days’ advance notice for any planned utility shutdowns to all allow the station to notify staff/visitors and prepare contingency plans if necessary.

b. Planned utility shutdowns should be indicated on the project schedule.

10) Submittals and Shop Drawings:

a. Unless otherwise stated the contractor shall provide shop drawings and equipment submittals for review and approval by the COR seven (7) calendar days prior to the start of construction.

b. No work shall be started prior to review and approval by the COR.

11) Certifications:

a. When applicable, the contractor shall provide certification for all personnel performing any welding and shall certify all welds prior to the start-up of any of the units.

b. These certifications shall be supplied to the COR and retained as a permanent record of the project folder.

c. Personnel certifications shall be provided to the COR prior to the start of construction.

d. All weld certifications shall be provided to the COR at the end of every work week when applicable.

12) OSHA Certification:

a. The contractor shall have an OSHA certified site superintendent on site whenever any work is being performed.

b. A copy of the OSHA certification shall be supplied to the COR prior to the start of any work and retained as part of the project folder.

13) Post-Award meeting: (COR to include in SOW for all SCIP projects)

a. The meeting shall be coordinated through the COR and CS/CO.

b. The meeting shall take place after the Notice to Proceed has been issued but prior to the start of demolition/construction.

c. The contractor shall schedule and attend a “Page-Turn” meeting in which the Designer of Record will be in attendance. The goal of this meeting is to clarify any confusion the contractor may have regarding the contract documents in advance of commencing construction activities, delivery of project submittals, submission of the project schedule, the coordination of project phasing, etc.

H) Scope of Work.

The scope of this project is to remove and replace approximately 465 ft of existing 6” steam supply piping, 3” condensate return piping and associated fittings. The project includes, but is not limited to, the following major items of work. All measurements/dimension are approximate. The contractor must insure the replacement piping design is engineered in accordance with ASME section B31 and VA standards, and verifying all measurements, dimensions anchor point, and insulating systems are installed per ASME section B31 standards and manufactures recommendation.

1) Phases – The project work will be performed in four (4) phases. During all phases the exits/entrances from both buildings to 1st Avenue shall NOT be interrupted. Also upon completion of each phase, the top surface shall be sufficiently patched temporarily to enable vehicular traffic until final surface work is done in Phase 4.

a. Phase 1 – Work inside Bldg. 20 and Bldg. 37. Also work outside walls of Bldgs.20&37

b. Phase 2 – South half of Building 20 parking lot & North half of Bldg. 37 parking lot.

c. Phase 3 - North half of Building 20 parking lot & South half of Bldg. 37 parking lot

d. Phase 4 – Testing pipes and final surface work.

2) Construction Notes:

a. Maintain staff and visitor safe access to the buildings during demolition and construction per specifications.

b. Locate and mark underground utilities within the work area.

c. Erect and maintain temporary work site fencing and traffic control signs and barricades throughout the work period.

d. Provide erosion control to prevent silt and debris from leaving the work area or entering the drainage system. Provide a silt fence around the work area. Provide an erosion barrier consisting of filter fabric over drain inlets and a straw bale or coir log barrier around the inlets.

e. Remove street sign as necessary from the work area; reinstall during area restoration actions are completed.

f. All piping welds must be accomplished by certified welders. The contractor shall provide a certified welding inspector, and submit inspection reports to the Government before work can be accepted and payment made. Nonconforming work shall be corrected by the contractor at no additional cost to the Government.

g. Backfill trench using pipe bedding material and suitable backfill. The contractor shall place topsoil on the trench in areas that are not roadways or parking lots, and other disturbed areas, perform final grading, and seed area.

h. Dispose of all demolition material and construction debris in accordance with Federal, State and local environmental requirements. The contractor shall provide waste tickets for all the removed waste.

3) Demolition:

a.Remove the fence between Bldg. 20 parking lot and Bldg. 37 parking lot.
b.Saw cut 5” depth asphalt road of approximate length 3900 SF.
c.Saw cut and remove sidewalks, curbs, and gutters of approximate length 15SY from area to be excavated.
d.Excavate by both buildings to expose the distribution piping, saw cut and remove roadway from area to be excavated.
e.Excavate as required to remove existing pipes and install new piping. Existing piping is approximately 5’ to 6’ below the existing grade. Provide shoring boxes and follow other OSHA regulations to protect workers in trenches as required.
f.Dispose of asphalt and concrete.
g.Remove existing steam supply piping and condensate return piping in Bldg. 37 mechanical room at southeast side of building where it leaves the building and dispose of materials. The approximate length of steam line is 5’ and condensate line is approximately 5’. Also, to remove is pre-insulated piping system.
h.Remove existing steam supply valve and condensate return valve in bldg. 37 mechanical room.
i.Remove existing steam supply pipe (6”) of approximate length 15’ and condensate return pipe(3”) of approximate length 15’ in Bldg. 20 mechanical room at north side of building where it leaves the building and dispose of materials.
j.Remove existing steam supply valve and condensate return valve in Bldg. 20 mechanical room.
k.Saw cut and remove foundation walls at both Bldg.37 and Bldg. 20. The quantity is approximately 8 Sq.ft at each of two buildings.
l.Expose and remove steam pipe of 6” and condensate pipe of 3”. The length of each pipe is approximately 465 LF.
m.Dispose of unsuitable backfill at offsite location.
n.Spoils generated during construction should be kept adjacent to the trench created and reserved for use in the restoration of the area if possible. Excess spoils shall be removed off site by the contractor per specifications.

4) Sitework:

a. Install temporary fence of approximately 200 LF.

b. Excavate approximately 1250 CY of fill to expose existing pipe.

c. Backfill trenches

d. Put top soil, final grade and plant grass seed. The area is approximately 1600 Sq.ft.

e. Install approximately 200 SF of sidewalk

f. Install approximately 2000 CY of aggregate base for Asphalt paving and sidewalk.

g. Install approximately 3,900 SF of Asphalt road

h. Install approximately 50 LF of curb & gutter

i. Any areas where storm or sanitary basins have been disturbed, shall be reset and inspected prior to backfilling. Prepare subgrade, place aggregate base, and replace roadway. Asphalt shall be IDOT approved mix. New road shall consist of minimum 1.5” HMA surface course, Mix “C” N50; 3.5” HMA binder course, IL 19.0 N50; and 12” crushed aggregate base course CA-6 (Type B).

j. Provide penetrations in concrete foundation walls of buildings as required to allow removal of existing piping and the installation of new piping. Install new wall sleeve and leak plate through wall, and secure with concrete in-fill.

k. Prepare subgrade, place aggregate base, and replace sidewalk, curb and gutter. Concrete shall be 4000 psi mix with air entrainment and 6”x6” xW2.9xW2.9 reinforcing.

l. Re-Install the fence between Bldg. 20 parking lot and Bldg. 37 parking lot after the construction is complete.

m. Re-stripe parking lot.

5) Plumbing:

a. Disconnect piping for demolition.

b. The contractor shall have COR approved shop drawing for all pipe work before proceeding to construction work.

c. The shut off valve for both steam and condensate pipes shall be cast steel with warmers.

d. Install 6” underground Schedule 80 black steel seamless steam pipe of approximate length 465 LF. Also install 15 LF of same pipe inside Bldg. 20 and Bldg. 37.

e. Install 3” underground Schedule 80 black steel seamless condensate pipe of approximate length 465 LF. Also install 15 LF of same pipe inside Bldg. 20 and Bldg. 37.

f. The contractor shall re-install two expansion loops in steam line.

g. Install new steam supply valve with by-pass system in building 37 mechanical room (Warm-up Valve).

h. Install new condensate return valve, shut off valve in building 37 mechanical room.

i. Install new steam supply valve, shut off valve, pressure reducing valve, two gages in Building 20 mechanical room.

j. Install new condensate return valve in Bldg. 20 mechanical room.

k. Provide and install new piping from the system in the steam pit inside Building 37 through the wall as required.

l. Install a tee fitting with cap and a high-pressure bucket traps. Install elbows and fittings, as necessary, to connect the existing system to the new piping in both buildings.

m. Weld pipes and joints wherever it is necessary.

n. All removable fittings (valves and traps) inside the buildings will use a removable blanket type insulating system.

o. Piping installation shall be accomplished in accordance with ASME B31 standards. After completion of all piping connections and before piping is covered, the steam system shall be Hydrostatic leak tested. The contractor shall coordinate with COR for inspections, approval, and certification.

p. The contractor shall paint underground pipes prior to insulation work. The paint shall be Acrylic DTM Lo luster P25 or approved equal. Surface temp to 200 degrees. The paint color shall be white grey.

q. After approval of underground piping, the Contractor shall install DriTherm Pour-in-Place insulation or approved equal insulation.

r. Provide Cathodic protection to all underground pipes installed in this project.

6) Data cable work:

a. Contractor shall provide and install approximately 420ft of underground concrete encased 1.5” conduit and 2 maintenance boxes along the steam lines (installed as required in the previous sections), for routing FO/telephone lines. Each maintaining box shall be 1/3 of the distance from both buildings(Bldg. 20 and Bldg.37). All pull boxes shall have a fiber optics logo cover with a 15,000 LB load rating. Fish tape shall be included and left in the conduit.

b. Fiber optics conduit shall terminate inside both buildings into a 12’X12” junction box in each of them.

I) Constraints.

1) Work hours for EHVAH staff are from 7:30 am until 4:00 pm, Monday through Friday.

2) Photographs may be taken of the work performed at the jobsite. However, photographs containing patients and/or staff are a violation of the Patient Privacy and hospital policy. Both violations are subject to penalties and dismissal. Permission from the EHVAH Public Affairs Officer (PAO) is required and should be coordinated with the project COR.

3) Exploratory demolition is permitted but must be coordinated with the COR.

4) All contractors visiting the jobsite will need to receive a temporary PIV badge. The procedure to follow is:

a. Contractors must FIRST get their fingerprints done by Human Resources located in Building 17.

b. It takes between 3-5 days at least for fingerprints clear.

c. Once fingerprints have cleared the person requesting a badge can be sponsored.

d. The contractor must then complete a “Request for a PIV card” form. See Attachment 10 and then turn in to the Engineering Services.

e. The contractor can then be sponsored upon verification the fingerprints have been cleared.

f. Once contractor has been sponsored the COR, they can call PIV (708) 202-5170 to make arrangements for issuance of a PIV for badge.

J) Tasks and Responsibilities.

A pre-construction (kick-off) meeting between the Contracting Officer (CO) or Contracting Specialist (CS), the Contracting Officers Representative (COR), and key GC team members will be conducted to review project objectives, scope, deliverables, communication, site access, schedule, and responsibilities. During this meeting the Notice to Proceed (NTP) should be signed. After this meeting the awarded GC firm shall provide their services according to the approved project schedule.

1) Preconstruction Period: The Contractor shall provide the following:

a. Logistics Plan: A comprehensive narrative describing the chronological planned development of the project. The Logistics Plan includes an organizational chart, hourly rates, staging plan, description of means and methods, and hours of work.

b. Construction Security Plan: Defines both physical and administrative security.

c. Construction Phasing Plan: It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

d. Submittal Registry: The Submittal Registry shall include a listing of all documentation required for pre-approved submissions including shop drawings, technical data, product performance information, calculations, and samples.

e. Accident Prevention Plan: The APP (aka Construction Safety & Health Plan) shall interface with the Contractor's overall safety and health program.

f. Activity Hazard Analyses: AHAs are also known as Job Hazard Analyses, Job Safety Analyses, and Activity Safety Analyses.

g. Construction Schedule: WBS schedule including start/end dates, duration and sequencing, preferably in MS Project or Primavera format (include floats).

h. Schedule of Values: A detailed Breakdown for Payment, including design stages, work performed and work invoiced per Progress Payment submission.

i. Existing Conditions Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of the buildings or areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer.

j. Infection Control Plan (ICP): Narrative description of the dust control and debris disposal process including disposal destination and methodology.

k. Quality Control Plan (QCP): Describes the methods by which the Contractor will ensure all work is being accomplished in accordance with specifications and this SOW.

l. Environmental Protection Plan: The Contractor shall meet with the COR to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental protection.

m. Document Submissions. All documents included as Attachments to this SOW that are required to be filled out and signed or jointly signed by the Contractor.

n. Demolition Debris Management Plan.

o. Certificates, Licenses, and Training Documents.

p. Obtain PIV badges.

q. RFI’s: Other than those resulting directly from demolition or construction.

2) Construction Period: The Contractor shall provide the following during construction services:

a. Display the signed PCRA, ICRA, ILSM and Emergency Contact Information in a location coordinated with the COR.

b. Attending biweekly construction meetings which are facilitated by the COR.

c. Submit RFI’s during construction as necessary.

d. Issue biweekly field reports of construction progress to the COR.

e. Attend field inspections and punch list inspections as requested by the COR.

3) Construction Close-out Period:

a. The Contractor shall provide the following:

1. Inspection and Approval by the COR and/or the CO.

2. Final Approval and Beneficial Occupancy when applicable.

3. Warranties documents and O&M Manuals.

4. As-built drawings and record submittals.

5. Staff training when applicable.

6. Contractor Release of Claims.

7. All Waste Reports submitted per Safety and Health during Construction Activities.

8. Existing Conditions Re-survey.

b. The COR shall review the contractor close-out submissions for thoroughness and conformance with the contract document requirements. The COR shall also review field-marked as-built drawings for conformance with final installations.

c. The COR shall utilize these as-built drawings and specifications from the contractor and generate as recorded drawings and specifications.

K) Deliverables.

1) The contractor shall provide all submittals required by the Specifications Book.

L) Time Frames.

1) This project shall be completed within One Hundred Fifty (150) calendar days once NTP is issued.

a. Phasing – This project shall be executed in four (4) phases based upon the work locations. Work in each location shall be executed uninterrupted until complete. No work shall commence for follow-on phase until the work is completed in the prior phase.

1. Phase 1 – 45 days.

2. Phase 2 - 15 days.

3. Phase 3 - 15days.

4. Phase 4 - 15 days.

b. Pre-construction (kick-off) Meeting is when the Notice to Proceed (NTP) is signed.

c. Pre-Construction Period duration is NTP + 30 calendar days. Within this period the contractor shall provide all materials included under Tasks and Responsibilities and the following:

1. Logistics Plan.

2. Construction Security Plan.

3. Construction Phasing Plan.

4. Submittal Registry.

5. Accident Prevention Plan.

6. Activity Hazard Analyses.

7. Construction Schedule.

8. Schedule of Values.

9. Existing Conditions Survey.

10. Infection Control Plan.

11. Quality Control Plan.

12. Environmental Protection Plan.

13. Document Submissions.

14. Demolition Debris Management Plan.

15. Certificates, Licenses, and Training Documents.

16. Obtain PIV badges.

d. Construction Period - To be determined based upon the approved schedule for construction. The estimated construction period is 90 calendar days with all product submittals to be delivered prior to the start of construction to the COR for review and approval. No demolition or construction shall be started without the review and approval from the COR for those items listed in the Pre-Construction Period unless authorized in writing by the COR or the CO.

e. Construction Closeout Period duration is NTP + 120 calendar days. The contractor shall submit within 30 calendar days from EHVAH acceptance of the completed punch list items and commissioning reports (if applicable). Within this period the contractor shall provide all materials included under Tasks and Responsibilities and the following:

1. Inspection and Approval by the COR and/or the CO.

2. Final Approval and Beneficial Occupancy when applicable.

3. Warranties documents and O&M Manuals.

4. As-built drawings and record submittals.

5. Staff training when applicable.

6. Contractor Release of Claims.

7. Waste Reports.

8. Existing Conditions Re-survey.

M) Performance Monitoring.

The Government will periodically evaluate the Contractor’s performance by appointing a representative(s) to monitor such performance and ensure services are received. The Government representative will evaluate the Contractor’s performance through intermittent on-site inspections of the Contractor's performance.

N) Other Pertinent Information or Special Considerations.

1) All Contractor personnel shall be certified by appropriate federal and state regulatory agencies to meet federal and local certification requirements as applicable. All licenses, permits and welding certifications shall be kept current throughout the period of performance of the contract. The Contractor shall provide the Government copies of such certificates.

2) Per VA Information Security Program policy – VA Directive and Handbook 6500 and 6500.6, Appendix A, contractor storage, generation, transmission or exchanging of VA sensitive information during this construction project is not acceptable.

3) All work shall be scheduled to meet requirements of EHVAH. All work shall be coordinated through the Contracting Officer. Local coordination shall be routed through the Contracting Officer’s Representative.

4) The contractor shall provide to the Contracting Officer record of work certifications for all trades relative to this contract 5 calendar days prior to beginning work. Certifications shall include welders, pipe installers, machine operators, etc.

5) Contractor is responsible for repairing any damages to existing utilities incurred during construction or demolition.

6) Utilities within the area and identified on existing drawings are not to be interpreted as the exact location, or as the only existing site conditions. Contractor shall verify all existing conditions and proceed with caution around any anticipated obstructions.

7) Where any work disturbs the grass areas, sod, walls, ceilings, floors, windows, entrances or building structures, etc. or where new and old work join, the Contractor shall restore, repair or refinish affected areas or surfaces to their original condition, or as existed before the commencement of this project. Upon completion of the contract, the Contractor shall deliver all work complete and undamaged. Any damage that may be caused by the Contractor or his work crews or subcontractors to any existing structure, grounds and utilities shall be repaired or replaced to their original condition.

8) Should a conflict exist between VA requirements and VA adopted nationally recognized codes and standards, the conflict shall be brought to the attention of the Contracting Officer. The resolution of the conflict shall be made by the authority having jurisdiction for VA to ensure system-wide consistency. All work conducted under this scope of work shall comply with the Department of Veterans Affairs Master Specifications and all applicable state and federal regulations and codes.

O) Risk Control.

1) Refer to the attached ICRA form.

P) Government Furnished Equipment (GFE)/Government Furnished Information (GFI).

1) GFE.

a. Light fixture switches will be provided by Hines Electric Shop.

2) GFI.

a. No additional information is intended to be supplied other than information that is requested by the Contractor.

Q) Point of Contact at the EHVAH.

TBD

578-19-011: Replace Steam Line Between Bldg 37 & 20 Edward Hines, Jr. VA Medical Center - Hines, Illinois

BID SCHEDULE

BASE BID:

Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, overtime, and other items designated in the provisions of this contract as outlined in the contract specifications, scope of work, and drawings for Project # 578-19-011: Replace Steam Line Between Bldg 37 & 20 at Hines VA Hospital, 5000 S. 5th Avenue, Hines, Illinois.

Work is to be completed within 150 calendar days of receipt of a Notice to Proceed.

Base Bid LUMP SUM: _______________________________ Cost Range $500,000 to $1,000,000 NOTICE TO BIDDERS: A single award will be made to the responsible bidder who submitted the lowest responsive bid.

The Illinois Administrative Code, 130.2075 allows construction contractors to be exempt from Retailers Occupation Tax and Use Tax within the State of Illinois when the materials are for Incorporation into real estate owned by Governmental bodies. For purposes of this authority, a Construction Contractor is defined as a General Contractor or a Subcontractor 86 Ill.Adm.Code 130.1940(a)(1). Materials, are defined as all of the tangible personal property, including fixtures, which enter into a structure or otherwise become incorporated into real estate 86 Ill.Adm.Code 130.1940(a)(5), but do not include tools, fuel, lumber for forms and other end use or consumption items which are not incorporated into the real property 86 Ill.Adm.Code 130.2075(d)(3).

‘Prospective offerors are notified that under 86 Ill.Adm.Code 130.2075, purchase within the State of Illinois to be incorporated into the real property of Edward Hines, Jr. Hines, Illinois may be exempt from Illinois Retailers’ Occupation Tax and Use Tax. VA will furnish a Certificate to the successful awardee of this solicitation with all required information to be used within the State of Illinois. Prime contractors may furnish the certificate to its subcontractors for use on this project. All bids received in response to this solicitation are presumed to reflect any tax benefit that may be realized upon receipt of this certificate.

METRIC PRODUCTS:

Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerances specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions, and those dimensions exceed the tolerances specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the COR, will accept or reject the product.

CONTRACTING OFFICER’S SPECIAL INSTRUCTIONS AS FOLLOWS:

Requests for information or clarifications to solicitation documents shall be submitted to the Contracting Officer at Alea.Barnes@va.gov no later than March 6, 2019.

After compiling all required information, submit the information in accordance with the "Bid Due Date" in Block 13 of the SF 1442. Return the original and specified number of copies to the issuing office listed in Block 8 of the SF 1442

INQUIRIES:

Inquiries and all correspondence concerning this solicitation document should be submitted in writing to the Contracting Officer. YOU ARE INSTRUCTED SPECIFICALLY TO CONTACT ONLY THE CONTRACTING OFFICER ISSUING THE SOLICITATION ABOUT ANY ASPECT OF THIS REQUIREMENT PRIOR TO CONTRACT AWARD.

CONTRACTOR'S SIGNATURE:

In accordance with Federal Acquisition Regulations Part 4, contractual documents (e.g. bids, proposals, awards, modifications, etc.) shall be completed and signed by the Contractor as follows:

(a) Individuals: Signed by the individual.

(b) Individual doing business as a firm. Signed by that individual, and the signature shall be followed by the individual's typed, stamped, or printed name and the words, "an individual doing business as __________________ (insert name of firm)".

(c) Partnership: Signed in the partnership name. Prior to award, provide list of all partners and designate which partners have authority to bind the partnership.

(d) Corporations: Signed in the corporate name followed by the word "by" and the signature, and title of the person authorized to sign. Prior to award, provide list of individuals who have authority to bind the corporation.

(e) Joint Ventures: Signed by each participant in the joint venture in the manner prescribed in (a) through (d) above.

(f) Agents. When an agent is to sign the contract, other than as stated in paragraph (a) through (e) above, the agent's authorization to bind the principal must be established by evidence satisfactory to the contracting officer.

CONTRACTOR INFORMATION:

Name of Company:
Name:
Title:
Address:_______
E-Mail Address:
Phone No:_______________
TAX ID Number:
DUNS Number:____________

Past Performance Point of Contact (within your company), include name and email address:

ADDITIONAL PRIME CONTRACTOR INFORMATION

Safety or Environmental Violations and Experience Modification Rating Information

Information provided below shall be applicable to Project # 578-19-011: Replace Steam Line Between Bldg 37 & 20 at Hines VA Hospital:

1.) All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.

2.) All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Bidder’s/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Bidder/Offeror’s EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.

3.) Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

4.) If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned Bidder/Offeror a Unity Rating of 1.0.

5.) The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

6.) This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

Pre-Award Contractor Safety and Environmental Record Evaluation Form Information provided below is current and applicable to Solicitation 36C25218B0033 for Project # 578-19-011: Replace Steam Line Between Bldg 37 & 20 at Hines VA Hospital:

Company Name: ______________________________________________ Address: _____________________________________________________ Telephone: ______________________ Fax: ________________________ Email: _______________________________________________________ Contact: ______________________________________________________

1. Utilizing your OSHA 300 Forms, please complete the following information:

Category
2013
2014
2015
2016

Number of man hours (jobsite and office).

Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).

Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).

Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations.

Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page: http://www.osha.gov/pls/publications/publication.html.

2.Provide six-digit North American Industrial Classification System (NAICS) Code for this acquisition: __________________________________
3.Who administers your company’s Safety and Health Program? ______________________
4.Company’s Insurance Experience Modification Rate (EMR): _______________________

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision) 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision) 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
19.6 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract…