Z1DA--603-24-902 Asbestos Abatement Federal contract opportunity
Solicitation number
36C24924R0023
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9

About this file

This federal solicitation requests proposals for asbestos abatement and demolition services at the Robley Rex VA Medical Center in Louisville, Kentucky. The contractor shall provide all labor, supervision, tools and materials to abate asbestos and demolish specified areas containing lab countertops, sinks, floor tile, walls and casework. The work must be completed within 21 calendar days of receiving the notice to proceed. This is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. Proposals are due by January 8, 2024 and the contract will be awarded using lowest price technically acceptable procedures. The solicitation includes requirements for past performance references, safety records, key personnel qualifications and descriptions of technical approaches.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (

Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24924R0023 X 603-24-2-2310-0001 603-24-902 90C Department of Veterans Affairs Network Contracting Office 9 (90C) Jen Jamieson, Contract Specialist 1639 Medical Center Parkway, Suite 204 Murfreesboro TN 37129 Department of Veterans Affairs Network Contracting Office 9 (90C) Jen Jamieson, Contract Specialist email: jen.jamieson@va.gov Jen Jamieson 615-867-6000 x20202 Project 603-24-902 Asbestos Abatement at Louisville VA Medical Center, Robley Rex VAMC, in Louisville, Kentucky.

The VA Medical center has a requirement for construction services to furnish all labor, material, and supervision necessary to abate asbestos and preform noted demolition on 8W and 9S area. Contractor will provide the necessary manpower, supervision, tools, and parts to properly execute the construction of the project listed in the Statement of Work.

Magnitude of Construction: Between $100,000.00 and $250,000.00.

Type of Construction: NAICS 562910 Small Business Size - $25 Million Contract Type: Firm Fixed Price Project will be procured under FAR 15.101-2 Lowest Price Technically Acceptable.

A scheduled site visit will be held on Friday December 2023 at 11:00 AM, CST at Louisville VA Medical Center, Robley Rex VAMC. All participants attending will meet Robley Rex VAMC, 800 Zorn Ave Room B016, Louisville, Kentucky.

Please Submit any Questions/Requests for Information thru email No Later Than Friday December 2023, 1:00 PM, CST To obtain clarifications and/or additional information concerning the contract requirement, specifications, and/or drawings, submit a written Request for Information (RFI) via email to the Contracting Officer, Jeffery Ridenour at jeffery.ridenour@va.gov and Jen Jamieson, Contract Specialist at jen.jamieson@va.gov. RFI's must be specific in identifying section, paragraph and page number and must be in question format. All RFI's submitted shall include the project number and title, contractor name, city, state, telephone, email address, date submitted and RFI question(s).

Questions received after 1:00 PM, CST, December 2023 will not be answered unless it is determined to be in the best interest of the Government as deemed by the Contracting Officer. All questions must be submitted in writing only.

In accordance with P.L. 109-461, this acquisition is 100% set-aside for Service-Disabled Veteran Owned Small Business (SDVOSB) concerns. To be eligible to receive an award under this solicitation, the SDVOSB contractor must be listed and viewable in the VetCert Registry located at https://veterans.certify.sba.gov/ at the time of offers due and at time of the award. In accordance with FAR 52.204-7 System for Award Management (SAM), all prospective offerors must have an active SAM's registration at the time of offer submission.

Contractors must provide and have a current VETS 4212 Report on file with the Department of Labor in order to receive an award.

X X 52.211-10 X

1:00 PM

CST

01- -2024 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Line Item 0001: _________________________ Detailed pricing must be submitted on the attached form titled "Pricing Schedule 90C Network Contracting Office 9 Department of Veterans Affairs Network Contracting Office (90C) 1639 Medical Center Parkway Suite 204 Murfreesboro TN 37129 90C FSC e-Invoicing Payment http://www.fsc.va.gov/fsc/einvoice.asp Invoice Setup Information 1-877-489-6135 Invoice must be submitted electronically

Setup 1-877-489-6135 Jeffery Ridenour, Contracting Officer

VA-VHA-RPOC-2022-208206

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
STATEMENT OF WORK5
A.3 PRICE/COST SCHEDULE7
ITEM INFORMATION7
A.4 DELIVERY SCHEDULE7
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS8
IMPORTANT SUBMISSION INFORMATION8
EVALUATION FACTORS14
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)18
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)18
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)18
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)19
2.5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)20
2.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)21
REPRESENTATIONS AND CERTIFICATIONS22
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)22
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)26
GENERAL CONDITIONS29
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)29
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED ENTITIES (DEC 2023)29
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)30
4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2023)30
4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)33
4.6 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)38
4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)38
4.8 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)39
4.9 52.233-2 SERVICE OF PROTEST (SEP 2006)40
4.10 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)41
4.11 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)44
4.12 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)45
4.13 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)46
4.14 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)47
4.15 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)48
4.16 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)48
ATTACHMENTS50

STATEMENT OF WORK

Project: 603-24-902 Asbestos Abatement

1. SCOPE: Contractor shall furnish all labor, material, and supervision necessary to abate asbestos and preform noted demolition on 8W and 9S area.

2. QUALIFICATIONS: Asbestos contractor must have a demonstrated history of removing asbestos and meet all federal and state qualifications.

3. SERVICES TO BE PROVIDED:

A. General:

1) Contractor will provide the necessary manpower, supervision, tools, and parts to properly execute the construction of the project listed above. All containers, including toolkits, can be subject to search at any time.

2) A “Field Service Report” (FSR) must be generated, and a copy given to the Robley Rex VAMC’s Contracting Officer’s Representative (COR) or designee after the repair is completed.

3) This contract includes all planning, phasing, design, construction services, commissioning coordination and project closeout documents required to support the installation of these systems located in the Robley Rex VAMC in Louisville, Kentucky. These systems shall be complete, coordinated, and technically correct.

4) The contractor is fully responsible for researching and documenting existing conditions and will be given full access during normal business hours to equipment locations and VA drawing files.

5) Contractor shall adhere to all Department of Veterans Affairs Safety Criteria and Standards and all applicable codes (found in the technical information library at the VA website http://www.cfm.va.gov/til/index.asp), Interim Life Safety Measures (ILSMs), Infection Control Risk Assessments (ICRAs) and Pre-Construction Risk Assessments (PCRAs) measures to ensure the safety of patients, staff, and contractors.

6) The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.

7) All work shall be performed to manufacturer’s specifications as written in the manufacturer guidelines and in accordance with good industry practice.

B. Infection Control:

1) Contractor shall construct airtight polywall (at least 10mil thickness) with zipper access to each room where work is being performed, and isolate hallway adjacent to B-820 during wall removal.

2) Contractor shall install and change out at least daily or when it becomes dirty a walk-off tacky mat at entrance.

3) Contractor shall wear clean shoe covers whenever exiting the construction area.

4) Contractor shall not track any dust outside the construction area.

C. Work:

1) Demolition and abatement work will be performed during normal business hours 7:30am - 4:30pm Monday thru Friday or coordinate with COR for off-hours or Saturday-Sunday.

2) Contractor shall demo lab countertops and sinks in rooms A-937, A-939, A-949, B-802, B-808, B-817, B-818B, and B-820/B-820A. Asbestos-containing materials will be abated.

3) Contractor shall abate floor tile and mastic in hatched area as shown on drawing 603-24-902A.

4) Contractor shall fully demo Bathroom B-803A and walls, including hallway wall into B-820A as shown on drawing 603-24-902A.

5) Contractor shall abate & demo any plumbing piping wrap on plumbing fixtures found in concrete walls. Additional unforeseen related work not to exceed $5,000.

6) Contractor shall remove all built-in casework identified on drawing 603-24-901A and 603-24-902A. The contractor shall be aware when removing the bases, the floor tiles may be stuck to the bottoms. Some floors may not have tile underneath original counters.

7) Contractor shall cut and cap above floor all deactivated gas lines funning through case work. Any active vacuum / med air line shall be turned off at the zone control valve and then cut and capped above floor.

8) Contractor shall clean area of all demolished material, unwanted debris and dust at completion of demolition work.

4. SPECIAL INSTRUCTIONS:

A. Contractor Check-In: Upon arrival, the contractor will check-in with the authorized VCS attendant to receive an identification sticker, prior to performing service(s) at the Robley Rex VA Medical Center. The contractor shall wear visible identification at all times while on the premises of the Robley Rex VA Medical Center, displaying name and company ID.

B. Documentation: All SDS sheets for the materials used shall be delivered to the Maintenance Shop, Room B016.

5. PERIOD OF PERFORMANCE: 21 Calendar Days

END OF STATEMENT OF WORK

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
_____________
_____________

603-24-902 Contractor shall furnish all labor, material, and supervision necessary to abate asbestos and perform noted demolition on 8 West and 9 South area as detailed in the Scope of Work. Contractor must furnish all tools and materials (e.g. ladders, scaffolding, etc.) All work shall be performed to manufacturer's specifications as written in the manufacturer guidelines and in accordance with good industry practice.

PRINCIPAL NAICS CODE: 562910 - Remediation Services PRODUCT/SERVICE CODE: Z1DA - Maintenance of Hospitals and Infirmaries

GRAND TOTAL
______________

A.4 DELIVERY SCHEDULE

ITEM NUMBER
SHIPPING INFORMATION
QUANTITY
DELIVERY DATE
0001
SHIP TO:
Department of Veterans Affairs

Robley Rex VA Medical Center 800 Zorn Avenue Louisville, KY 40206 United States

1.00

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

IMPORTANT SUBMISSION INFORMATION

SOLICITATION MATERIALS: All solicitation materials consisting of drawings, specifications, contract forms, Amendments, and other documents will be posted to the Contract Opportunities Government website located at https://sam.gov/. Enter “36C24924R0023” into the search box to access the solicitation materials. This is the only official location where these documents can be obtained and where updates are posted. No ‘hard copy’ solicitation materials are available.

SOLICITATION SUBMISSION: The following documents must be included in the solicitation submission in the formats as stated:

- One (1) electronic copy of an original, fully completed and signed and dated SF 1442 Offer page, acknowledgment of all amendments issued by completing block 19 of the SF1442 and providing them with the SF 1442 Offer page; prices online item(s) listed on the Price/Cost Schedule; completed Representations and Certifications section (FAR 52.204-8, 52.209-5 (Deviation), and 52.209-7); and fully completed Contractor Experience Modification Rate (EMR) Certification documents.

- One (1) electronic copy of an original completed and signed SF 24 Bid Bond or other allowable Bid Security. Any missing elements of the bid bond submission could render the offeror ineligible and their offer will not be considered.

Subject: Class Deviation from the Federal Acquisition Regulation to Eliminate Hard Copy Original Documents, Signatures, Notarization, Seals on Bonds, and Other Seals for Certain Contract Requirements.

1. Purpose. To issue a class deviation in accordance with Federal Acquisition Regulation (FAR) 1.404, to allow greater flexibility by eliminating the requirement for hard copy original documents, original signatures, notarization, seals on bonds, and other scenarios confronting the acquisition workforce in connection with the Coronavirus Disease 2019 (COVID-19) pandemic.

2. FAR Parts Impacted. FAR parts 28, 32, 42, and 52.

3. Effective Date. Immediately.

4. Expiration Date. This deviation expires when incorporated into the FAR or otherwise or rescinded.

5. Applicability. This class deviation applies to all VA contracting activities.

6. Exception. None.

7. Background. The deviation is issued in response to the COVID-19 national emergency, as authorized by the Civilian Agency Acquisition Council (CAAC) letter 2020- 04, dated May 1, 2020.

a. Current FAR Policy. In certain situations, the FAR requires hard copy original documents, original signatures, notarization, and seals on bonds. Class Deviation from the FAR eliminating hard copy original documents, signatures, notarization, seals on bonds and other seals for certain contract requirements was issued and serves as consultation to agencies in accordance with FAR 1.404. Email copy will be acceptable.

b. Need for Deviation. In response to the COVID-19 national emergency, agencies are encouraged to issue FAR deviations to eliminate the requirements discussed herein.

c. New Policy. Contracting officers shall use the attached deviation FAR text as follows:

1) When obtaining financial protection against losses under contracts per FAR part 28:

· 28.101-3(c) allowing the use of electronic means is moved to an added section at 28.002 to apply the same flexibilities to all of part 28;

· 28.106-1 adding an exception to stamping a corporate seal on bonds;

· 28.106-8 allowing a signed statement by the contractor that the payment is due and owed;

· 28.203(b) not requiring the Standard Form 28 to be sworn and notarized;

· 28.203-5 allowing a written authorization of the release signed by the surety saying that it approves of such release;

· 52.228-11, Pledges of Assets (Aug 2018) (DEVIATION APR 2020), not requiring the Standard Form 28 to be sworn and notarized, in place of 52.228-11, Pledges of Assets (Aug 2018);

· 52.228-15, Performance and Payment Bonds – Construction (OCT 2010) (DEVIATION APR 2020), not requiring the seal when executing the standard forms required by the clause; and

· 52.228-16, Performance and Payment Bonds – Other than Construction (NOV 2006) (DEVIATION APR 2020), not requiring the seal when executing the standard forms required by the clause.

2) When processing assignment of claims per FAR subpart 32.8:

· 32.802(e) allowing the use of a copy of the assignment instrument; and

· 32.805(a), (b), (c), and (e) allowing the use of electronically signed documents and a copy of the assignment instrument.

3) When executing novation agreements and change-of-name agreements per FAR part 42:

· 42.1204(f) allowing the use of a copy of the documents;

· 42.1204(i) not requiring a seal on the Novation Agreement; and 42.1205(b) not requiring a seal on the Change-of-Name Agreement.

FEDERAL HOLIDAYS: Federal law (5 U.S.C. 6103) establishes the following public holidays for Federal employees: New Year’s Day, Birthday of Martin Luther King, Jr., Washington’s Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day. Please note that most Federal employees work on a Monday through Friday schedule. For these employees, when a holiday falls on a non-workday -- Saturday or Sunday -- the holiday usually is observed on Monday (if the holiday falls on Sunday) or Friday (if the holiday falls on Saturday).

All contractors are required to complete:

· VA Privacy Training for employees with access to VA computer systems or VA sensitive information.

· VA Talent Management System (TMS) training course VA10176 provides the mandatory Privacy Training requirements for any contractor with access to VA computer systems or VA sensitive information.

· VA Privacy Training for employees without access to VA computer systems or VA sensitive information.

· VA Talent Management System (TMS) training course VA20939 provides the mandatory Privacy Training requirements for any contractor without access to VA computer systems or VA sensitive information.

· Each employee self-enrolls for a profile on the VA TMS by visiting https://www.tms.va.gov/plateau/user/login.jsp. Once there, employees should follow the steps below to create a profile, launch the mandatory training, and complete the content prior to starting work at VA.

· Provide the COR with each employee’s printed certificate of completion from the TMS. This certificate displays the employee’s TMS User ID.

· Training must be completed annually throughout the performance of this contract.

THE EXCLUDED PARTIES LIST SYSTEM (EPLS): To ensure that the individuals or businesses providing services under the contract have not engaged in fraud or abuse regarding Sections 1128 and 1128A of the Social Security Act regarding federal health care programs, the contractor is required to check the Excluded Parties List System (EPLS) located at https://sam.gov for each person or business providing services under this contract. During the performance of this contract the Contractor is prohibited from using any individual or business listed on the List of Excluded Individuals/Entities.

VETS-4212 REPORTING REQUIREMENT: Contractors are required to submit a required annual Form VETS-4212, Federal Contractor Veterans' Employment Report in all cases where the contractor or subcontractor has received an award of $150,000 or more in any fiscal year. Contracting Officers are prohibited from awarding a contract to a contractor that has not submitted a required VETS-4212 Report with respect to the preceding fiscal year if the contractor was subject to the reporting requirement of 38 U.S.C. 4212(d). Submit this report as soon as possible, if not already submitted, to avoid delays in the contract award process. For more information on this requirement and/or for completing the web-based reporting form, visit the following website https://www.dol.gov/agencies/vets/programs/vets4212. See FAR provision 52.222-38, Compliance with Veterans' Employment Reporting Requirements (FEB 2016) under the Representations, Certifications and Other Statements of Offerors, and FAR clause 52.222-37, Employment Reports on Veterans (FEB 2016) under the General Conditions.

SECURITY:

It is agreed that:

1. The preliminary and final deliverables, and all associated working papers, application source code, and other material deemed relevant by VA which have been generated by the contractor in the performance of this contract, are the exclusive property of the U.S. Government and shall be submitted to the CO at the conclusion of the contract.

2. The CO will be the sole authorized official to release, verbally or in writing, any data, draft deliverables, final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract, presented to the contractor, shall be submitted to the CO for response.

3. Press releases, marketing material, or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.

4. Employees shall not be on site without appropriate badge. Employees are responsible for reporting to the Engineering office with acceptable photo ID to obtain a badge. A VA approved badge shall be worn with the identification facing forward and visible above the waist. The employees may also be subject to inspection of their personal effects when entering or leaving the facility.

5. No photography or video recording of VA premises is allowed without prior authorization.

6. VA issued keys are to remain on VA property. Keys that are checked out from the Engineering Office shall be returned each day.

7. The contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

8. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

9. VA Information Custodial Language

· Information made available to the contractor or subcontractor by VA for the performance or administration of this contract or information developed by the contractor/subcontractor in performance or administration of the contract shall be used only for those purposes and shall not be used in any other way without the prior written agreement of the VA. This clause expressly limits the contractor/subcontractor's rights to use data as described in Rights in Data - General, FAR 52.227-14(d) (1).

· VA information should not be co-mingled, if possible, with any other data on the contractors/subcontractor’s information systems or media storage systems to ensure VA requirements related to data protection and media sanitization can be met. If co-mingling must be allowed to meet the requirements of the business need, the contractor must ensure that VA’s information is returned to the VA or destroyed in accordance with VA’s sanitization requirements. VA reserves the right to conduct onsite inspections of contractor and subcontractor IT resources to ensure data security controls, separation of data and job duties, and destruction/media sanitization procedures follow VA directive requirements.

· Prior to termination or completion of this contract, contractor/subcontractor must not destroy information received from VA, or gathered/created by the contractor while performing this contract without prior written approval by the VA. Any data destruction done on behalf of VA by a contractor/subcontractor must be done in accordance with National Archives and Records Administration (NARA) requirements as outlined in VA Directive 6300, Records and Information Management and its Handbook 6300.1 Records Management Procedures, applicable VA Records Control Schedules, and VA Handbook 6500.1, Electronic Media Sanitization. Self-certification by the contractor that the data destruction requirements above have been met must be sent to the VA Contracting Officer within 30 days of termination of the contract.

· The contractor/subcontractor shall not make copies of VA information except as authorized and necessary to perform the terms of the agreement or to preserve electronic information stored on contractor/subcontractor electronic storage media for restoration in case any electronic equipment or data used by the contractor/subcontractor needs to be restored to an operating state. If copies are made for restoration purposes, after the restoration is complete, the copies must be appropriately destroyed.

E-VERIFY SYSTEM: Companies awarded a contract with the federal government shall enroll in E-Verify within 30 days of the contract award date. They shall also begin using the E-Verify system to confirm that all their new hires and their employees directly working on federal contracts are authorized to legally work in the United States. E-Verify is an Internet-based system that allows an employer, using information reported on an employee's Form I-9, to determine the eligibility of that employee to work in the United States. There is no charge to employers to use E-Verify. (FAR 52.222-54).

PRIME CONTRACTOR INFORMATION- SAFETY OR ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATING INFORMATION

All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record (using the attached EMR information/data form). The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.

All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Bidders/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Bidder/Offeror’s EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.

Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and Puerto Rico shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.

If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead and include a letter from the NCCI indicating that it has assigned Bidder/Offeror a Unity Rating of 1.0.

The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

PAYMENT FOR MATERIALS STORED OFF-SITE: The COR and the contractor/project manager (whoever will oversee submitting the invoice) shall meet and discuss the items listed on a draft copy of the invoice prior to submission to OB10. All items will be approved prior to submission. It is the Contracting Officer’s discretion to pay for any stored materials. This should be discussed prior to submission of the first invoice. Contract financing is not part of this contract.

REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS)

As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts that exceed $750,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.

Each contractor whose contract award is estimated to exceed $750,000 is required to register with CPARS database at the following web address: www.cpars.csd.disa.mil. Help in registering can be obtained by contacting Customer Support Desk at 207-438-1690. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor's registered representative.

For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor's performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor's designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.

Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government's evaluation being placed on file in the database with a statement that the “contractor failed to respond.”

END OF SUBMISSION INFORMATION

EVALUATION FACTORS

603-24-902 - Asbestos Abatement (Robley Rex)

This section describes the evaluation process, proposal preparation, the significant factors and sub-factors and criteria to be used in the evaluation process. This procurement action is a Lowest Price Technically Acceptable source selection process in accordance with FAR 15.101-2. Proposals will be evaluated for acceptability, but not ranked using the non-price factors/sub-factors. In order to be considered for award, an offeror must have an “acceptable” rating in every non-price factor/sub-factor under consideration.

The Government intends to award a single contract to a qualified Service-Disabled Veteran Owned Small Business (SDVOSB) determined responsible in accordance with the Federal Acquisition Regulation (FAR), whose proposal conforms to all the requirements in this solicitation and is further determined to meet or exceed the standards of acceptability at the lowest offered price. The Government intends to evaluate proposals and award a contract without discussions with Offerors. Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from both a technical and cost standpoint.

The evaluation of offers submitted in response to this Request for Proposal (RFP) solicitation will be conducted utilizing the Lowest Price Technically Acceptable (LPTA) selection process. Utilization of this source selection process may result in not all offers being evaluated. The Contracting Officer upon receipt of offers, will determine eligibility and compliance to the solicitation requirements. The Vendor Information Pages (VetCert registry) will be checked to ensure that any offeror submitting a proposal to perform the work is both listed and verified. All proposals received will also be checked for an active registration in the System for Award Management (SAM). Thereafter, the Contracting Officer will review all proposals to ensure that the minimum proposal submission requirements have been met. Once these requirements have been satisfied, the Contracting Officer will select and submit for review to the Technical Evaluation Board (TEB) the technical proposal of the lowest priced offeror for consideration. Initially, the TEB will not receive any pricing information, only the technical portion of the offeror’s proposal. The offeror’s proposal will be rated against each evaluation factor as set forth in this solicitation.

If the selected offeror’s proposal is determined to be acceptable based on the standards of acceptability, and that offeror’s price is the lowest of all offers submitted, then no further evaluation of offers shall occur, and the Contracting Officer will document these findings and proceed with the responsibility determination of the offeror. Pricing information will only be provided to the TEB upon notification to the Contracting Officer that the technical proposal as submitted meets or exceeds the acceptability standard necessary to fulfill the objective of the requirement.

Should the initial offeror’s proposal be determined to be unacceptable according to the standards of acceptability, then the TEB will be required to provide to the Contracting Officer a summary evaluation sheet that documents how the offeror’s proposal fails to meet the standards of acceptability, and request to the Contracting Officer that another selection be made for consideration of award. This process shall continue until such time that an award is made.

Offerors shall respond in writing to the evaluation factors listed below, in the same order as they appear in this solicitation document. Failure to provide all information will adversely affect the evaluation of an offer. The information contained in the technical proposal should be complete, concise, and address each factor. If information is applicable to more than one evaluation factor, it must be repeated for each factor, unless stated otherwise.

Proposals are to be submitted via email to the Contracting Officer, Jeffery Ridenour and Contract Specialist, Jen Jamieson. Offerors shall submit one (1) electronic copy of complete proposal (a. Technical & b. Price) to the email provided below.

EMAIL: jeffery.ridenour@va.gov and jen.jamieson@va.gov

FAR 52.209-7 Information regarding responsibility Matters (b) shall be marked. If not marked, the proposal is technically unacceptable and cannot be considered for award.

Technical and Price sections of an Offeror’s proposal will be evaluated independently. Offeror shall separately bind each section. All pages containing text shall be consecutively numbered, type-written on 8-1/2x11 inch paper with margins of at least once inch and created using a Times New Roman 12-point font. The submitted package should contain two (2) sections, separately bind: a.) Technical Proposal b.) Price Proposal. The Offeror’s Technical proposal shall be no more than 50 pages’ total, which is not inclusive of the solicitation and any amendments issued thereof. The Offeror’s Price Proposal shall be no more than 25 pages inclusive of the bid bonds required. The Offeror is hereby advised that the attached “Pricing Schedule” worksheet shall be considered as 20 pages, regardless of the overall total. Each section must therefore be labeled with the following:

1. Construction Company Name

2. Physical Address of the Company

3. Telephone Number

4. Email address

5. VA Project Number (Project 603-24-902)

6. VA Project Name (Asbestos Abatement (Robley Rex))

7. Solicitation number (36C24924R0023) The Technical Evaluation Board (TEB) shall evaluate the offeror’s proposal against all non-price factors/sub-factors using “ACCEPTABLE” or “UNACCEPTABLE” ratings based upon the standard of acceptability that follows each factor/sub-factor below. In order to obtain an “ACCEPTABLE” rating, an offeror must meet the standard of acceptability that is listed for each factor/sub-factor.

The evaluation process and criteria stated in this section will be strictly adhered to. Evaluators will make no assumptions regarding an offeror’s proposal. Therefore, an Offeror must demonstrate understanding by the thoroughness, soundness, comprehensiveness and price reasonableness of technical approach. There will be no public opening of offers.

The following evaluation factors and sub-factors will apply to this procurement:

FACTOR 1 – Hospital/Healthcare Construction Management The offeror shall provide a narrative that describes the Offeror’s overall organization, organizational chart, as well as number of personnel and the duties of proposed technical staff to determine if offeror can manage multi-discipline projects without significant difficulty. The proposal narrative must adequately address functions, responsibilities and authorities for performing such duties as overall project management, site superintendence, quality control, safety, administration and in-house trade capabilities.

Sub-Factor 1a – Relevant Experience: The Prime Contractor shall provide demonstrated satisfactory experience in new construction, renovation, or the addition of a hospital/medical center and/or health care facility for two (2) completed projects within the past five (5) years with a contract value equal to or greater than $250,000.00. The subject project must have consisted of multiple trades to demonstrate the management and coordination of trades by the Prime Contractor.

Standard for Acceptability: The Prime Contractor shall provide project title, location, start and completion dates, contract price, along with a written narrative of the scope of work that clearly demonstrates new construction, renovation or the addition of a hospital/medical center and/or health care facility. Prime Contractor must show experience in performing this type of requirement for two (2) completed projects within the past five (5) years with a contract value equal to or greater than $250,000.00.

Sub-Factor 1b - Key Personnel: Provide the names of the Prime Contractor’s project manager and on-site superintendent, including name with title, years with prime contractor, and total work experience as it relates to the new construction or the addition of a hospital/medical center and/or health care facility. Both Project Manager and Site Superintendent must demonstrate (by way of professional resume) experience in managing and providing oversight with new hospital construction or construction additions with a project magnitude equal to or greater than $250,000.00 or more over the past five (5) years.

Standard for Acceptability: Project Manager and the on-site superintendent must have a minimum of five (5) or more years of experience in managing new hospital construction, renovations, and/or constriction additions in a hospital or medical center environment.

FACTOR 2 - Technical Management Approach: The offeror shall provide a narrative that outlines the proposed technical approach for this project, including assumptions and rationale for choosing the preferred approach.

Sub-Factor 2a-Project & Construction Quality Control: Include a discussion of how the duration of project time was achieved; provide a Gantt chart of contract times broken into schedule of values by trade discipline and by General Wage Decision (formerly Davis-Bacon Act). Offeror must include identification of proposed personnel for project management, site superintendence, and quality control; including role in commissioning, safety during construction, and in-house trade capabilities.

Standard for Acceptability: Gantt chart achieving successful project completion in 21 calendar days, with all requirements met for contract. Technical narrative always demonstrates sound logic with minimal disruption to medical center operations.

Sub-Factor 2b-Change Order Management: Explain methods for identifying changes along with company procedures for managing changes, regardless of unforeseen site conditions or owner-initiated changes. Methods and procedures for handling changes are to be based on your experience in hospital construction of a project of this magnitude and scope, involving multiple trades and the coordination of trades. Discuss any potential changes or unforeseen conditions that could result from this project along with how those would be handled both internally as a company and with the VA.

Standard for Acceptability: This factor will be considered acceptable if the information provided demonstrates adequate procedures for identifying and handling changes as stated above.

FACTOR 3 - Past Performance: Offeror shall list three (3) only prior clients for completed projects of new construction or new addition of hospital/healthcare facility, medical clinics where the projects dollar magnitude equal to or greater than $250,000.00 within the last five (5) years on the VA Past Performance questionnaire and ask the client to forward directly to the Contract Specialist via email at jen.jamieson@va.gov no later than 8 January 2024 at 1:00 PM CST.

Standard for Acceptability:

NOTE: The past performance evaluation results is an assessment of the Offeror’s probability of meeting the minimum past performance solicitation requirements. This assessment is based on the Offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. The government may also obtain past performance information through the Past Performance Information Retrieval System (PPIRS) other sources known to the Government.

RELEVANT:
The Government will perform an independent determination of data relevancy, provided or obtained. The main assessment of relevancy shall focus on capability and magnitude. Capability assesses whether the work being performed in the reference is like the work in the requirement. Magnitude defines whether the amount of work in the reference is like the amount of work that is to be performed in the requirement.
RECENT:
Recent past performance shall be defined as successful performance under contracts similar in scope to the subject requirement completed within the last five (5) years through proposal due date

Price: The offeror shall provide pricing for the stated offer item. The Government will evaluate offers for award purposes.

The price proposal must include the Construction Pricing Schedule, the signed SF 1442, with acknowledgment of any amendments, plus the Offeror’s Bid Guarantee documents.

END OF EVALUATION FACTORS

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
11.2 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects.