36C25023B0028 0001-1.pdf
PDF 141 KB Posted
- Attached to
- Z1DA--Install Lab Water Supply 610A4-23-508 Federal contract opportunity
- Solicitation number
- 36C25023B0028
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S04 Install Lab Water Supply Sign-In.pdf | ||
| 36C25023B0028 0002.pdf | ||
| Attachment II - Wage Determination.pdf | ||
| Attachment VI - Drawings.pdf | ||
| 36C25023B0028_1.pdf | ||
| Attachment IV - Design and Construction.pdf | ||
| Attachment III - Minimum_Property_Requirement.pdf | ||
| Attachment V - Request for Information.pdf | ||
| Attachment VII - VHA Directive 1192.01.pdf | ||
| Attachment I - Install Lab Water Supply Spec.pdf | ||
| 36C25023B0028.docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 5
610-23-3-6902-0011
610A4-23-508
36C250
Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 1100 Indianapolis IN 46240
36C250
Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 1100 Indianapolis IN 46240
To all Offerors/Bidders
36C25023B0028
03-30-2023
X
610-3690162-6901-854200-3220-23NRNR001
X 1
The purpose of this amendment is to clarify and to correct the posted RFI Responses
Please see page 2 for more details.
All other terms and conditions remain unchanged.
Luke Turner Contracting Officer
CONTINUATION PAGE
UPGRADE LOBBY RESTROOMS
VA NORTHERN INDIANA HEALTH CARE SYSTEM-- FORT WAYNE, IN
PROJECT NUMBER: 610A4-23-508
TO INVITATION FOR BID (IFB) NUMBER
36C25023B0028
IFB AMENDMENT NUMBER A00001
REQUEST FOR INFORMATION (RFI) Question and Answer:
Question 1: Are we to bid this as a design/build proposal or are we bidding this per plans and SPECS (design completed by VA)?
Answer 1: No, design is not part of this project. The design language has been crossed out. Please see the revise statement of work
Question 2: Please confirm contractor is only responsible for submitting completed SF1442 box #17.
Answer 2: Confirm. Complete bid includes completed SF 1442, and signed SF30, if applicable
Install Lab Water Supply (REVISED) Project Number: 610A4-23-508
I. DESCRIPTION OF SERVICES:
GENERAL:
Contractor shall provide all needed labor, materials, parts (to Include system components), Supervision, Project Management, Equipment, Quality and Safety Assurance, and all other necessary resources required to run a redundancy water line to the labs analyzers to prevent an interruption of utilities during outages at VA Northern Indiana Health Care System –Fort Wayne Campus located at 2121 Lake Avenue, Fort Wayne, IN 46805.
SCOPE:
To include:
A. Contractors work and responsibility shall include all contractor planning, programming, administration, and management necessary to provide all construction and related services as specified.
B. Contractor shall provide all related contractor administration services to perform the work such as quality control, contractor financial control, preparing and submitting required reports, and submitting necessary information as specified under this contract and within the individual TOS.
C. The work shall be conducted by the contractor in strict accordance with the contract, to include all applicable federal, state and municipal laws, codes, regulations, and directives and specifications.
D. Design Contractor shall comply with applicable sections of the Technical Information Library on the Office of Construction and Facilities Management (CFM) website www.cfm.va.gov. Project is to be designed to comply with the latest codes as outlined in the VHA Program Guide PG-18-3, Topic 1 – Codes, Standards, and Executive Orders on the TIL. Contractor will be responsible for complete functional design and provide bidding documents meeting those requirements.
E. The contractor shall coordinate all shutdowns with the COR at least 3 weeks in advance of the shutdown. This shall include interior and exterior such as work involving cranes, taking parking spaces, utilities, and public spaces.
F. Representatives of the Contractor shall be required to attend a Pre-Construction Conference prior to scheduling work, mobilizing or performing any work for any issued task order.
G. The Pre-Construction Conference shall be conducted by the CO or the designated COR and will consist of a formal review of project requirements and establish the Notice to Proceed (NTP).
1. Contractor shall install a fully operational redundancy water line to the lab’s analyzers.
2. Contractor shall provide an appropriate means of disposing of all waste from remodel.
3. Contractor shall provide an inventory of waste items by weight to the VA.
4. Contractor shall install a tee fitting on the water line bypass located in the basement ceiling outside room 44.
5. Contractor shall install an insulated ¾” copper water line from the bypass in the basement up to the labs analyzer water supply located on 2nd floor in room 249
6. A tee fitting shall be installed on the water supply for the analyzers in the lab.
7. Two valves will be installed on the line so that it can be isolated with one located at the basement tie-in and one located at the lab supply tie-in on second floor.
8. Valves Shall be readily accessible to maintenance staff.
9. Pipe shall be clearly labeled as lab redundancy water supply at both ends.
10. Contractor shall provide a detailed construction plan showing means and methods to complete the project to the VA for approval before the start of construction.
11. Contractor shall provide a detailed project schedule to the VA providing timelines and milestones to the VA for approval before the start of construction
12. Contractor shall provide the VA with an estimate broken down by line items and a schedule of values as part of their proposal.
Regulations and requirements.
A. Work Shall be performed during normal business hours, 7:00 A.M. – 3:00 P.M. Monday through Friday.
B. The Contractor shall coordinate project expectations with the subcontractors to ensure everything in the SOW and on the specifications and drawings is included in subcontractor bids and work is properly completed prior to the final inspection.
C. Contractor shall provide a site-specific safety plan.
D. Contractor shall provide a construction schedule before the start of work.
E. Contractor shall provide Submittals to COR prior to install.
F. Retainage.
(1) The Contracting Officer may retain funds—
(i) Where performance under the contract has been determined to be deficient or the Contractor has performed in an unsatisfactory manner in the past; or
(ii) As the contract nears completion, to ensure that deficiencies will be corrected and that completion is timely.
(2) Examples of deficient performance justifying a retention of funds include, but are not restricted to, the following—
(i) Unsatisfactory progress as determined by the Contracting Officer;
(ii) Failure to meet schedule in Schedule of Work Progress;
(iii) Failure to present submittals in a timely manner; or
(iv) Failure to comply in good faith with approved subcontracting plans, certifications, or contract requirements.
(3) Any level of retention shall not exceed 10 percent either where there is determined to be unsatisfactory performance, or when the retainage is to ensure satisfactory completion.
Retained amounts shall be paid promptly upon completion of all contract requirements, but nothing contained in this paragraph (a)(3) shall be construed as limiting the Contracting Officer’s right to withhold funds under other provisions of the contract or in accordance with the general law and regulations regarding the administration of Government contracts.
Formal review of project requirements shall include but is not limited to:
Designation of COR, Task Order and Site-Specific Information, Infection Control, Interim Life Safety Measures, Safety, Badging and Identification requirements, parking access to premises and building; space for material and equipment storage; delivery of materials and use of approaches; and use of corridors, stairways, elevators, eating spaces, and restrooms for Contractor personnel.
The CO will issue the Notice to Proceed before any work or mobilization is authorized to begin.
Contractors shall clearly include the solicitation number (prior to award) or the contract number (as appropriate) on all documents submitted to the VA.
TO Identification: After successful award of each task order the contractor shall clearly include the contract number, task order number, obligation number and project number on all correspondence submitted to the VA.
The solicitation number, contract number, task order number, obligation and project numbers are displayed and be easily found on all official government documents issued by the VA.
"No Government personnel, other than the Contracting Officer, have the authority to change or alter these requirements. The COR shall clarify technical points or supply relevant technical information, but no requirements in this scope of work may be altered as a sole result of such verbal clarification."
II. PAYMENT FOR SERVICES:
Payment is to be made in arrears by certified invoice. Failure to provide purchase order number on the invoice may result in the return of the invoice.