36C24919Q0035-006.docx
DOCX document 34 KB Posted
- Attached to
- Municipal Solid Waste and Recycling for TVHS Federal contract opportunity
- Solicitation number
- 36C24919Q0035
About this file
36C24919Q0035 Attachment B QASP MSW and Recycling.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24919C0055_1.docx | DOCX document | |
| 36C24919Q0035-007.docx | DOCX document | |
| 36C24919Q0035-004.docx | DOCX document | |
| 36C24919Q0035-005.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MUNICIPAL SOLID WASTE & RECYCLING SERVICES
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
For: (3/12) locations:
Solid Waste and recycling removal is required at the following sites:
| a. |
| Alvin C. York VA Medical Center |
3400 Lebanon Pike Murfreesboro, TN 37129
| b. |
| Nashville Campus |
1310 24th Avenue South Nashville, TN 37212
| c. |
| Chattanooga VA Outpatient Clinic |
6098 Debra Rd Suite 5200, Bldg 6200 Chattanooga, Tennessee 37411
Recycling plans, concepts and education shall be developed for the following sites:
| a. |
| Alvin C. York VA Medical Center |
3400 Lebanon Pike Murfreesboro, TN 37129
| b. |
| Nashville Campus |
1310 24th Avenue South Nashville, TN 37212
| c. |
| Chattanooga VA Outpatient Clinic |
6098 Debra Rd Suite 5200, Bldg 6200 Chattanooga, Tennessee 37411
| d. |
| Clarksville Outpatient Clinic |
1832 Memorial Street Clarksville, Tennessee 37043
| e. |
| Charlotte Avenue Clinic |
1919 Charlotte Avenue Nashville, TN 37203
| f. |
| Women Veterans Healthcare Center |
1919 Charlotte Avenue Suite 300 Nashville, TN 37203
| g. |
| Athens Outpatient Clinic |
1320 Decatur Pike Athens, TN 37303
| h. |
| Tullahoma Outpatient Clinic |
225 Von Karman Road Arnold Air Force Base, TN 37389
| i. |
| Clarksville Dental Clinic |
2291 Dalton Drive Suite F Clarksville, TN 37043
| j. |
| Compensation and Pension Clinic |
2 International Plaza Nashville, TN 37217
| k. |
| International Plaza VA Clinic |
2 International Plaza Suite 300 Nashville, TN 37217
| l. |
| Pointe Center VA Clinic |
1208 Pointe Center Drive Suite 100 Chattanooga, TN 37421
Contract Number: Provided Upon Award
Contract Description: Complete management of Tennessee Valley Healthcare’s (TVHS) municipal solid waste & recycling program.
Contractor’s name: Provided Upon Award
1. PURPOSE
This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
· What will be monitored.
· How monitoring will take place.
· Who will conduct the monitoring.
· How monitoring efforts and results will be documented.
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance.
This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the Government shall coordinate changes with the contractor. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
2. GOVERNMENT ROLES AND RESPONSIBILITIES
The following personnel shall oversee and coordinate surveillance activities.
a. Contracting Officer (CO) - The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
Assigned CO: Tara R. Hammrich Organization or Agency: Department of Veterans Affairs, NCO9
b. Contracting Officer’s Representative (COR) - The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR shall keep a quality assurance file. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. Additionally, an Alternate COR (ACOR) may be appointed.
a. Assigned COR: Erin Dickey, Administrative Officer, EMS
b. Assigned ACOR: Gary S. McCarthy, Jr., Chief, EMS
c. Assigned ACOR: Sean Stephens, Asst. Chief, EMS
c. Other Key Government Personnel - <Upon award, Government will enter name, if applicable. This may include Performance Monitors, Clinical Quality experts, etc. who may act on behalf of the COR to monitor performance.>
3. CONTRACTOR REPRESENTATIVES
The following employees of the contractor serve as the contractor’s program manager for this contract.
a. Program Manager: Completed upon award
b. Other Contractor Personnel: Completed upon award
4. PERFORMANCE STANDARDS
Performance standards define desired services. The Government performs surveillance to determine if the contractor exceeds, meets or does not meet these standards.
| Required Service |
| Performance Standard |
| Method of Surveillance |
| Incentive/ Disincentive |
| Completion of container change out in a timely manner. |
| Within 2 working days from the day of initial application. 95% completed on time. |
| Observation and random inspection (auditing). |
| Deficiencies noted in quarterly performance evaluations, and notes made in CPARS. |
| Contractor is found not to be routinely placing recyclable materials into a landfill or other inappropriate location |
| As required No more than 2 instances within a 12 month period (over entire contract performance period) |
| Periodic Inspections/Observation |
| Deficiencies noted in quarterly performance evaluations, and notes made in CPARS. |
| Compactors and all equipment is repaired within 72 hours of notification or a plan is prepared for those requests not resolved within 24 hours |
| Review as needed 95% completed on time. |
| Random inspection (auditing)/Observation |
| Deficiencies noted in quarterly performance evaluations, and notes made in CPARS. |
| Contractor sends checks for credit amounts to TVHS within 30 days of processing materials |
| No more than 1 failure annually |
| Observation |
| Deficiencies noted in quarterly performance evaluations, and notes made in CPARS. |
| Provide required training in a timely manner. |
| Review as needed 95% completed on time. |
| Observation and auditing. |
| Deficiencies noted in quarterly performance evaluations, and notes made in CPARS. |
| Provide accurate documentation in a timely manner using approved forms. |
| As required 95% completed on time. |
| Observation and random inspection (auditing). |
| Deficiencies noted in quarterly performance evaluations, and notes made in CPARS. |
| Ensure billing is completed in a timely manner. |
| Audit Monthly 95% completed on time. |
| Observation and random inspection (auditing). |
| Deficiencies noted in quarterly performance evaluations, and notes made in CPARS. |
| At contract expiration or termination, Contractor coordinates with TVHS and incoming Contractor to ensure smooth transition of equipment and services and there are no risks to public health or safety of persons |
| Review as needed 100% completed |
| Observation |
| Deficiencies noted in quarterly performance evaluations, and notes made in CPARS. |
5. INCENTIVES
Incentives shall be based on exceeding, meeting, or not meeting performance standards. If applicable, the Government shall use “Potential Exercise of Option Period” as an incentive.
6. METHODS OF QA SURVEILLANCE
The COR shall use the surveillance methods listed below in the administration of this QASP.
a. DIRECT OBSERVATION: 100% surveillance/Inspection
b. PERIODIC INSPECTION: Inspections will be scheduled Daily, Weekly, Monthly, Quarterly, annually and unscheduled, as needed.
c. USER SURVEY: Customer complaints and random sampling. Random survey is conducted to solicit user satisfaction.
d. VALIDATED USER/CUSTOMER COMPLAINTS: Complaints are investigated and validated.
e. PROGESS/STATUS MEETINGS: Quarterly
7. DOCUMENTING PERFORMANCE
a. ACCEPTABLE PERFORMANCE:
The Government shall document positive performance. Any report may become a part of the supporting documentation for any contractual action.
b. UNACCEPTABLE PERFORMANCE:
When unacceptable performance occurs, the COR shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the COR shall document the discussion and place it in the COR file.
When the Contracting Officer (CO) determines formal written communication is required, a Contract Discrepancy Report (CDR) shall be prepared and presented to the contractor's program manager.
The contractor shall acknowledge receipt of the CDR in writing. The CDR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CDR will also state how long after receipt the contractor has to present this corrective action plan to the Contracting Officer. The Contracting Officer shall review the contractor's corrective action plan to determine acceptability.
Any CDRs may become a part of the supporting documentation for any contractual action deemed necessary by the CO.
8. FREQUENCY OF MEASUREMENT
a. Frequency of Measurement:
During contract performance, the COR will periodically analyze whether the negotiated frequency of surveillance is appropriate for the work being performed.
b. Frequency of Performance Assessment Meetings:
The COR shall meet with the contractor quarterly to assess performance and shall provide a written assessment. The written assessment will be placed in the COR file and a copy provided to the Contracting Officer.
Signature – Contractor Program Manager (contractor)