This document contains an amendment to a solicitation for replacing an emergency generator and electrical distribution system at Building 162 for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9.
The amendment provides additional questions and answers received from offerors. Key details include that the hour and date for bid submission is not extended. The VA will provide a staging and parking area for the contractor to prepare and secure, but storage of materials is the contractor's responsibility. Dumpsters, dust chutes, excavation safeguards, and disposal of demolition materials are also the contractor's responsibility. Clean-up during and after construction is the responsibility of the contractor. Air permits must be filed by the contractor with the appropriate state regulatory agency. All demolition and construction work, including concrete work, is the responsibility of the contractor. Clarification is provided on conduit and wiring removal and temporary power requirements during construction. Contractor must determine best method for existing generator removal. Safety barriers are the contractor's responsibility to install and maintain.
The solicitation number, agency, and opportunity type are provided for reference.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24923B0010 0004.docx | DOCX document | |
| 36C24923B0010 0003.docx | DOCX document | |
| 621-22-137 Replace Bldg 162 Emergency Generator Pre-Bid Sign In Sheet.pdf | ||
| 36C24923B0010 0001.docx | DOCX document | |
| WD TN20230191 Washington County 01062023.pdf | ||
| 621-22-137 Replace Bldg 162 Emergency Generator Specs.pdf | ||
| 621-22-137 Replace Bldg 162 Emergency Generator Drawings.pdf | ||
| 36C24923B0010_1.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 621-23-3-5615-0007 621-22-137 90C Department of Veterans Affairs Network Contracting Office 9 (90C)
NCO 9
1639 Medical Center Parkway, Suite 400 Murfreesboro TN 37129 90C Network Contracting Office 9 Department of Veterans Affairs Network Contracting Office (90C) 1639 Medical Center Parkway Suite 400 Murfreesboro TN 37129 To all Offerors/Bidders
36C24923B0010 04-17-2023
X x x
** HOUR & DATE for Bids is NOT extended
621-3630162-5615-854200-3220 23NR2JA35
x The purpose of this amendment is to provide additional Questions (RFIs) and Answers received.
Jeannette Morphew Contracting Officer 621-22-137 Replace Bldg 162 Emergency Generator
Additional RFIS and Answers
Would you please consider an extension in order to allow manufacturers to provide quotes and allow questions to be answered?
There will not be an extension at this time, as quotes from the manufacturer could have already begun with the information from the SOW. Original RFIs (questions) were received and answered 4 May 2023 in Amendment 1 posted in SAM.
· Will we be provided site storage, staging and parking area be available during construction time at no cost?
· A staging and parking area can be provided with the responsibility of the contractor to prep the area (i.e. gravel, fencing) and secure it. Storage is the responsibility of the contractor as well. The VA does not pay for stored materials.
· Will we be provided trash dumpers at site?
· Dumpsters are the responsibility of the contractor and must be stored within the fenced in staging area.
· Will we be provided enclosed dust chutes with control gates from floor to carry debris to truck?
· The contractor is required to supply all equipment and materials to complete the work required for this project.
· Will we be provided safeguards for use during demolition, removal operations and around exposed excavations?
· The contractor is required to supply all safeguards for safely completing the scope of work for this project.
· Will we be provided disposal of all materials, other than earth to remain, from trash dumps?
· The contractor is responsible for the disposal of all materials generated during demolition and construction.
· Will a clean-up crew be created?
· Clean-up is the responsibility of the contractor, not the VA.
· Air Permit with TDEC will be needed?
· The contractor is required to file the air permit with TDEC.
· Demo of existing and New equipment pads for electrical equipment will be done by us?
· All demolition is the responsibility of the contractor.
· Any other concrete work in site for electrical equipment will be done by us?
· All concrete work required for the installation of the equipment for this project is the responsibility of the contractor, including any concrete damaged due to construction equipment operated by the contractor.
For Engineering
· Plan E-601
· Existing 5 sets of 4#500 - 3-1/2"C from existing transformer, generator and from ATS to both Main and Main Emergency Distribution Panelboards are in a hatched area to be demolished. Is it acceptable for the underground conduits to just cut and abandon/cap?
· All conduit and wiring is to be removed unless it can be reused for the new installation.
· As demolition plan ask for the removal of all Primary/Emergency power supply as well as the whole Service Entrance gear and Specs call for Temporary power supply as well, would you please provide an schedule/phasing of how this process is planned? Please clarify.
· It is the responsibility of the contractor to phase the construction to maintain the operation of the facility throughout the construction.
· Plan E-602
· Deductive alternate asks for reduction of capacity for all new electrical equipment but not for feeders/sub-feeders. Should we keep the same wires/conduits a for the Main Bid or recalculate them for Alternate conditions?
· Conductor size can be reduced based on the reduced capacity generator for the deductive alternate.
· New generator auxiliary panel is represented in One Line diagram as a separate panel but it could be internal to the generator enclosure. Please confirm which one will be?
· The auxiliary panel can be internal to the generator as long as the panel can also be used to supply electrical loads outside of the generator enclosure, such as receptacles or lighting in the generator docking station.
· New Emergency is located at the Generator Enclosure on this plan but on EP101 is represented in both inside and outside walls of electrical room. Are the (3) stops needed? Please clarify.
· There is an e-stop on the generator, an e-stop in the electric room and an additional one on the exterior to the building which is for the local fire department to shut down the generator if needed since they do not have access to the electric room or generator enclosure.
· Plan ED101, from scaled plan is not clear if there is enough space to move the existing generator out of the room. Please clarify.
· The existing generator is capable of being removed through the existing louvres, either whole or in pieces. It is the contractors responsibility to determine the best method of generator removal without damaging the structure.
· Besides that, safety barriers outside the room will be demolished and put in place again by General Contractor? Please confirm.
· Any safety barriers are the responsibility of the contractor to install and maintain throughout the construction.