This document contains questions and answers related to a solicitation for sitework and accessibility improvements at a Veterans Affairs medical center. The solicitation seeks a contractor to perform work including installing new storm lines, sidewalks, site grading, erosion control, paving, and truncated domes. Questions addressed include the need for confined space entry permits, potential conflicts with existing infrastructure, clearly defining limits of work, maintaining access to buildings during construction, compaction requirements for subgrades and bases, use of prime coats, and confirming design details. The solicitation number is 36C24923B0005 and is issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9 for site improvements at their medical center. The bid opening will take place on March 8, 2023 at 2:00 PM Central Time via Microsoft Teams.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised drawings.pdf | ||
| Header - List of Attachments.txt | TXT text file | |
| 36C24923B0005 0004.docx | DOCX document | |
| 36C24923B0005 0003.docx | DOCX document | |
| 36C24923B0005 0002.docx | DOCX document | |
| 36C24923B0005_1.pdf | ||
| 626A4-21-501 Combined Specs Sitework and Acc.pdf | ||
| 626A4-21-501 Sitework and Acc Signed Drawings.pdf | ||
| WD TN20230147 01062023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 626-23-1-4209-0011 626A4-21-501 90C Department of Veterans Affairs Network Contracting Office 9 (90C)
NCO 9
1639 Medical Center Parkway, Suite 400 Murfreesboro TN 37129 90C Network Contracting Office 9 Department of Veterans Affairs Network Contracting Office (90C) 1639 Medical Center Parkway Suite 400 Murfreesboro TN 37129 To all Offerors/Bidders
36C24923B0005 01-31-2023
X x x 8 March
2023, 2PM CT
626-3630162-4209-854200-3220 23NRNR000
x The purpose of this amendment is to provide the questions and answers for this project.
The official bid opening will remain March 8, at 2:00 PM CT and will occur via Microsoft Teams meeting.
Please call 1-205-235-3524 Conf. No. 914 871 44# five minutes before the bid ope ning to be present for the bid opening.
Submit electronic copy of bids with bid bond(s) via email to jeannette.morphew@va.gov and diana.grube@va.gov
Please see enclosed RFI(s) for the below project:
Project 626A4-21-501, Title: "Sitework & Accessibility"
1. Title: Confined Space Permit Background:
C-100 Detail 3 (Location 1) Grading and Drainage Plan calls for a new storm line to be installed with a new inlet. This new piping will tie into an existing manhole.
RFI: Does the Government classify the work to be performed in the existing manhole to be permit confined space entry? The existing storm drain MH will be considered a confined space. All safety precautions will be followed. A confined space form will be filled out and turned into VA Campus Safety Dept.
2. Title: Existing Sidewalk Background: C-100 (Location 2) is adding a sidewalk from an existing sidewalk to a gravel lot.
RFI: During the site walk the Contractor noticed a PIV for a fire main in this general area. Will this existing PIV interfere with the location of the new sidewalk? The PIV will not be in the sidewalk nor moved.
3. Title: Site Control Background: C-101 It appears that the limit of work is at the apron leaving the Government property.
RFI: Where is the boundary/property line between the Government and the city/state road? Per the drawings, this line is not determined. The contractor should construct to the specific location on the drawings. The end of Southview drive, per the drawings, is in close proximity of Compton Road and all VA safety precautions will need to be followed while working in close proximity to Compton Rd.
4. Title: Site Control Background: C-101 It appears that the limit of work is at the apron leaving the Government property.
RFI: What type of barricade/traffic control will be required for this location? TDOT/ VA specified road signage for the closure at Compton/ Southview is approved. The road closure at Veterans Circle will adhere to VA AHJ (Authority having jurisdiction) per VA specs.
5. Title: Site Control Background: C-101 It appears that the limit of work is at the apron leaving the Government property.
RFI: Can the limit of work be clearly defined? The Contractor suggests a straight cut from break in curb provide this is not in the city/state right of way and existing concrete band for bollard inserts to remain in place. A Straight/ perpendicular line will be directed at the end of the VA’s curb/gutter. This is located approx. 4’ south of the VA’s brick columns.
6. Title: Access to Parking Lot Background: G-001 Location 3 appears to be the only access to parking lot of the Fisher Building.
RFI: Will access need to be maintained to the Fisher Building during construction? Yes.
7. Title: Access to Parking Lot Background: G-001 Location 3 appears to be the only access to parking lot of the Fisher Building.
RFI: If access is required to stay open, will the project need to be phased or will this work need to be performed on the weekend? The contractor is required to plan out construction in a manner to keep at least one access to the Fisher House. Signage to the Fisher House will be required. Temporary surfaces are approved during this time (gravel) but must be easily passable by small passenger cars.
8. Title: Paving Background: CS-501 Detail 12/CS-501 shows a paving section. The bottom note calls for TDOT Section 230 Improved Roadbed (100% Standard Density). This is an existing road bed and may not be at 100% Standard Density.
RFI: How does the Government want the Contractor to test the Density? By compacting the existing soil to designed density per VA specifications. “THE SUBGRADE TO REMAIN SHALL BE COMPACTED TO 98% STANDARD PROCTOR MAXIMUM DRY DENSITY” Note 9, sheet C-100.
9. Title: Paving Background: CS-501 Detail 12/CS-501 shows a paving section. The bottom note calls for TDOT Section 230 Improved Roadbed (100% Standard Density). This is an existing roadbed and may not be at 100% Standard Density.
RFI: If the existing roadbed is not 100% Standard Density would this be an unforeseen site condition? The parent material (existing roadbed) is to be compacted to meet designed compaction strength.
The contractor will place in the Base Bid- 50 Cubic Yards of excavation of unsuitable material and also the replacement of Engineered approved compacted backfill of 50 cubic yards (with 3” minus).
10. Title: Paving Background: CS-501 Detail 12/CS-501 shows a paving section. The bottom note calls for TDOT Section 230 Improved Roadbed (100% Standard Density). This is an existing roadbed and may not be at 100% Standard Density.
RFI: Would a proof roll of the existing subbase prior to placement of TDOT section 903.05 Crushed Aggregate Base an acceptable solution for the government? The existing material may/ will require compaction methods (roller) to meet designed density as it may not meet density without rolling.
11. Title: Paving Background: CS-501 Detail 12/CS-501 shows a paving section. The bottom note calls for TDOT Section 230 Improved Roadbed (100% Standard Density). This is an existing roadbed and may not be at 100% Standard Density.
RFI: Would the government accept Aggregate base be 95% standard proctor as an acceptable solution? Testing is by specification and performed by third party.
12. Title: Prime Coat Background: CS-501 Detail 12/CS-501 calls for TDOT Section 401-A Bituminous prime coat between the crushed aggregate base and binder course.
RFI: Can this prime coat be deleted from the project? The Prime coat will not be deleted and is required.
13. Title: Concrete Paving Background: SC-501 Detail 1 for heavy Duty Concrete Paving. Detail 1/SC501 calls for existing sub grade or structural fill shall be compacted to 98% Standard Proctor.... Proof rolling shall be performed and approved by an independent testing agency. The next lift is 4” min of TDOT Section dense graded aggregate base (100% Modified Density). We believe this to be an error in the drawings, 100% of modified proctor would be very difficult (almost impossible) on top of 98% standard proctor soils. Even 100% standard proctor on top of 98% standard proctor would be very difficult. The existing subgrade would have to be compacted similar to the stone placed over the existing subgrade in order to achieve the 100% of modified proctor. We do not see the value to the Government to generate an RFP to remove the existing subgrade and install new fill to replace the subgrade using a 100% modified proctor. Two different compaction efforts. The modified effort Proctor is 5 lifts and 56 blows per lift with a 10 lbs. hammer verses a Standard Proctor is 3 lifts and 56 blows per lift with a 5.5 lb. hammer. Big difference and amounts to a higher dry density of 4 to 5 PCF.
RFI: Is it acceptable to the government to change the verbiage on the note from 100% modified density to 90%-95% Standard Proctor? This would be more in line with the 32 20 11 Earthwork spec 3.3. Filling and Backfilling? Contractor is to Bid per VA specification of this project.
14. Title: Demolition Background: C-100 Demolition Notes Section 16, 18, and 19 states, RFI: For bidding purposes can the government define the scope of erosion control? Example location of silt fences, BMP’s for inlet protection, and state or local permit that is required etc.
Silt fence will be required on the down slope side of all excavation work as a standard BMP (Better Management Practice). Storm drain inlets will also be protected from soil/ silt intrusion. If silt fences fail from point load discharge of runoff water, Small rip rap check-dams will be placed at point load discharge areas (grass areas) on the jobsite to dissipate the runoff energy. All BMPs are to be monitored during construction and maintained (weekly or after each rain event). All BMPs are to be removed at the end of the job, when the soils are stabilized, and all damage will be returned to an as good or better condition of the existing condition prior to construction (with normal methods- leveling, topsoil where needed, seed, straw mulch, etc.. as needed)
15. Title: Truncated Domes Background: CS 501 detail 6 calls for truncated domes.
RFI: What color are the truncated domes? Match existing campus standard (clay/ red color)
16: Title: Missing designation Background: The concrete below does not have a note designation. Sheet C-100 Detail 2 RFI: Please confirm what note designation the small piece of concrete below is to receive.
This is to be “normal duty concrete pavement” note 2, to protect the storm drain cover/ PR grate inlet and shall be poured at a the FFE of the Top of manhole/ inlet casting and to the same integrity of a standard sidewalk. See location 1, note 3 on sheet C-100 for reference. This concrete feature will slope to drain.
17. The paving spec shown only shows 3” of rock, which is abnormal for any time of paved surface. Can you please confirm this is accurate?
Accurate. 3” is the measurement on the contract documents.
18. With the paving spec shown there will be no rock under the curb due to the depth of stone and asphalt. The civil details show stone under the curb. Is stone required under the curb?
Stone will be required under the curb.
19. I took a look at the paving details and it looks as though the measurement is incorrect. If you compare the 3" aggregate base to the 2" binder, it seems closer to 6" aggregate base.
What are your thoughts?
It does appear to be “not to scale”. 3” crushed aggregate base stone is correct.
Also, the bituminous wear surface is not clarified per the detail. Wear Surface to conform to TDOT Section 903.11 Bituminous Wear Layer 411-D.
image4.png image1.png image2.png image3.png