This solicitation is for construction services to complete Project #539-22-209 "Improve Trailers" at the Cincinnati VA Medical Center. The project scope includes interior and exterior repairs and upgrades to four existing onsite trailers, such as replacing flooring, insulation, and skirting; improving drainage; and replacing wood decking with composite walkways. The total period of performance is 125 calendar days from notice to proceed. The solicitation is set aside for service-disabled veteran-owned small businesses. Offerors must submit bids by June 23rd, 2023. The award is estimated between $300,000 to $600,000 and is subject to the wage determination included in the document.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 539-22-209 Pre-Bid Site Visit Sign-in Sheet (5-30-23).pdf | ||
| 36C25023B0041 0001.docx | DOCX document | |
| EMR.docx | DOCX document | |
| 539-22-209 Bid Drawings 2023-02-23.pdf | ||
| WD OH20230082.pdf | ||
| VHA_Directive_1192.pdf | ||
| Attachment 3 - VAAR 852.219-75 VA Notice of Limitations on Subcontracting (JAN 2023).pdf | ||
| 539-22-209 Bid Specifications 2023-02-23.pdf | ||
| RFI Form-36C25023B0041.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________
(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25023B0041
X
05-22-2023
610-23-3-6902-0006
539-22-209
36C250
Department of Veterans Affairs
Cincinnati
Department of Veterans Affairs,VA Health
260 E. University, 2nd Floor
Cincinnati OH 45219
Department of Veterans Affairs
Columbus
2780 Airport Drive, Suite 340
Columbus OH 43219-2292
Kenyon Dulaney 614-969-8804
Improve Trailers - Project 539-22-209 - Cincinnati, OH Cincinnati VAMC
The contractor shall provide complete construction services including labor, materials, equipment, and supervision required to complete Project# 539-22-209 “Improve Trailers” for the Cincinnati VAMC. The project will provide needed repairs and upgrades to the existing trailers located at the main campus of the Cincinnati VAMC.
Fulfillment of this project will ensure the existing trailers are kept in a safe and operable condition.
Cincinnati VAMC – 3200 Vine St, Cincinnati, OH 45220
Duration of the project shall not exceed 125 calendar days from receipt of the Notice to Proceed (NTP).
Pre-Bid/Site Investigation will be conducted in accordance with FAR 52.236-27.
Meeting Place: Cincinnati VAMC – 3200 Vine St, Cincinnati, OH 45220
SITE VISIT: 5/30/2023 at 11:00AM EST
This project is 100% set-aside for service-disabled veteranowned small business (SDVOSB).
NAICS Code: 236220; Small Business Standard: $45M.
Project Magnitude is between $300,000.00 and $600,000.00.
Cut-off date and time to submit electronic Request for Information (RFIs) is June 6th, 2023 at 3:00PM EST
Submit all RFIs to kenyon.dulaney@va.gov
Bid Opening will be held via phone conference at the time specified in block 13 unless otherwise stated via amendment.
Call in information will be provided via amendment prior tobid opening.
Electronic bids shall not be accepted. A formal in-person bid opening WILL NOT take place. Offerors are responsible to ensure bids are delivered via US Mail or Commercial Delivery are received by the Contracting Officer no later than
June 23rd, 2023 at 3:00PM EST. See BLOCK 8 for address. Hand delivered bids will be accepted by the Contracting officer on-site at the public bid opening for bids submitted no later than June 23rd at 3:00PM EST..
A conference line has been set up for bidders who would like to listen in during the "bid opening". Please call
+1 205-235-3524 between 3:0PM EST and 4:00PM EST, enter access code 487952618# to be connected.
An original Bid bond must be submitted with your bid.
Failure to submit all requirements as stated in this solicitation may result in offer/bid being deemed unresponsive.
Contractor must acknowledge and sign VAAR clause 852.219-75& return with the bid package, or the bid will be considered nonresponsive.
10 125
X X 52.211-10
X
1 Original 3:00PM EDT
06-23-2023
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your
Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
BID AMOUNT:
UEI:
TAX I.D:
EMAIL:
539-3630162-6905-854200 -3223-23NRNR000
36C250
Department of Veterans Affairs
Columbus
Chalmers P. Wylie Outpatient Clinic
420 North James Road
Columbus OH 43219-1834
36C250 Department of Veterans Affairs
Financial Services Center
Invoices to be Submitted Electronically www.ob10.com/us/en/veterans-affairs// e-Invoice Setup Info Phone 877-489-6135
877-353-9791 512-460-5429
Luke Turner
Contracting Officer
36C25023B0034
Table of Contents
PART I - THE SCHEDULE ...................................................................... Error! Bookmark not defined.
SECTION A - SOLICITATION/CONTRACT FORM ..................................... Error! Bookmark not defined.
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) ..... Error!
Bookmark not defined.
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)–
BACK ................................................................................ Error! Bookmark not defined.
STATEMENT OF WORK
IMPORTANT BIDDER INFORMATION
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK
(MAY 2014)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY
2014)
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
2.7 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
2.9 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)
2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC 2022)
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION
(NOV 2021)
3.4 52.229-11 TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION
(JUN 2020)
GENERAL CONDITIONS
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS
(NOV 2021)
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
ALTERNATE I (APR 1984)
4.3 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)
4.4 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)
4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (OCT 2022)
4.6 52.223-20 AEROSOLS (JUN 2016)
4.7 52.223-21 FOAMS (JUN 2016)
4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
4.9 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.10 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
4.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.12 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)
4.13 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
4.14 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY
2020)
4.15 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED
SMALL BUSINESSES (JAN 2023) (DEVIATION)
4.16 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING - CERTIFICATE OF
COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)
4.17 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)
4.18 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)
4.19 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED
SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)
4.20 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT
NAS– CPM) (NOV 2018)
4.21 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)
4.22 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)
4.23 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019)
4.24 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)
4.25 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)
4.26 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT
2020)
4.27 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)
4.28 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)
STATEMENT OF WORK
1. Background
The chosen contractor shall provide complete construction services including labor, materials, equipment, and supervision required to complete Project# 539-22-209 “Improve Trailers” for the
Cincinnati VAMC. The project will provide needed repairs and upgrades to the existing trailers located at the main campus of the Cincinnati VAMC. Fulfillment of this project will ensure the existing trailers are kept in a safe and operable condition for continued daily use by patients and employees.
2. Scope
The “Improve Trailers” project provides needed repairs and upgrades to the trailers currently located at the Cincinnati VAMC main campus. Interior work in the trailers involves replacement of existing flooring. Exterior work under each trailer involves various repairs & installations to mitigate current moisture, drainage and freezing issues. In addition, the existing wood decking around the trailers is to be replaced with composite walkways for patients and employees to safely access each trailer.
This construction project requires general contracting, survey and demolition of existing conditions, masonry, carpentry, opening installations, finishes, plumbing, HVAC and electrical for successful completion.
3. Specific Tasks
A general summary of tasks involved with this project are listed below as currently documented in the project drawings & specifications. For a full and complete understanding of all required work to be completed under this project, carefully read through all aspects of the project drawings and specifications.
Note 1: Contractor to field verify measurements and quantities of all items needed to complete this project.
Note 2: Any requirements listed in the project documentation that are unclear to the contractor or requires further clarification are to be documented and submitted via Request For
Information (RFI) to be formally answered by the project’s CO/COR prior to starting any work.
Work for the “Improve Trailers” project will include, but is not limited to, the following various repairs and upgrades to the four (4) existing onsite trailers:
• Replacing existing interior flooring
• Replacing insulation & vapor barriers underneath the trailers
• Replacing heat tape and insulating domestic water piping below flooring
• Installing ventilation fans & electrical circuits in the crawl spaces
• Replacing skirting
• Improving drainage under & around each trailer
• Removing and replacing the existing wood decking with composite walkways
• Providing general site cleanup
This work has been divided up into phases in an effort to minimize impact on patients and employees. The phases as currently listed in the project drawings and specifications are as follows:
• Phase 1A – Renovate Exterior of Trailers:
This phase will address exterior repairs & upgrades to three (3) of the four (4) trailers as indicated in project documentation.
• Phase 1B – Renovate Interior and Exterior of Trailers:
This phase will address both interior and exterior repairs & upgrades to the 4th trailer as indicated in project documentation.
• Phase 2A – Partial Deck/Walkway Replacement:
This phase will partially replace the existing wood decking between the trailers with composite decking as noted in the project documentation.
• Phase 2B – Remaining Deck/Walkway Replacement:
This phase will replace the remaining existing wood decking between the trailers with composite decking as noted in the project documentation.
It is the intent of the VA to award a contract to complete the full scope of work as defined by the project drawings and specifications. No deduct alternates have been identified in the current project documentation.
4. Performance Monitoring
Construction contract supervision will be conducted by the Project Section of Engineering Service at the Cincinnati VA Medical Center.
Inspection will be made throughout the project and delivery and installation.
5. Security Requirements
None.
6. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI)
None.
7. Other Pertinent Information or Special Considerations
a. Identification of Possible Follow-on Work.
None.
b. Identification of Potential Conflicts of Interest (COI).
None.
c. Identification of Non-Disclosure Requirements.
None.
d. Packaging, Packing and Shipping Instructions.
None
e. Inspection and Acceptance Criteria.
Project COR to conduct the final acceptance of satisfactory installation.
8. Risk Control
An infection control risk assessment will be completed for this project by the facility and should be followed during periods of construction.
The selected contractor may also be subject to COVID-19 regulations outlined within VHA Directive
1193 which provides guidance towards vaccination requirements, exemptions, documentation, masking, and testing requirements. Further confirmation will be provided by the Contracting Officer.
9. Place of Performance
This product will be used at the main campus of the Cincinnati VAMC, specifically inside and around the four (4) existing on-site trailers located on the east side of the campus.
10. Period of Performance
Total Period of Performance: 125 calendar days from the effective date of the Notice To Proceed
(NTP).
11. Delivery Schedule
TBD
12. Technical/Administrative Requirements
Contracted work shall be conducted in accordance with the below VA Specifications.
1. Support features for each room can be found within U.S. Department of Veterans Affairs Office of Construction & Facilities Management Technical Information Library.
a. This resource provides information regarding construction specifications, construction procedures, design manuals, design guides, room finishes, and door/hardware schedules which should be followed throughout the administration of this contract.
The above SOW constitutes a basic outline of work required for this project but does not include all details required for the design, construction, and completion of this project. A pre-construction walkthrough and inspection of current conditions is recommended to determine all needs and requirements prior to starting the project.
13. Warranty
Contractor must provide a one (1) year warranty to include all materials and labor.
14. Record Management
1. Contractor shall comply with all applicable records management laws and regulations, as well as
National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII
Subchapter B, and those policies associated with the safeguarding of records covered by the
Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for
Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
4. Cincinnati VA Medical Center (CVAMC) and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of CVAMC or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to CVAMC. The agency must report promptly to NARA in accordance with 36 CFR 1230.
5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the Statement of Work. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from
Government facilities or systems, or facilities or systems operated or maintained on the
Government’s behalf, without the express written permission of the Head of the Contracting
Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to CVAMC control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the Statement of
Work. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts.
The Contractor (and any sub-contractor) is required to abide by Government and CVAMC guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with CVAMC policy.
8. The Contractor shall not create or maintain any records containing any non-public CVAMC information that are not specifically tied to or authorized by the contract.
9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
10. The CVAMC owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which CVAMC shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training. The
Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.
[Note: To the extent an agency requires contractors to complete records management training, the agency must provide the training to the contractor. TMS Course 10203, VA Privacy &
Information Security Awareness will be used to satisfy this requirement.]
12. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this Statement of Work and require written subcontractor acknowledgment of same.
13. Violation by a subcontractor of any provision set forth in this clause will be attributed to the
Contractor.
IMPORTANT BIDDER INFORMATION
A.1 PROJECT SPECIFIC INFORMATION
PROPOSAL MATERIALS: Offeror materials consist of Request for Proposal forms and any issued Amendments which will be provided via email.
PROPOSAL SUBMISSION:
The following documents are to be included in the proposal submission: one (1) original fully completed and signed SF 1442 Offer page, acknowledgment of all amendments either via entering data in block 19 of the SF1442 or completing blocks 15a, b, and c of the Amendment and attaching to the original SF 1442 Offer page; one (1) original completed bid schedule if one is provided, otherwise bid amounts are entered in block 17 of the SF1442 Offer page; one (1) original completed/wet ink signed SF 24 Bid Bond (if required, see block 13B) of the SF1442 Solicitation page; Offerors are responsible for ensuring and verifying their proposal and all required proposal documents are received at the address designated in block 8 of the SF 1442 Solicitation and by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment).
PROJECT INFORMATION
PROJECT TITLE AND NUMBER: Improve Trailers 539-22-209
PROJECT LOCATION: Cincinnati VAMC 3200 Vine St, Cincinnati, OH 45220
MAGNITUDE OF CONSTRUCTION: FAR 36.204 (d) Between $250,000 and $500,000.
TYPE CONSTRUCTION: Commercial and Institutional Building Construction
NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM CODE: (NAICS): 236220
SMALL BUSINESS SIZE STANDARD: $45M
PERIOD OF PERFORMANCE: 125 calendar days from receipt of Notice to Proceed for Entire Project
Scope.
LIQUIDATED DAMAGES: (__) YES or (X) NO (reference Contract Clause FAR 52.211-12)
PERFORMANCE PERIOD: The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 125 calendar days from receipt of the Notice to Proceed for the entire project. The time stated for completion shall include final cleanup of the premises.
RESPONSIBILITY REQUIREMENTS: A responsibility check will be accomplished for the apparent awardee prior to award. Checks of the VIP database (to ensure apparently successful offeror is a verified Service
Disabled Veteran Owned Small Business), System for Award Management (SAM) database, Online
Representations and Certifications, and Excluded Parties List System to insure registrations are current, valid, and no debarment records exist, and Experian (to check Intelliscore Plus Score to insure it is below a risk value of 4). Any information retrieved or received by the Government that would be cause for negative or unsatisfactory responsibility rating may result in the offeror being determined ineligible for award.
WAGE DETERMINATION: OH20230082 04/14/2023
BONDING INFORMATION
PERFORMANCE AND PAYMENT BONDS: In accordance with Contract Clause 52.228-15, and FAR
28.102, Contractors are reminded that any amount awarded over $30,000.00 shall require a Payment
Bond (SF 25A), and awards exceeding $150,000.00 shall require both Payment and Performance Bonds
(SF 25). Payment and Performance bonds are due no later than 10 days after notification of award.
Bonds must be provided with original ‘wet ink’ signatures - no white outs or other corrections are allowable. Copies and facsimiles of bonds shall not be accepted.
REQUESTS FOR INFORMATION (RFI): To obtain clarifications and/or additional information concerning the contract requirements, specifications and/or drawings, submit a written RFI utilizing the RFI Form attached to this Solicitation, send via email to Kenyon.Dulaney@va.gov. RFIs must be specific identifying section, paragraph and page no. of the specifications or cite the drawing number and must be in question format. All RFIs submitted shall include the solicitation number and title, contractor name, city, state, telephone, email address, date submitted, and the RFI question(s). RFI responses will be submitted via email.
SECURITY
BACKGROUND INVESTIGATIONS: All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform the statement of work. This requirement is also applicable to all subcontractor personnel requiring the same level of access.
Levels and associated types of Background Investigations:
• If the project requires that workers have only limited physical access to the VA facility for a period of one year or less, a local flash badge with fingerprint check is issued.
• If the project requires that workers require un-supervised, logical and/or physical access for 180 consecutive or aggregate days in a 365 day period, over a 3 year period, a background investigation is required (Special Agency Check (SAC)) which must be completed prior to being allowed access.
• If the project requires that workers have un-supervised, full-time, logical, and/or physical access for more than 6 months or more than 180 aggregate days in a one year period, a background investigation is required (Special Agency Check and National Agency Check with Written Inquiries (NACI)) and access is not allowed until a favorable SAC completion.
All costs for SAC and NACI checks are borne by the contractor. The VA may at its discretion make deductions against the contract in order to recoup the investigation costs. Current cost for a SAC is
$25.00 per employee and the current cost for a NACI check is $182.00 per employee (subject to change at any time).
MEDICAL CENTER ACCESS: Anyone participating in the site visit, or for any other reason that involves visiting the medical center related to this solicitation, must have a valid ID on their person and their vehicle must be properly registered and insured. Visitors are prohibited from possessing weapons while on a federal installations (See 18 USC 930 - Possession of Firearms and Dangerous Weapons in Federal Facilities). Handheld cellphone use or texting while driving is also prohibited. All VA Medical Centers and associated properties are Federal Property.
PRIVACY TRAINING: All workers regardless of project length must take VA Privacy Training which will be coordinated after project award with the Contracting Officer's Representative.
E-VERIFY SYSTEM: Companies awarded a contract with the federal government shall enroll in E-Verify within 30 days of the contract award date. They shall also begin using the E-Verify system to confirm that all of their new hires and their employees directly working on federal contracts are authorized to legally work in the United States. E-Verify is an Internet-based system that allows an employer, using information reported on an employee's Form I-9, to determine the eligibility of that employee to work in the United States. There is no charge to employers to use E-Verify. (FAR 52.222-54).
OTHER IMPORTANT BIDDER INFORMATION
ADDITIONAL PRIME CONTRACTOR INFORMATION- SAFETY OR ENVIRONMENTAL VIOLATIONS AND
EXPERIENCE MODIFICATION RATING INFORMATION:
All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record.
(using the attached EMR information and certification form) pertaining to their past Safety and Environmental record. The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat,, and/or willful OSHA violations, along with a detailed description of those violations.
All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Bidders/Offeror's insurance carrier and be furnished on the insurance carrier's letterhead. If a Bidder/Offeror's EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier's letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and Puerto Rico shall obtain their EMR rating from their state run worker's compensation insurance rating bureau.
If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier's letterhead, and include a letter from the NCCI indicating that it has assigned Bidder/Offeror a Unity Rating of 1.0.
The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make a Determination of Responsibility.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS: The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility Green Environmental Management System (GEMS) applicable for the contract.
The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility GEMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the facility GEMS Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.
All on-site contractor personnel shall complete yearly EPA sponsored environmental training specified for the type of work conducted on-site. Upon inclusion in the contract, the Contracting Officer's Representative will verify that all contractor personnel have acquired EMS Awareness Training at their appropriate site or location.
REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, SENIOR RESIDENT ENGINEER, OR PROJECT MANAGER: Any reference contained within contract specifications and/or drawings to the “VA Engineer”, “Resident Engineer”, “Senior Resident Engineer”, “Project Manager”, or their abbreviations are to be replaced with “Contracting Officer's Representative (COR)”.
PAYMENT FOR MATERIALS STORED OFF-SITE: Payment in advance of installation for materials stored off-site is not authorized under this contract.
SCHEDULE OF MATERIAL SUBMITTALS: The submittals contemplated by FAR 52.236-5, Material and Workmanship, are listed on the Schedule of Material Submittals in the Specifications. The provided schedule is for reference only, all submittals required by the contract documents are required.
PROGRESS SCHEDULE: The schedule required by FAR 52.236-15 shall be provided after receipt of the Notice to Proceed.
REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS)
(a) As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts that exceed $700,000, and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.
(b) Each contractor whose contract award is estimated to exceed $700,000 is required to register with CPARS database at the following web address: www.cpars.csd.disa.mil. Help in registering can be obtained by contacting Customer Support Desk at DSN: 684-1690 or COMM: 207-438-1690. Registration should occur no later than thirty days after contract award, and must be kept current should there be any change to the contractor's registered representative.
(c) For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor's performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor's designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.
(d) Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government's evaluation being placed on file in the database with a statement that the contractor failed to respond.”
**NOTE
The Construction Contractors representatives performing construction activities on VA campus must validate the following additional requirements are in place before starting construction activities on campus:
1. Daily visit at check-in station for COVID and temperature screening a. Sticker/device must be worn visibly
2. Annual influenza shot is required for all staff performing work on campus
3. Contractor badge must be obtained and worn by contractor or representative at all times while on campus
The contractor will validate in writing via signed memo to the Contracting Officer that the above items are being done as part of the bid package. No Personally Identifiable Information (PII) will be collected.
The temperature checks are performed on the VA campus and must be performed immediately when the contractor arrives on site. Temperature checks are currently performed at front entrance. If at any time an employee of the Construction Contractor is found in deficiency of the listed, a stop work order will be issued for safety of VAMC patients and staff. Any further questions please refence the below document.
▪ Seasonal influenza with Vaccines (VHA Directive 1192.01)"
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate
Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT
OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action
Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade Goals for female participation for each trade
3.7 % 6.9 %
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41
CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance
Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to
Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4.
Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal
Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
(End of Provision)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition
Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy
American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy
American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the
Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and
(d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph
(c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Luke Turner
Contracting Officer
Hand-Carried Address:
Department of Veterans Affairs
Cincinnati Department of Veterans Affairs,VA Health 260 E. University, 2nd Floor Cincinnati OH 45219 Mailing Address:
Department of Veterans Affairs
Cincinnati
Department of Veterans Affairs,VA Health
260 E. University, 2nd Floor
Cincinnati OH 45219
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions
Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
SITE VISIT: 5/30/23 at 11:00AM EST
(c) Participants will meet at—
Cincinnati VAMC, 3200 Vine St, Cincinnati, OH 45220
(End of Provision)
2.7 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the provision.
(b) The use in this solicitation of any VAAR Acquisition Regulation (48 CFR Chapter FEDERAL
ACQUISITION REGULATION (48 CFR Chapter 1)) provision with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.
(End of Provision)
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
FAR Number Title Date
52.204-7 SYSTEM FOR AWARD MANAGEMENT OCT 2018
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING AUG 2020
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS DEC 2016
52.214-4 FALSE STATEMENTS IN BIDS APR 1984
52.214-5 SUBMISSION OF BIDS DEC 2016
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS APR 1984
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF
BIDS
NOV 1999
52.214-18 PREPARATION OF BIDS—CONSTRUCTION APR 1984
52.214-19 CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION AUG 1996
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE APR 1991
FAR Number Title Date
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY APR 1991
52.228-1 BID GUARANTEE SEP 1996
52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) FEB 2021
2.9 VAAR 852.233-70 PROTEST…